| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.5 CrAccepted-AOC ASANAPUDUR VILLAGE PERUMBEDU POST PONNERI 601204 | THIRUVALLUR | TAMIL NADU | 601204 | ₹2.5 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹2.6 Cr+₹7.5 L (3.01%)Rejected-AOC | ₹2.6 Cr+₹7.5 L (3.01%) | L2 | Rejected-AOC L2 |
| 3 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹2.5 Cr
EMD Value
₹2.5 L
Closing Date
10 Jan 2025, 3:00 pmClosed
Project Director
DRDA Tiruvallur
Strengthening the BT Road From S.J.Puram to Meathinapura NH205 via Srinivasapuram Km 0/0 to 3/7 at Tiruttani Block in Tiruvallur District under NABARD RIDF XXX-2024-25 PAc No.09
2024_RDTN_515787_1
DIPR/5603/Tender/2024
Open Tender
Civil Works - Roads
Item Rate
180 days
Tiruttani Block
Class III and above as per new GO
5 documents required · 5 mandatory
₹0
₹2.5 L
Yes
10 May 2025
1 Jan 2025
10 Jan 2025
1 Jan 2025
10 Jan 2025
2 Jan 2025
Amount
Strengthening of BT Road S J Puram to Medhinipuram NH205(Via Srinivasapuram) km 0/0-3/370 R-93 PUR
Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201. etc. comp.
Picking BT Surface Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material with a lift upto 3 m and lead upto 1000 m as per Technical Specification Clause 301.4
Gravel Shoulders Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS
Formation of Earthern Shoulders Using Conveyed Earth collection and supply of carted earth from the approved quarry including cost and conveyance of conveyed earth all materials to site anf labour charges , including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS
Laying of Wet Mix Macadam(WMM) Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Slow Setting Emulsion (SS-1) 7.00 Kg Applying PRIMECOAT over WBM/ WMM surface at 7.00Kg of SS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp.
Rapid Setting Emulsion (RS-1) 3.00 Kg Providing and laying Tack coat over BT surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
Rapid Setting Emulsion (RS-1) 2.50 Kg Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
Bituminous macadam 50mm Thick Providing and laying 50mm Compacted thick Bituminous macadam using 26.50-11.2mm graded metal and 0.10 cum of 13.20-2.36mm grade metal with 37.00kgs of VG30/VG40 for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 50mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP asper clause 507 of MORTH Rev-5
Providing and laying Bituminous Concrete 25/30/40mm Thick (Grade-II) Using VG30 Providing and laying Bituminous Concrete to 25/30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.3 kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5
Provision of Rumble Strips with premix Bituminous carpet Provision of 15 nos. rumble strips covered with premix bituminous carpet, 15-20mm high at centre, 250mm wide placed at 1m centre-to-centre approved locations to control speed, marked with while strips of road marking paint. Rumble Strips = 3 X 3.75 X 0.25 = 2.81
Road Marking Road Marking With Hot Applied Thermoplastic Compound With reflectorising Glass Beads on Bituminous Surface:Providing and laying of hot applied thermoplastic compound 2.50mm thick |including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5mm is exclusive of surface applied glass beads as per IRC:35, The finishedsurface to be level uniform and free from streaks and holes etc complete as per MORTH&H specification No.803
Provision for KM Stone
Provision for HM Stone
Provision for Name board /Citizen information Board
Provision for Logo board
Supply and fixing of Sign boards as per specification
RCC Slab Culvert 1.5 m span CH 0/220,0/890 2 nos
Earth work Excavation and depositing on bank with intial Lead of 10m and intial lift of 2m
Supply and filling good river sand for basement filling not more than 15cm thick
Cement comcrete 1:4:8 mix using 40mm ISS Metal including cost and conveyence of all other labour charges
Cement comcrete 1:3:6 mix using 20mm ISS Metal including cost and conveyence of all other labour charges
Supply and erecting centering for side and suffits including suports and sturting upto 3.29m height
Below Sill
Above Sill
Cement comcrete 1:2:4 mix using 20mm ISS Metal including cost and conveyence of all other labour charges
Reinforced Cement comcrete 1:11/2:3 mix using 20mm ISS Metal including cost and conveyence of all other labour charges
Supplying Fab of Steel Including cost and conveyence of all labour chages
Providing and dixing 20mm thick compressible fiber board in expansion joint complete
Providing and fixing Tar Paper for bearing between bed blocxk
Providing weepholes in brick masonry plain rainfor concrete
gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS
RCC Slab Culvert 1.5 m span CH 1/465 1 no
Earth work Excavation and depositing on bank with intial Lead of 10m and intial lift of 2m
Supply and filling good river sand for basement filling not more than 15cm thick
Cement comcrete 1:4:8 mix using 40mm ISS Metal including cost and conveyence of all other labour charges
Cement comcrete 1:3:6 mix using 20mm ISS Metal including cost and conveyence of all other labour charges
Supply and erecting centering for side and suffits including suports and sturting upto 3.29m height
Below Sill
Above Sill
Cement comcrete 1:2:4 mix using 20mm ISS Metal including cost and conveyence of all other labour charges
Reinforced Cement comcrete 1:11/2:3 mix using 20mm ISS Metal including cost and conveyence of all other labour charges
Supplying Fab of Steel Including cost and conveyence of all labour chages
Providing and dixing 20mm thick compressible fiber board in expansion joint complete
Providing and fixing Tar Paper for bearing between bed blocxk
Providing weepholes in brick masonry plain rainfor concrete
gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS
RCC Slab Culvert 1.5 m span CH 2/160,2/635 2 nos
Earth work Excavation and depositing on bank with intial Lead of 10m and intial lift of 2m
Supply and filling good river sand for basement filling not more than 15cm thick
Cement comcrete 1:4:8 mix using 40mm ISS Metal including cost and conveyence of all other labour charges
Cement comcrete 1:3:6 mix using 20mm ISS Metal including cost and conveyence of all other labour charges
Supply and erecting centering for side and suffits including suports and sturting upto 3.29m height
Below Sill
Above Sill
Cement comcrete 1:2:4 mix using 20mm ISS Metal including cost and conveyence of all other labour charges
Reinforced Cement comcrete 1:11/2:3 mix using 20mm ISS Metal including cost and conveyence of all other labour charges
Supplying Fab of Steel Including cost and conveyence of all labour chages
Providing and dixing 20mm thick compressible fiber board in expansion joint complete
Providing and fixing Tar Paper for bearing between bed blocxk
Providing weepholes in brick masonry plain rainfor concrete
gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS
cc Road Ch 3/100-3/370
clnstruction of un reinfocement dowel jointed at expansion and construction joint pCC Sub bae 43grade Cement or any other type as per M30Grade
Supply and erecting centering for side and suffits including suports and sturting upto 3.29m height
Retaining wall 0/085 -1/185
Earth work Excavation and depositing on bank with intial Lead of 10m and intial lift of 2m
Supply and filling good river sand for basement filling not more than 15cm thick
Cement comcrete 1:4:8 mix using 40mm ISS Metal including cost and conveyence of all other labour charges
Cement comcrete 1:3:6 mix using 20mm ISS Metal including cost and conveyence of all other labour charges
Cement comcrete 1:2:4 mix using 20mm ISS Metal including cost and conveyence of all other labour charges
Providing weepholes in brick masonry plain rainfor concrete
Providing and fixing 20mm thick compressible fiber board in expansion joint complete as per drawing
Centring for sides and soffits for PCC item including cost and convaince complete
Below Sill
Above Sill
Road Marking/ Road Stud with lens reflector
Routine Maintenance after completion of work the road sufrace and shoulder to be maintained in proper condition to make them free from excessive edge drop offs, roughness, scouring and pot holes and cleaning of surface drain including culverts for frre flow of water. Relettering name boards and K.M & H.M stone and other maintenance operation required to keep the road traffic worthly at all the time for the maintenance period for the following years. As per General condition of contract para 32.2.2
For 1st Year
For 2nd Year
For 3rd Year
For 4th Year
For 5th Year
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
M/S. SRI AYYAPPA ENTERPRISES (BID ID -1229513)
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .