| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.0 CrAccepted-AOC C 2 MADEL INDUSTRIAL ESTATE NEAR VIRWANI INDUSTRIAL ESTATE ROAD NO 2 GOREGAON E MUMBAI 400063 | MUMBAI | MUMBAI | MAHARASHTRA | 400063 | ₹3.0 Cr | L1 | Accepted-AOC Being L1 |
| 2 | L2₹3.0 Cr+₹9.3 L (3.14%)Rejected-Finance 1104 QUANTUM TOWER RAM BAUG LANE MALAD WEST MUMBAI MAHARASHTRA 400064 UDYAM MH 18 0008080 | MUMBAI SUBURBAN | MAHARASHTRA | 400064 | ₹3.0 Cr+₹9.3 L (3.14%) | L2 | Rejected-Finance Being L2 |
| Sl No | Description | Qty | Unit | TECHNOCRATS SECURITY SYSTEMS PVT LTD L1 | Mahendra Realtors & Infrastructure Limited L2 |
|---|---|---|---|---|---|
| 1.00 | Part A- Civil work
Dismantling doors, windows and clear storey openings (steel / wood) shutter including chowkhats, architraves, holdfasts etc. complete and stacking within 100 m lead (full windows) Of area 3.00 Sq.M and below | 10 | Nos | 291.65 ₹2,916.5 Lowest | 1,177 ₹11,770 |
| 2.00 | Dismantling Aluminium / Gypsum partitions, /panelling, doors, windows, fixed glazing and false ceiling including disposal of unserviceable surplus material and stacking of serviceable materials within 100 m lead as directed by the Engineer-in-charge. | 1,200 | SqM | 76.95 ₹92,340 Lowest | 177 ₹2,12,400 |
| 3.00 | Dismantling of existing wall panelling including laminate, plywood, frame work and others, completely including disposal of unserviceable material and stacking of serviceable materials within 150 m lead as directed by the Engineer-in-charge. Note : Removal of wooden panelling with aluminium/wooden frame of conference room and exhibition hall will measured in this item. | 250 | SqM | 76.95 ₹19,237.5 Lowest | 235 ₹58,750 |
| 4.00 | Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 100 m lead For thickness of tiles above 10 mm and up to 25 mm . Note : Bedding mortar also to be removed along with tiles. | 600 | SqM | 48.45 ₹29,070 Lowest | 235 ₹1,41,000 |
| 5.00 | Dismantling old plaster / skirting carefully , raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground within 100 m lead | 250 | SqM | 46.55 ₹11,637.5 Lowest | 177 ₹44,250 |
| 6.00 | Dismantling steel work in single sections including dismantling and stacking within 100 m lead In R.S Joists, Angles etc. | 1 | MT | 6,994.85 ₹6,994.85 Lowest | 14,708 ₹14,708 |
| 7.00 | Dismantling plain cement concrete manually / by mechanical means carefully without damaging adjacent structures including disposal of debris within 200 m lead as per direction of Engineer-in-charge | 5 | CuM | 1,200.8 ₹6,004 Lowest | 4,413 ₹22,065 |
| 8.00 | Dismantling / Removing of of MS/GI/ other material HVAC duct of various sizes (200mm to 2000 mm) alongwith fittings, supports, wrapped insulation materials including scaffolding, cutting, stacking, removing of insulated materials from duct and transporting upto 5 km lead (TVS store)and as directed by Engineer in charge. Note : 1) Insulated materials and metal duct materials will seperately dispose off/stack in TVS store. 2) Transporting upto 5 km lead (TVS store) will be paid under relevant item. | 250 | M | 251.75 ₹62,937.5 | 235 ₹58,750 Lowest |
| 9.00 | Providing and laying 3mm thick Plastic sheet of approved make over existing flooring for protection from scratches while construction including duct taping if required and as directed by Engineer in Charge. Cost shall include removal and stacking of the sheets after required time and submitting to the department. | 360 | SqM | 217.55 ₹78,318 Lowest | 265 ₹95,400 |
| 10.00Fabrication, supply and installation of wall panelling, over aluminium frame work (50/60mm x 50mm x 1.2 @ 600mm c/c including SS screws), fixing of acquostic membrane, 12mm thick cement board, 6mm thick fire rated plywood and 1.5 mm thick laminate of approved colour and shade including making groove 3mm etc all as per approved shop drawing and technical specification and as per instruction of Engineer -in Charge. Note : 1. Drawings provided by CED are conceptual drawings. Detail Shop drawings to be prepared by contractor and get concured by Architect /Engineer in charge before execution of works. 2. Acoustic membrane, Cement board, Fire rated plywood & laminates, scaffolding are included in this item rate and no extra payment for wasteage/any item. 3. Aluminium frame work will be paid in respective item. | |||||
Tender Value
₹3.2 Cr
EMD Value
₹7.6 L
Closing Date
10 Dec 2025, 3:00 pmClosed
Chief Engineer, CED
CED, BARC, Trombay, Mumbai
Composite upgradation work of Conference room, Exhibition hall and Entrance lobby of FIPLY building including Civil, Electrical, Mechanical, Audio Video, Physical protection system and miscellaneous civil works of sea side buildings, North SIte, BARC
2025_BARC_884195_1
BARC/CED/ET/50/2025-2026 Dated 03/11/2025
Open Tender
Civil Works
Item Rate
365 days
BARC, Trombay, Mumbai.
Please refer Tender documents.
8 documents required · 8 mandatory
₹0
₹7.6 L
CED, BARC, Trombay, Mumbai
26 Mar 2026
7 Nov 2025
15 Dec 2025
7 Nov 2025
10 Dec 2025
26 Nov 2025
7 Nov 2025 - 14 Nov 2025
18 Nov 2025
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Part A- Civil work
Dismantling doors, windows and clear storey openings (steel / wood) shutter including chowkhats, architraves, holdfasts etc. complete and stacking within 100 m lead (full windows) Of area 3.00 Sq.M and below | 10 | Nos | - | - |
| 2 | Dismantling Aluminium / Gypsum partitions, /panelling, doors, windows, fixed glazing and false ceiling including disposal of unserviceable surplus material and stacking of serviceable materials within 100 m lead as directed by the Engineer-in-charge. | 1,200 | SqM | - | - |
| 3 | Dismantling of existing wall panelling including laminate, plywood, frame work and others, completely including disposal of unserviceable material and stacking of serviceable materials within 150 m lead as directed by the Engineer-in-charge. Note : Removal of wooden panelling with aluminium/wooden frame of conference room and exhibition hall will measured in this item. | 250 | SqM | - | - |
| 4 | Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 100 m lead For thickness of tiles above 10 mm and up to 25 mm . Note : Bedding mortar also to be removed along with tiles. | 600 | SqM | - | - |
| 5 | Dismantling old plaster / skirting carefully , raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground within 100 m lead | 250 | SqM | - | - |
| 6 | Dismantling steel work in single sections including dismantling and stacking within 100 m lead In R.S Joists, Angles etc. | 1 | MT | - | - |
| 7 | Dismantling plain cement concrete manually / by mechanical means carefully without damaging adjacent structures including disposal of debris within 200 m lead as per direction of Engineer-in-charge | 5 | CuM | - | - |
| 8 | Dismantling / Removing of of MS/GI/ other material HVAC duct of various sizes (200mm to 2000 mm) alongwith fittings, supports, wrapped insulation materials including scaffolding, cutting, stacking, removing of insulated materials from duct and transporting upto 5 km lead (TVS store)and as directed by Engineer in charge. Note : 1) Insulated materials and metal duct materials will seperately dispose off/stack in TVS store. 2) Transporting upto 5 km lead (TVS store) will be paid under relevant item. | 250 | M | - | - |
| 9 | Providing and laying 3mm thick Plastic sheet of approved make over existing flooring for protection from scratches while construction including duct taping if required and as directed by Engineer in Charge. Cost shall include removal and stacking of the sheets after required time and submitting to the department. | 360 | SqM | - | - |
| 10Fabrication, supply and installation of wall panelling, over aluminium frame work (50/60mm x 50mm x 1.2 @ 600mm c/c including SS screws), fixing of acquostic membrane, 12mm thick cement board, 6mm thick fire rated plywood and 1.5 mm thick laminate of approved colour and shade including making groove 3mm etc all as per approved shop drawing and technical specification and as per instruction of Engineer -in Charge. Note : 1. Drawings provided by CED are conceptual drawings. Detail Shop drawings to be prepared by contractor and get concured by Architect /Engineer in charge before execution of works. 2. Acoustic membrane, Cement board, Fire rated plywood & laminates, scaffolding are included in this item rate and no extra payment for wasteage/any item. 3. Aluminium frame work will be paid in respective item. | |||||
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Tendernotice_1.pdf
PDF • 8.02 MB
Tendernotice_2.pdf
PDF • 1.59 MB
ScheduleAET50.pdf
Tender Documents • 0.36 MB
ProformaOfSchedulesET50.pdf
Tender Documents • 1.36 MB
TechnicalbidET50.xls
Tender Documents • 0.08 MB
RFIDspecification.pdf
Tender Documents • 0.82 MB
DrawingsFiplyET50.pdf
Tender Documents • 2.25 MB
ElectricalDrawingsFiplyET50.pdf
Tender Documents • 3.94 MB
ElectricalSpecification.pdf
Tender Documents • 0.68 MB
SpecificationHVAC.pdf
Tender Documents • 0.34 MB
TechnicalSpecificationsPPS.pdf
Tender Documents • 0.39 MB
BOQ_929347.xls
BOQ • 0.51 MB
Information.pdf
Tender Documents • 0.47 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .