| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹6.6 LAccepted-Finance | L1 | Accepted-Finance Lowest Price | |
| 2 | L2₹6.6 L+₹585.14 (0.09%)Rejected-Finance | L2 | Rejected-Finance Highest Price |
| Sl No | Description | Qty | Unit | P.RENGARASU L1 | A SENTHILNATHAN L2 |
|---|---|---|---|---|---|
| 1.00Construction of Community Sanitary Complex for (Girls) PUE School at Aladikumulai Panchayat.SBM 2026-27 | |||||
| 2.00 | Earth work excavation and depositing on bank with initial lead of 10 m and lift of 2m in all class of soils as per SS 20B specifications etc. Complete for foundation | 12.04 | cum | 260 ₹3,130.4 Lowest | 263.7 ₹3,174.95 |
| 3.00 | C.C.1:4:8 Mix using 40mm HBG metal including cost and conveyance of all materials and all Labour charges for mixing , laying and curing charges etc, Complete.,. | 2.52 | cum | 6,090 ₹15,346.8 Lowest | 6,091.7 ₹15,351.08 |
| 4.00 | Brick work in cm 1:5 mix using country bricks of including cost & conveyance of all materials and all Labour charges and curing charges etc, Complete.(Below Basement) | 10.2 | cum | 6,309 ₹64,351.8 Lowest | 6,309.5 ₹64,356.9 |
| 5.00 | Brick work in cm 1:5 mix using country bricks of including cost & conveyance of all materials and all Labour charges and curing charges etc, Complete.,. | 11.43 | cum | 6,400 ₹73,152 Lowest | 6,402.4 ₹73,179.43 |
| 6.00Supplying and erecting centering for sides Centering for soffits of RCC slabs of plane surface like lintels, beams ,etc.,including strutting 3m high using mild steel sheets of size 90cm x 60cm x and B.G 10 stiffened with M.S angles of size 25mm x 25mm x '3mm laid over silver Oak (C.W) joists of size 10cm x 6.5cm (spaced at about 90cm c/c )and supported dy casurina props of 10cm to 13cm dia (spaced of 75cm C/C) complying with standard specification. | |||||
| 7.00 | Plinth Beam | 3.8 | sqm | 547 ₹2,078.6 Lowest | 547.45 ₹2,080.31 |
| 8.00 | Lintel | 12.04 | sqm | 1,095 ₹13,183.8 Lowest | 1,095 ₹13,183.8 Lowest |
| 9.00 | Reinforced cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete | 2.26 | cum | 9,800 ₹22,148 Lowest | 9,819.3 ₹22,191.62 |
| 10.00 | Supplying fabricating and placing in position of ribbed steel rods for reinforcement to all RCC works as per the design given including cost of steel and binding wire also in all floors etc., complete | 0.2 | Mt | 91,880 ₹18,559.76 Lowest | 91,880.5 ₹18,559.86 |
Tender Value
₹6.8 L
EMD Value
₹6,840
Closing Date
13 Oct 2026, 3:00 pmClosed
Block Development Officer (BP)
Nadimuthu Nagar, Block Development Office, Pattukkottai
Thanjavur District Construction of Community Sanitary Complex for (Girls) PUE School at Aladikumulai Panchayat. SBM 2026-27
2026_RDTN_708752_1
171/2026/A2
Open Tender
Civil Works - Buildings
Item Wise
90 days
Block Development Office, Pattukkottai
Please refer Tender documents.
8 documents required · 8 mandatory
₹0
₹6,840
Yes
14 Oct 2026
28 Sept 2026
13 Oct 2026
28 Sept 2026
13 Oct 2026
28 Sept 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Construction of Community Sanitary Complex for (Girls) PUE School at Aladikumulai Panchayat.SBM 2026-27 | - | - | - | - |
| 2 | Earth work excavation and depositing on bank with initial lead of 10 m and lift of 2m in all class of soils as per SS 20B specifications etc. Complete for foundation | 12.04 | cum | - | - |
| 3 | C.C.1:4:8 Mix using 40mm HBG metal including cost and conveyance of all materials and all Labour charges for mixing , laying and curing charges etc, Complete.,. | 2.52 | cum | - | - |
| 4 | Brick work in cm 1:5 mix using country bricks of including cost & conveyance of all materials and all Labour charges and curing charges etc, Complete.(Below Basement) | 10.2 | cum | - | - |
| 5 | Brick work in cm 1:5 mix using country bricks of including cost & conveyance of all materials and all Labour charges and curing charges etc, Complete.,. | 11.43 | cum | - | - |
| 6 | Supplying and erecting centering for sides Centering for soffits of RCC slabs of plane surface like lintels, beams ,etc.,including strutting 3m high using mild steel sheets of size 90cm x 60cm x and B.G 10 stiffened with M.S angles of size 25mm x 25mm x '3mm laid over silver Oak (C.W) joists of size 10cm x 6.5cm (spaced at about 90cm c/c )and supported dy casurina props of 10cm to 13cm dia (spaced of 75cm C/C) complying with standard specification. | - | - | - | - |
| 7 | Plinth Beam | 3.8 | sqm | - | - |
| 8 | Lintel | 12.04 | sqm | - | - |
| 9 | Reinforced cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete | 2.26 | cum | - | - |
| 10 | Supplying fabricating and placing in position of ribbed steel rods for reinforcement to all RCC works as per the design given including cost of steel and binding wire also in all floors etc., complete | 0.2 | Mt | - | - |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.79 MB
Technical.pdf
Tender Documents • 0.88 MB
Price.pdf
Tender Documents • 0.56 MB
BOQ_851716.xls
BOQ • 0.34 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .