Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹9.9 LAccepted-Finance | L1 | Accepted-Finance QUALIFIED | |
| 2 | L2₹11.6 L+₹1.7 L (17.5%)Accepted-Finance | L2 | Accepted-Finance QUALIFIED | |
| 3 | L3₹12.3 L+₹2.4 L (23.8%)Accepted-Finance | L3 | Accepted-Finance QUALIFIED |
Tender Value
₹8 L
EMD Value
₹8,000
Closing Date
27 Mar 2025, 11:00 amClosed
SE EDC III BULANDSHAHR
SE EDC III BULANDSHAHR
RELEASE NEW CONNECTION OF DIFFERENT CATEGORY AT NIVESH MITRA AND JHATPAT PORTAL UNDER FULL DEPOSIT SCHEME UNDER EDD SHIKARPUR.
2025_PVVNL_1020330_1
83/EDC-III/B/2024-2025
Open Tender
Electrical Works
Lump-sum
90 days
BULANDSHAHR
RELEASE NEW CONNECTION OF DIFFERENT CATEGORY AT NIVESH MITRA AND JHATPAT PORTAL UNDER FULL DEPOSIT SCHEME UNDER EDD SHIKARPUR.
2 documents required · 2 mandatory
₹1,180
SE EDC III BULANDSHAHR
₹8,000
Yes
29 Mar 2025
21 Mar 2025
27 Mar 2025
21 Mar 2025
27 Mar 2025
21 Mar 2025
Amount
fo|qr forj.k [k.M&f”kdkjiqj] cqyUn”kgj ds vUrxZr fo|qr forj.k mi[k.M&izFke ,oa f}rh; f”kdkjiqj dk;Z{ks= esa iw.kZtek ;kstukUrxZr ¼>ViV@fuos”k fe= iksVZy½ ij izkIr vkosnu tSls ;Fkk vkS|ksfxd] okf.kfT;d] ykbZu f”kf¶Vax o fo|qr la;kstu o vU; la;kstu “kh?kz vfr”kh?kz fuxZRk fd;s tkus ds dk;ZA
Carriage of fallowings from ESC. BSR to pit site on kachcha pacaa road including loading and unloading chagres at both ends, rcquricd for proper completion of work, distance about to 60 Kms.
PCC Pole 8.5 mtr Long.
S.T.P.Pole 11 Mtr. Long
Carriage of All line Material from store center BSR to j.e store Sub station as ACSR Weasel conductor, ABC conductor & cable GI Wire, Earth Wire. M.S. Chanel, Angle, Stay & Earthig Rods, Barbed Wire. Disc Insulator etc.
Erection of Single pole support including complete 1 IT fittings as per RESPO manual and as per direction of Engineer in charge including the cost of labour, T&P and carrier etc. required for proper completion of work.
Erection of Double pole/Scation Pole support including complete 1 IT fittings as per RESPO manual and as per direction of Engineer in charge including the cost of labour, T&P and carrier etc. required for proper completion of work.
Grouting of Single support shall be grouted with cement, sand and birck ballast/stone ballast in including the cost of cement, sand, birck ballast/stone ballast, etc. as per actual size requirement, as per RESPO manual and as per direction of Engineer in charge including the cost of labour, T&P and carrier etc. required for proper completion of work.
Grouting of Double pole support shall be grouted with cement, sand and birck ballast/stone ballast in including the cost of cement, sand, birck ballast/stone ballast, etc. as per actual size requirement, as per RESPO manual and as per direction of Engineer in charge including the cost of labour, T&P and carrier etc. required for proper completion of work.
Carriage of All line Material from J.E store Sub station to Pit Site ACSR Weasel conductor, ABC conductor GI Wire, Earth Wire. M.S. Chanel, Angle, Stay & Earthig Rods, Barbed Wire. Disc Insulator etc.
Cutting /drilling /Welding of MS Angle iron for making guarding angle size 65x65x6/50x50x6 mm including the work of fixing the bracket on PCC/ST pole for construction of the line.
Carriage of 11 Kv CT/PT metering polemounted unit Varius ratio
Carriage and installation of 11 Kv Pilferresistant metering cubicle with out cable termination kit
Mounting of 11 KV CT/PT Unit Varius ratio
Carriage of T/F from ESC. BSR to pit site on kachcha pacaa road including loading and unloading chagres at both ends, rcquricd for proper completion of work, distance about to 60 Kms.
25 KVA T/F
63 KVA T/F
100 KVA T/F
Fixing of 11 Kv Stay rod with Stay wire in proper way with Nozelling
Grouting of 11 Kv Stay rods
Laying, sagging. Stringing and binding and jumpering of 11 Kv XLPE cable 3*70/120/185 Square MM & Outher size newly erected pole as per RESPO manual and as per direction of supervising engineer. It includes the cost of labour, T&P, carrier etc. requried for proper completion of work.
Laying, sagging. Stringing and binding and jumpering of ACSR Weisal , rabbit, dog newly erected pole as per RESPO manual and as per direction of supervising engineer. It includes the cost of labour, T&P, carrier etc. requried for proper completion of work.
ACSR weisal conductor
ACSR Rabbit/Dog conductor
ABC Cable 3*50 Square MM
ABC Cable 3*95 Square MM
Fixing of Earthing rod
Fixing of pin insulator
Fixing disc insulator
Fixing of Toff Channel
Fixing of Sub station Angle.
Mounting & Installation of T/F From D/P
25 KVA T/F
63 KVA T/F
100 KVA T/F
The folloing material is required to be supplied by the contractor.
DISTRIBUTION BOX 3 PHASE Complet
Providing & Fixing of Chemicle earthing.
Holding clamp.
11Kv Cable Jointing kit 3*70 Square mm XLPE cable
Double Pole clamp
Fuse set
F Clamp
LT Clamp
PG Clamp
J hook
Earth clamp
Stay clamp
dead & clamps
Stay insulator
Suspension clamps
LT Insulator
Bolt & nut off size.
Extra Milage charges and carriage from PCC/ST Pole & other material from each 10 Km.
Above work shall be done as per UPPCL/RESPO Rules.
A K ELECTRICAL ENG WORKS (BID ID -5082729)
Vivek Electricals (BID ID -5083709)
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .