| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹19.7 LAccepted-Finance K K M TOWER KANDHIKUPPAM POST BARGUR TALUK KRISHNAGIRI DISTRICT 635 108 | KRISHNAGIRI | TAMIL NADU | 635108 | L1 | Accepted-Finance Admitted | |
| 2 | L2₹19.8 L+₹9,579.20 (0.49%)Accepted-Finance | L2 | Accepted-Finance Admitted |
Tender Value
₹19.9 L
EMD Value
₹20,000
Closing Date
8 Dec 2022, 3:00 pmClosed
The BDO Krishnagiri
BDO Office Krishnagiri
Krishnagiri Dt Krishnagiri Block Under SFC_DP_ 2022-23 Constructions of 3m Span Culvert and Retaining Wall With Approach Pavement at KM 1_050 of Ekkalnatham road at Naralapalli Panchayat Package No KGI 14
2022_RDTN_269597_2
RocNo_58_2022_DPS NO1_20_10_2022
Open Tender
Civil Works - Others
Item Rate
90 days
Krishnagiri
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹20,000
BDO Office Krishnagiri
13 Dec 2022
2 Dec 2022
8 Dec 2022
2 Dec 2022
8 Dec 2022
2 Dec 2022
6 Dec 2022
Amount
01.Constructions of 3m Span Culvert, Retaining Wall With Approach Pavement at KM 1/050 of Ekkalnatham road H/o Naralapalli
Earth work excavation for foundation in all class of soils except hard rock requirng blasting including cost and conveyance of all etc., complete
Cement concrete 1:4:8 mix using 40mm HBG metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete
Cement concrete 1:3:6 mix using 20mm HBG metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for bed blocks
Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etcusing mild steel sheets of size 90 x 60 cm and 10 guage stiffened, welded with mild steel angles of size 25mmx25mmx3mm for boarding laid over silver oak (countrywood) scantlings of size 10cm x 6.5cm spaced of about 90cm centre to centre and supported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centre complete complying with standard specifications and as directed by departmental officers including conveyance of all materials to site and proper centering etc complete.
Footings & Retaing Wall
Deck Slab
Supplying and Fabrication and placing in position MS Steel or Ribbed tor steel for al retainfprced cement Concrete works as per the design given including cost of steel and binding wire in all floors etc., complete complying with standard specification.
Rein Forcement cement concrete 1:1.5:3 using 20mm ISS HBG metal fo all RCC items of works excluding cost of rein forcement and fabrication charges, centering and shuttering but including curing provinding fixtures like fan clamps in the RCC Floor
Cement Concrete 1:2:4 using 20mm ISS Size hand broken granite stone jelly for foundation and flooring including labour charges for mixing concrete watering and laying the concrete in layers
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
T.THIRUPATHI
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .