Chief Engineer (Projects)
O/o. Chief Engineer (Projects),4th Floor, A Block, Corporate Office, TGSPDCL, Mint Compound, Hyderabad
Conversion of existing Overhead line to Underground cable in Asmangadh Division in Hyderabad South Circle of GHMC area of TGSPDCL
736170
CE/PROJECTS/TGSPDCL/TGUGC/ L-ASG-20/2026-27
OPEN
Electrical Works
HYDERABAD, TELANGANA
1 document required · 1 mandatory
₹29,500
₹1.3 Cr
18 Sept 2026
18 Sept 2026
25 Sept 2026
24 Sept 2026
Supply of 33KV 3 Core 400 Sq.mm Heat Shrinkable Indoor end termination kit
Supply of 33KV 3 Core 400 Sq.mm Heat Shrinkable Outdoor end termination kit
Supply of 33KV 3 Core 400 Sq.mm Heat Shrinkable Straight Through Jointing Kits
Supply of 11KV 3 Core 400 Sq.mm Heat Shrinkable Indoor end termination kit
Supply of 11KV 3 Core 400 Sq.mm Heat Shrinkable Outdoor end termination kit
Supply of 11KV 3 Core 400 Sq.mm Heat Shrinkable Straight Through Jointing Kits
Supply of 11KV 3 Core 300 Sq.mm Heat Shrinkable Indoor end termination kit
Supply of 11KV 3 Core 300 Sq.mm Heat Shrinkable Outdoor end termination kit
Supply of 11KV 3 Core 300 Sq.mm Heat Shrinkable Straight Through Jointing Kits
Supply of 11KV 3 Core 185 Sq.mm Heat Shrinkable Indoor end termination kit
Supply of 11KV 3 Core 185 Sq.mm Heat Shrinkable Outdoor end termination kit
Supply of 11KV 3 Core 185 Sq.mm Heat Shrinkable Straight Through Jointing Kits
Supply of 11KV 3 Core 95 Sq.mm Heat Shrinkable Indoor end termination kit
Supply of 11KV 3 Core 95 Sq.mm Heat Shrinkable Outdoor end termination kit
Supply of 11KV 3 Core 95 Sq.mm Heat Shrinkable Straight Through Jointing Kits
Supply of LT 3.5 Core 240 Sq.mm Heat Shrinkable Out Door end termination kit
Supply of LT 3.5 Core 240 Sq.mm Heat Shrinkable Straight Through Joint kits
Supply of LT 3.5 Core 185 Sq.mm Heat Shrinkable Outdoor end termination kit
Supply of LT 3.5 Core 185 Sq.mm Heat Shrinkable Straight Through Joint
Supply of 6"/8" Double Wall Corrugated HDPE pipe including one coupler with 'O' ring every 6 meters straight length
Supply of 4" Double Wall Corrugated HDPE pipe including one coupler with 'O' ring every 6 meters straight length
Supply of Hume pipe 9" size
Supply of Hume pipe 4" size
Supply & erection of RCC cable Joint markers/ Cable route markers of size 700 X 240 X 75 mm duly engraving with 5 mm thick letters , TGSPDCL 33000/11000 Cable/Cable joint fixing the 300mm below ground level and 400mm above ground level confirming to IS 5820 2001 with concreting
Supply of I hook
Supply of Suspension clamp assembly
Supply of dead end clamp assembly for AB Cable
Supply of Piercing connector suitable for 16 Sq. mm - 95 Sq. mm AB Cable - Pole mounted feeder pillar boxes
Supply of Piercing connector suitable for 16 Sq. mm - 95 Sq. mm AB Cable - Street Light Connections
Supply of Service Connection box to accommodate 15nos. Single phase connections - AB Cable
Supply of CI Earth Pipe 50mm diameter with flange on one end and length 2 meters length
Supply of GI Earth Pipe with 40 mm dia,3mm thickness with 2.0M Length
Supply of 6" B class GI pipe 150 NB GI Pipe 4.85 mm thickness, 19.2 KG/Mtr
Supply of 4" B Class GI Pipe 100 NB GI Pipe 4.50 mm thickness, 12.1 KG/Mtr
Supply of 2" B Class GI Pipe 50NB GI Pipe 3.65 mm thickness, 5.1KG/Mtr as per ISI Standard
Supply of GI flat 50x6 mm including accessories
Supply of GI flat 25x3 mm including accessories
Caution Tape with description “DANGER ⚡ TGSPDCL UG CABLE” rolls of 150mm wide x 200m long with thickness of P 100 microns (0.1mm)
GPS survey to prepare the base map of existing 33 kV, 11 kV feeders, showing location of poles, DT, other equipment & HT customers, by carrying out Ground Penetrating Radar survey of route to locate utilities like cable, pipes etc., in normal soil & hard rock and submission of drawings of proposed cable route, cable jointing locations and RMUs.
Making of 33KV 3 Core 400 Sq.mm XLPE UG Cable Outdoor/ Indoor End Termination
Making of 33KV 3 Core 400 Sq.mm XLPE UG Cable Straight through joints
Making of 11kV 3 Core 400 Sq.mm Outdoor/ Indoor end termination
Making of 11 KV 3 Core 400 Sq.mm Cable Straight through joints
Making of 11kV 3 Core 300 Sq.mm Outdoor/Indoor end termination
Making of 11 KV 3 Core 300 Sq.mm Cable Straight through joints
Making of 11kV 3 Core 185 Sq.mm Outdoor/Indoor end termination
Making of 11 KV 3 Core 185 Sq.mm Cable Straight through joints
Making of 11kV 3 Core 95 Sq.mm Outdoor/Indoor end termination
Making of 11 KV 3 Core 95 Sq.mm Cable Straight through joints
Making of LT 3.5 Core 240 Sq.mm Heat Shrinkable Out Door end termination kit
Making of LT 3.5 Core 240 Sq.mm Heat Shrinkable Straight Through Joint
Making of LT 3.5 Core 185 Sq.mm Heat Shrinkable Outdoor/Indoor end termination
Making of LT 3.5 Core 185 Sq.mm Heat Shrinkable Straight Through Joint
Running of GI earth flat of size 50X6mm from all metallic parts of channels, AB Switch, HG fuse set, DTr neutral and LT Distribution box and inter connection of earth pits etc complete
Running of GI earth flat of size 25X3mm from all metallic parts of channels, AB Switch, HG fuse set, DTR neutral and LT Distribution box and inter connection of earth pits etc complete
Providing of earthing with CI/GI Earth pipes including excavation of earth pit (0.6 x0.6x2.4Mts.) duly filling with bentonite, earth , running of earth wire etc., complete, including cost of bentonite and excluding cost of RCC collar of size 0.75M dia x 0.5 M height
Providing of RCC Collar guarding to the existing earth pits with damaged masonry including dismantling and removing of existing masonry and fixing the RCC collar of 0.60 M dia X 0.50 M height
Laying of 33 kV & 11 kV UG cable by HDD method with casing HDPE pipe of 160 mm PN4 PE 80 as per IS 4984 and carrying HDPE pipe 120 mm PN4 PE 80 as per IS 4984 (for railways and ORR crossings)
Laying of 33 kV & 11 kV UG cable by HDD (6 to 8 inch) method without HDPE pipe - Hard Soil
Laying of 33 kV & 11 kV UG cable by HDD (6 to 8 inch) method without HDPE pipe - Normal Soil
Excavation and Formation of trench for Single Cable run, with 450 mm width and 1200 mm depth from road level and cable separation with machine cut bricks horizontally for every 3 meters, providing of DWC/GI pipes wherever required depth is not acquired as per the instructions of Engineer in Charge, the prorata basis rates to be adopted for 2 feet, 3 feet depths and filling with sand 250 mm above the cable and 50mm below the cable, placing of 40mm shabad protective slabs and caution tape, back filling the trench with earth, levelling and removing the debris from the site including the cost of lead and lift etc., In Hard Gravel Soil / BC soil / Red earth / stone and earth mixed with fair boulders / Normal soil
Excavation and Formation of trench for Single Cable run, with 450 mm width and 1200 mm depth from road level and cable separation with machine cut bricks horizontally for every 3 meters, providing of DWC/GI pipes wherever required depth is not acquired as per the instructions of Engineer in Charge, the prorata basis rates to be adopted for 2 feet, 3 feet depths and filling with sand 250 mm above the cable and 50mm below the cable, placing of 40mm shabad protective slabs and caution tape, back filling the trench with earth, levelling and removing the debris from the site including the cost of lead and lift etc.,-Along the CC / BT multi layer road requiring compressor
Excavation and Formation of trench for Single Cable run, with 450 mm width and 1200 mm depth from road level and cable separation with machine cut bricks horizontally for every 3 meters, providing of DWC/GI pipes wherever required depth is not acquired as per the instructions of Engineer in Charge, the prorata basis rates to be adopted for 2 feet, 3 feet depths and filling with sand 250 mm above the cable and 50mm below the cable, placing of 40mm shabad protective slabs and caution tape, back filling the trench with earth, levelling and removing the debris from the site including the cost of lead and lift etc.,-Across the CC/ BT road crossing multi layer road requiring compressor with hume pipe (excluding the cost of Hume Pipe)
Excavation and Formation of trench for Single Cable run, with 450 mm width and 1200 mm depth from road level and cable separation with machine cut bricks horizontally for every 3 meters, providing of DWC/GI pipes wherever required depth is not acquired as per the instructions of Engineer in Charge, the prorata basis rates to be adopted for 2 feet, 3 feet depths and filling with sand 250 mm above the cable and 50mm below the cable, placing of 40mm shabad protective slabs and caution tape, back filling the trench with earth, levelling and removing the debris from the site including the cost of lead and lift etc.,-In Hard Rock (1.2x0.45x1 = 0.54 Cum)
Excavation and Formation of trench for Double Cable run, with 600 mm width and 1200 mm depth from road level and cable separation with machine cut bricks horizontally for every 3 meters, providing of DWC/GI pipes wherever required depth is not acquired as per the instructions of Engineer in Charge, the prorata basis rates to be adopted for 2 feet, 3 feet depths and filling with sand 250 mm above the cable and 50mm below the cable, placing of 40mm shabad protective slabs and caution tape, back filling the trench with earth, levelling and removing the debris from the site including the cost of lead and lift etc.,-In Hard Gravel Soil / BC soil / Red earth / stone and earth mixed with fair boulders / Normal soil
Excavation and Formation of trench for Double Cable run, with 600 mm width and 1200 mm depth from road level and cable separation with machine cut bricks horizontally for every 3 meters, providing of DWC/GI pipes wherever required depth is not acquired as per the instructions of Engineer in Charge, the prorata basis rates to be adopted for 2 feet, 3 feet depths and filling with sand 250 mm above the cable and 50mm below the cable, placing of 40mm shabad protective slabs and caution tape, back filling the trench with earth, levelling and removing the debris from the site including the cost of lead and lift etc.,-Along the CC / BT multi layer road requiring compressor
Excavation and Formation of trench for Double Cable run, with 600 mm width and 1200 mm depth from road level and cable separation with machine cut bricks horizontally for every 3 meters, providing of DWC/GI pipes wherever required depth is not acquired as per the instructions of Engineer in Charge, the prorata basis rates to be adopted for 2 feet, 3 feet depths and filling with sand 250 mm above the cable and 50mm below the cable, placing of 40mm shabad protective slabs and caution tape, back filling the trench with earth, levelling and removing the debris from the site including the cost of lead and lift etc.,-Across the CC/ BT road crossing multi layer road requiring compressor with hume pipe (excluding the cost of Hume Pipe)
Excavation and Formation of trench for Double Cable run, with 600 mm width and 1200 mm depth from road level and cable separation with machine cut bricks horizontally for every 3 meters, providing of DWC/GI pipes wherever required depth is not acquired as per the instructions of Engineer in Charge, the prorata basis rates to be adopted for 2 feet, 3 feet depths and filling with sand 250 mm above the cable and 50mm below the cable, placing of 40mm shabad protective slabs and caution tape, back filling the trench with earth, levelling and removing the debris from the site including the cost of lead and lift etc.,-In Hard Rock (1.2x0.6x1 = 0.72 Cum)
Excavation and Formation of trench for Triple Cable run, with 750 mm width and 1200 mm depth from road level and cable separation with machine cut bricks horizontally for every 3 meters, providing of DWC/GI pipes wherever required depth is not acquired as per the instructions of Engineer in Charge, the prorata basis rates to be adopted for 2 feet, 3 feet depths and filling with sand 250 mm above the cable and 50mm below the cable, placing of 40mm shabad protective slabs and caution tape, back filling the trench with earth, levelling and removing the debris from the site including the cost of lead and lift etc.-In Hard Gravel Soil / BC soil / Red earth / stone and earth mixed with fair boulders / Normal soil
Excavation and Formation of trench for Triple Cable run, with 750 mm width and 1200 mm depth from road level and cable separation with machine cut bricks horizontally for every 3 meters, providing of DWC/GI pipes wherever required depth is not acquired as per the instructions of Engineer in Charge, the prorata basis rates to be adopted for 2 feet, 3 feet depths and filling with sand 250 mm above the cable and 50mm below the cable, placing of 40mm shabad protective slabs and caution tape, back filling the trench with earth, levelling and removing the debris from the site including the cost of lead and lift etc.-Along the CC / BT multi layer road requiring compressor
Excavation and Formation of trench for Triple Cable run, with 750 mm width and 1200 mm depth from road level and cable separation with machine cut bricks horizontally for every 3 meters, providing of DWC/GI pipes wherever required depth is not acquired as per the instructions of Engineer in Charge, the prorata basis rates to be adopted for 2 feet, 3 feet depths and filling with sand 250 mm above the cable and 50mm below the cable, placing of 40mm shabad protective slabs and caution tape, back filling the trench with earth, levelling and removing the debris from the site including the cost of lead and lift etc.-Across the CC/ BT road crossing multi layer road requiring compressor with hume pipe (excluding the cost of Hume Pipe)
Excavation and Formation of trench for Triple Cable run, with 750 mm width and 1200 mm depth from road level and cable separation with machine cut bricks horizontally for every 3 meters, providing of DWC/GI pipes wherever required depth is not acquired as per the instructions of Engineer in Charge, the prorata basis rates to be adopted for 2 feet, 3 feet depths and filling with sand 250 mm above the cable and 50mm below the cable, placing of 40mm shabad protective slabs and caution tape, back filling the trench with earth, levelling and removing the debris from the site including the cost of lead and lift etc.-In Hard Rock (1.2x0.75x1 = 0.9 Cum)
Excavation and Formation of trench for Four Cable run, with 900 mm width and 1200 mm depth from road level and cable separation with machine cut bricks horizontally for every 3 meters, providing of DWC/GI pipes wherever required depth is not acquired as per the instructions of Engineer in Charge, the prorata basis rates to be adopted for 2 feet, 3 feet depths and filling with sand 250 mm above the cable and 50mm below the cable, placing of 40mm shabad protective slabs and caution tape, back filling the trench with earth, levelling and removing the debris from the site including the cost of lead and lift etc.-In Hard Gravel Soil / BC soil / Red earth / stone and earth mixed with fair boulders / Normal soil
Excavation and Formation of trench for Four Cable run, with 900 mm width and 1200 mm depth from road level and cable separation with machine cut bricks horizontally for every 3 meters, providing of DWC/GI pipes wherever required depth is not acquired as per the instructions of Engineer in Charge, the prorata basis rates to be adopted for 2 feet, 3 feet depths and filling with sand 250 mm above the cable and 50mm below the cable, placing of 40mm shabad protective slabs and caution tape, back filling the trench with earth, levelling and removing the debris from the site including the cost of lead and lift etc.-Along the CC / BT multi layer road requiring compressor
Excavation and Formation of trench for Four Cable run, with 900 mm width and 1200 mm depth from road level and cable separation with machine cut bricks horizontally for every 3 meters, providing of DWC/GI pipes wherever required depth is not acquired as per the instructions of Engineer in Charge, the prorata basis rates to be adopted for 2 feet, 3 feet depths and filling with sand 250 mm above the cable and 50mm below the cable, placing of 40mm shabad protective slabs and caution tape, back filling the trench with earth, levelling and removing the debris from the site including the cost of lead and lift etc.-Across the CC/ BT road crossing multi layer road requiring compressor with hume pipe (excluding the cost of Hume Pipe)
Excavation and Formation of trench for Four Cable run, with 900 mm width and 1200 mm depth from road level and cable separation with machine cut bricks horizontally for every 3 meters, providing of DWC/GI pipes wherever required depth is not acquired as per the instructions of Engineer in Charge, the prorata basis rates to be adopted for 2 feet, 3 feet depths and filling with sand 250 mm above the cable and 50mm below the cable, placing of 40mm shabad protective slabs and caution tape, back filling the trench with earth, levelling and removing the debris from the site including the cost of lead and lift etc.-In Hard Rock (1.2x0.9x1 = 1.08 Cum)
Excavation and Formation of trench for Five Cable run, with 1050 mm width and 1200 mm depth from road level and cable separation with machine cut bricks horizontally for every 3 meters, providing of DWC/GI pipes wherever required depth is not acquired as per the instructions of Engineer in Charge, the prorata basis rates to be adopted for 2 feet, 3 feet depths and filling with sand 250 mm above the cable and 50mm below the cable, placing of 40mm shabad protective slabs with TGSPDCL name painted and caution tape, back filling the trench with earth, levelling and removing the debris from the site including the cost of lead and lift etc.-In Hard Gravel Soil / BC soil / Red earth / stone and earth mixed with fair boulders / Normal soil
Excavation and Formation of trench for Five Cable run, with 1050 mm width and 1200 mm depth from road level and cable separation with machine cut bricks horizontally for every 3 meters, providing of DWC/GI pipes wherever required depth is not acquired as per the instructions of Engineer in Charge, the prorata basis rates to be adopted for 2 feet, 3 feet depths and filling with sand 250 mm above the cable and 50mm below the cable, placing of 40mm shabad protective slabs with TGSPDCL name painted and caution tape, back filling the trench with earth, levelling and removing the debris from the site including the cost of lead and lift etc.-Along the CC / BT multi layer road requiring compressor
Excavation and Formation of trench for Five Cable run, with 1050 mm width and 1200 mm depth from road level and cable separation with machine cut bricks horizontally for every 3 meters, providing of DWC/GI pipes wherever required depth is not acquired as per the instructions of Engineer in Charge, the prorata basis rates to be adopted for 2 feet, 3 feet depths and filling with sand 250 mm above the cable and 50mm below the cable, placing of 40mm shabad protective slabs with TGSPDCL name painted and caution tape, back filling the trench with earth, levelling and removing the debris from the site including the cost of lead and lift etc.-Across the CC/ BT road crossing multi layer road requiring compressor with hume pipe (excluding the cost of Hume Pipe)
Excavation and Formation of trench for Five Cable run, with 1050 mm width and 1200 mm depth from road level and cable separation with machine cut bricks horizontally for every 3 meters, providing of DWC/GI pipes wherever required depth is not acquired as per the instructions of Engineer in Charge, the prorata basis rates to be adopted for 2 feet, 3 feet depths and filling with sand 250 mm above the cable and 50mm below the cable, placing of 40mm shabad protective slabs with TGSPDCL name painted and caution tape, back filling the trench with earth, levelling and removing the debris from the site including the cost of lead and lift etc.-In Hard Rock (1.2x1.05x1 = 1.26 Cum)
Excavation and Formation of trench for Six Cable run, with 1200 mm width and 1200 mm depth from road level and cable separation with machine cut bricks horizontally for every 3 meters, providing of DWC/GI pipes wherever required depth is not acquired as per the instructions of Engineer in Charge, the prorata basis rates to be adopted for 2 feet, 3 feet depths and filling with sand 250 mm above the cable and 50mm below the cable, placing of 40mm shabad protective slabs and caution tape, back filling the trench with earth, levelling and removing the debris from the site including the cost of lead and lift etc.-In Hard Gravel Soil / BC soil / Red earth / stone and earth mixed with fair boulders / Normal soil
Excavation and Formation of trench for Six Cable run, with 1200 mm width and 1200 mm depth from road level and cable separation with machine cut bricks horizontally for every 3 meters, providing of DWC/GI pipes wherever required depth is not acquired as per the instructions of Engineer in Charge, the prorata basis rates to be adopted for 2 feet, 3 feet depths and filling with sand 250 mm above the cable and 50mm below the cable, placing of 40mm shabad protective slabs and caution tape, back filling the trench with earth, levelling and removing the debris from the site including the cost of lead and lift etc.-Along the CC / BT multi layer road requiring compressor
Excavation and Formation of trench for Six Cable run, with 1200 mm width and 1200 mm depth from road level and cable separation with machine cut bricks horizontally for every 3 meters, providing of DWC/GI pipes wherever required depth is not acquired as per the instructions of Engineer in Charge, the prorata basis rates to be adopted for 2 feet, 3 feet depths and filling with sand 250 mm above the cable and 50mm below the cable, placing of 40mm shabad protective slabs and caution tape, back filling the trench with earth, levelling and removing the debris from the site including the cost of lead and lift etc.-Across the CC/ BT road crossing multi layer road requiring compressor with hume pipe (excluding the cost of Hume Pipe)
Excavation and Formation of trench for Six Cable run, with 1200 mm width and 1200 mm depth from road level and cable separation with machine cut bricks horizontally for every 3 meters, providing of DWC/GI pipes wherever required depth is not acquired as per the instructions of Engineer in Charge, the prorata basis rates to be adopted for 2 feet, 3 feet depths and filling with sand 250 mm above the cable and 50mm below the cable, placing of 40mm shabad protective slabs and caution tape, back filling the trench with earth, levelling and removing the debris from the site including the cost of lead and lift etc.-In Hard Rock (1.2x1.2x1 = 1.44 Cum)
Laying of 33KV 3 Core 400 Sq.mm Cable in Excavated Trench
Laying of 11KV 3 Core 400/ 300/ 185/ 95 Sq.mm XLPE Cable in Trench
Laying of LT 3.5 Core 240 Sq.mm Cable in Excavated Trench
Laying of LT 3.5 Core 185 Sq.mm Cable in Excavated Trench
Raising of 33 kV 3 Core 400 Sq.mm XLPE Cable
Raising of cable 11 KV 3 Core 400 Sq.mm XLPE Cable
Raising of cable 11 KV 3 Core 300 Sq.mm XLPE Cable
Raising of cable 11 KV 3 Core 185 / 95 Sq.mm XLPE Cable
Raising of LT 3 1/2 Core 185/240 Sq.mm XLPE UG Cable Single Run
Raising of LT 3 1/2 Core 185/240 Sq.mm XLPE UG Cable Double Run
Transport of conductor drums, cable drums, fragile material such as kiosks, VCBs, control panels, Battery Chargers with Batteries, RMU, current transformers, boosters, lightning arrestors, insulators, transformers, meters (which are less in weight and occupy more space) (excluding of loading unloading) Upto 10 Km with Lorry for each trip
Loading of 11 kV, 33KV XLPE UG Cable for all sizes
Unloading of 11 kV, 33kV XLPE UG Cable for all sizes
Loading of LT XLPE UG Cable for all sizes
Unloading of LT XLPE UG Cable for all sizes
Loading of LT Cable /AB Cable (XLPE) Single core Drum (including Accessories) for all size
Un loading of LT Cable /AB Cable (XLPE) Single core Drum (including Accessories) for all size
Loading of 33 kV RMU
Unloading of 33 kV RMU
Loading of 11KV 3 Way RMU/Twin feeder panel
Unloading of 11KV 3 Way RMU/Twin feeder panel
Loading of 11KV 5 Way RMU
Unloading of 11KV 5 Way RMU
Loading of 11 kV 6 way RMU
Unloading of 11 kV 6 way RMU
Loading of 11 kV Compact 3 way RMU
Unloading of 11 kV Compact 3 way RMU
Construction of Plinth for 33 kV 3 way RMU(Construction of RCC plinth/foundation for outdoor type 33 kV RMU, including excavation in ordinary soil, dressing and compaction of foundation bed, providing PCC bed, reinforcement with steel bars, centering and shuttering, and laying of specified grade RCC, including provision of anchor bolts/embedded plates for mounting of RMU, cable entry and exit openings, cable trench/duct arrangement, provision for equipment earthing, grouting, plastering/finishing, curing and all other incidental works, complete in all respects as per approved drawings and specifications.)
Construction of Plinth for 11 kV 3 way RMU(Construction of RCC plinth/foundation for outdoor type 11 kV RMU, including excavation in ordinary soil, dressing and compaction of foundation bed, providing PCC bed, reinforcement with steel bars, centering and shuttering, and laying of specified grade RCC, including provision of anchor bolts/embedded plates for mounting of RMU, cable entry and exit openings, cable trench/duct arrangement, provision for equipment earthing, grouting, plastering/finishing, curing and all other incidental works, complete in all respects as per approved drawings and specifications.)
Construction of Plinth for 11 kV 5 way RMU(Construction of RCC plinth/foundation for outdoor type 11 kV RMU, including excavation in ordinary soil, dressing and compaction of foundation bed, providing PCC bed, reinforcement with steel bars, centering and shuttering, and laying of specified grade RCC, including provision of anchor bolts/embedded plates for mounting of RMU, cable entry and exit openings, cable trench/duct arrangement, provision for equipment earthing, grouting, plastering/finishing, curing and all other incidental works, complete in all respects as per approved drawings and specifications.)
Construction of plinth for 11 kV 6 way RMU(Construction of RCC plinth/foundation for outdoor type 11 kV RMU, including excavation in ordinary soil, dressing and compaction of foundation bed, providing PCC bed, reinforcement with steel bars, centering and shuttering, and laying of specified grade RCC, including provision of anchor bolts/embedded plates for mounting of RMU, cable entry and exit openings, cable trench/duct arrangement, provision for equipment earthing, grouting, plastering/finishing, curing and all other incidental works, complete in all respects as per approved drawings and specifications.)
Construction of plinth for 11 kV 3 way RMU Compact Side by Side Cabling(Construction of RCC plinth/foundation for outdoor type 11 kV RMU, including excavation in ordinary soil, dressing and compaction of foundation bed, providing PCC bed, reinforcement with steel bars, centering and shuttering, and laying of specified grade RCC, including provision of anchor bolts/embedded plates for mounting of RMU, cable entry and exit openings, cable trench/duct arrangement, provision for equipment earthing, grouting, plastering/finishing, curing and all other incidental works, complete in all respects as per approved drawings and specifications.)
Erection of 33 kV 3 way RMU(Erection, installation and commissioning of outdoor type 33 kV RMU on prepared RCC plinth, positioning, levelling and alignment of RMU, fixing and anchoring on foundation, assembly of RMU components/accessories, suitable washers, bolts & nuts etc., making necessary cable terminations and connections, connection of equipment earthing, operation and control wiring, installation of operating mechanism and accessories, tightening of all electrical and mechanical connections, testing of insulation resistance, contact resistance and other requisite tests, and commissioning of the RMU, complete in all respects as per manufacturer's recommendations, approved drawings and specifications.
Erection of 11KV 3 Way RMU (Erection, installation and commissioning of outdoor type 11 kV RMU on prepared RCC plinth, positioning, levelling and alignment of RMU, fixing and anchoring on foundation, assembly of RMU components/ accessories, suitable washers, bolts & nuts etc., making necessary cable terminations and connections, connection of equipment earthing, operation and control wiring, installation of operating mechanism and accessories, tightening of all electrical and mechanical connections, testing of insulation resistance, contact resistance and other requisite tests, and commissioning of the RMU, complete in all respects as per manufacturer's recommendations, approved drawings and specifications.
Erection of 11 kV 5 Way RMU(Erection, installation and commissioning of outdoor type 11 kV RMU on prepared RCC plinth, positioning, levelling and alignment of RMU, fixing and anchoring on foundation, assembly of RMU components/ accessories, suitable washers, bolts & nuts etc., making necessary cable terminations and connections, connection of equipment earthing, operation and control wiring, installation of operating mechanism and accessories, tightening of all electrical and mechanical connections, testing of insulation resistance, contact resistance and other requisite tests, and commissioning of the RMU, complete in all respects as per manufacturer's recommendations, approved drawings and specifications.
Erection of 11 kV 6 Way RMU(Erection, installation and commissioning of outdoor type 11 kV RMU on prepared RCC plinth, positioning, levelling and alignment of RMU, fixing and anchoring on foundation, assembly of RMU components/ accessories, suitable washers, bolts & nuts etc., making necessary cable terminations and connections, connection of equipment earthing, operation and control wiring, installation of operating mechanism and accessories, tightening of all electrical and mechanical connections, testing of insulation resistance, contact resistance and other requisite tests, and commissioning of the RMU, complete in all respects as per manufacturer's recommendations, approved drawings and specifications.
Erection of 11KV 3 Way RMU Compact Side by Side Cabling(Erection, installation and commissioning of outdoor type 11 kV RMU on prepared RCC plinth, positioning, levelling and alignment of RMU, fixing and anchoring on foundation, assembly of RMU components/ accessories, suitable washers, bolts & nuts etc., making necessary cable terminations and connections, connection of equipment earthing, operation and control wiring, installation of operating mechanism and accessories, tightening of all electrical and mechanical connections, testing of insulation resistance, contact resistance and other requisite tests, and commissioning of the RMU, complete in all respects as per manufacturer's recommendations, approved drawings and specifications.
Painting of Name on Panel including cost of paint
Supply & erection of Pole Mounted Service Distribution Box (Feeder pillar box) - UG Cable
Erection of I hook
Erection of Suspension clamp assembly
Fixing of deadend clamp assembly for AB Cable
Stringing of LT AB Cable 3x95+1X50+1x16Sq.mm
Stringing of LT AB Cable 3x70+1X50+1x16Sq.mm
Fixing of Service Connection box to accommodate 15nos. Single phase connections – AB Cable
Removing and Reconnection of LT Services
As Built CAD Drawing upon project completion (upto 10 km) with GPS coordinates
Dismantle of existing PSCC poles 11 Mtrs height
Dismantle of existing PSCC poles 9.1 Mtrs height
Dismantle of existing PSCC poles 8 Mtrs height
Dismantle of Rail pole 90 lbs
Dismantle of Rail pole 105 lbs
Dismantle of RS Joists 175 x 85 mm
Dismantle of RS Joists 150 x 150 mm
Dismantle of Spun poles 9.5 Mtrs
Dismantle of Spun poles 11 Mtrs
Dismantle of Spun poles 12.5 Mtrs / 12.9Mtrs
Dismantle of AAAC 100 Sq.mm conductor Single Circuit
Dismantle of AAAC 100 Sq.mm conductor Double Circuit
Dismantle of AAAC 55 or 34 Sq.mm Single Circuit
Dismantle of AAAC 55 Sq.mm Double Circuit
Dismantle of 34 or 55 Sq.mm (2 wire/ 3 wire)
Loading of MS Scrap/ Conductor Scrap/ Cable Scrap and other scrap materials at field location, transport and unloading at District Stores complete
Reclamation charges - Laying Plain C.C(1:3:6) nominal mix using 40 mm HBG metal including cost & conveyance of all materials mixing, curing, all labour charges etc., complete for finished item of work (M10)-trench size 0.3 height x 0.45 m width x length
Reclamation charges - Laying Plain C.C(1:3:6) nominal mix using 40 mm HBG metal including cost & conveyance of all materials mixing, curing, all labour charges etc., complete for finished item of work (M10)--trench size 0.38 height x 0.6 m width x 1762359 length
Reclamation charges - Laying Plain C.C(1:3:6) nominal mix using 40 mm HBG metal including cost & conveyance of all materials mixing, curing, all labour charges etc., complete for finished item of work (M10)--trench size 0.40 height x 0.75 m width x 223375 length
Reclamation charges - Laying Plain C.C(1:3:6) nominal mix using 40 mm HBG metal including cost & conveyance of all materials mixing, curing, all labour charges etc., complete for finished item of work (M10)--trench size 0.45 height x 0.9 m width x 74773 length
Reclamation charges - Laying Plain C.C(1:3:6) nominal mix using 40 mm HBG metal including cost & conveyance of all materials mixing, curing, all labour charges etc., complete for finished item of work (M10)--trench size 0.5 height x 1.05 m width x 3584 length
Reclamation charges - Laying Plain C.C(1:3:6) nominal mix using 40 mm HBG metal including cost & conveyance of all materials mixing, curing, all labour charges etc., complete for finished item of work (M10)--trench size 0.6 height x 1.2 m width x 17756 length
Reclamation charges - Laying Plain C.C(1:3:6) nominal mix using 40 mm HBG metal including cost & conveyance of all materials mixing, curing, all labour charges etc., complete for finished item of work (M10)--HDD pit size 0.25 height x 2 m width x 2 m length (51520 pits)
Storage @ 1%, Insurance @1% & Watch & Ward @1% on Materials supplied by TGSPDCL
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
BOQ ASG.xls
TENDER_DOCUMENT • 0.61 MB
L-ASG 20_2026-27.docx
TENDER_DOCUMENT • 5.13 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .