Loading…
Loading…
Tender Value
₹40.9 L
EMD Value
₹1.0 L
Closing Date
13 Jun 2026, 6:00 pm7d left
SA, ASI, Rajkot
Office of the superintending archaeologist, old collectorate compound, Rajkot
Conservation and civil works at various monuments as per boq
2026_ASI_911427_1
3C/1(47)/RJT/DIU/2026-27
Open Tender
Civil Works
120 days
Diu Fort and surrounding area
as per tender document
2 documents required · 2 mandatory
₹0
₹1.0 L
Yes
3 Jun 2026
3 Jun 2026
15 Jun 2026
3 Jun 2026
13 Jun 2026
3 Jun 2026
3 Jun 2026 - 13 Jun 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1.01 | Carefully removing existing weathered, damaged, or loose plaster from the surface of walls/structure at all heights and levels, including raking out joints, cleaning the exposed surface thoroughly of dust, loose mortar, laitance, vegetation, and other foreign materials by brushing and washing, and preparing the surface to receive new plaster and disposing debris 100m from the site as per direction & as specified by site incharge including all labors, T& P etc. complete. | 129.66 | Sqm. | - | - | BI01010001010000000000000515BI0100001116 |
| 1.02 | Applying 20 mm thick traditional lime plaster in three coats over prepared masonry/structural surfaces, using matured fat lime putty, sand, surkhi, and marble dust, incorporating traditional organic admixtures, complete in all respects as per conservation specifications. First Coat (Scratch/Base Coat): Applying 10 mm thick base coat in lime mortar of proportion 1:1.5:1.5 (lime : sand : surkhi) using coarse sand, well compacted and finished rough with suitable scratching to provide a mechanical key for the subsequent coat. Second Coat (Brown/Intermediate Coat): Applying 8 mm thick intermediate coat in lime mortar of proportion 1:2:1 (lime : sand : surkhi), properly levelled and finished to receive the final coat.Third Coat (Finish Coat): Applying 2–5 mm thick finishing coat in lime mortar of proportion 1:1 (lime : marble dust) using fine materials, finished to a smooth and even surface as specified The lime mortar shall be prepared using traditional organic admixtures, including: Jaggery (gur) Bael fruit pulp Fenugreek (methi) Natural fibres (jute/coconut) Pulses (where specified). These shall be incorporated in appropriate proportions to enhance workability, cohesion, crack resistance, and durability, as per traditional conservation practices. All materials, labour (including skilled heritage masons), mixing, application, curing, complete scaffolding, tools and plants (T&P), and all incidental works necessary to complete the plastering work, and as directed by the Engineer in-Charge(Lime shall be properly slaked and matured (lime putty) prior to use Each coat shall be applied with adequate curing and surface preparation before application of the next coat Surfaces shall be cleaned, wetted, and properly keyed, final surface shall be true to line, level, and plumb as per direction & as specified by site incharge. including all labors, materials T& P etc. complete. | 129.66 | Sqm. | - | - | BI01010001010000000000000515BI0100001117 |
| 1.03 | Fabrication, supply and installation of a freestanding MS Double Leaf Gate with self supporting portal frame, of overall size approximately 1 m to 1.5 m width and upto 2 m height, at identified locations within the monument area for safety and controlled access of visitors, comprising vertical posts of 75x75x4 mm MS square hollow sections, top connecting beam of 75x50x4 mm MS rectangular hollow section, firmly connected to form a rigid frame, and double- leaf gate shutters( each approx. 0.5-0.7m width and 1.8-2 m height ) fabricated out of 40x40x3 mm MS square tube outer frame with 16mm dia and solid MS vertical bars spaces at 100-120mm C/C , including provision of heavy-duty MS hinges (100-125mm), centrally locking arrangement, tower bolts and necessary fixtures. The entire assembly shall be erected over MS base plates of size 250x 250x 10 mm fixed to the floor using 12-16mm dia anchor bolts embedded 100-150 mm deep in joints only, ensuring that no drilling or fixing is carried out in the existing heritage walls and maintaining full reversibility without damage to the historic fabric including proper alignment, smooth operation, provision of stoppers and ensuring structural stability including surface preparation application of zinc rich anti - corrosive primer nad 2 coats of approved finish paint in connection with visitor safety and site management requirement complete as directed by Engineer- in - charge ( larger Gate = 3.1mx1.5m, Smaller gate= 1.5m x 1.2m) as per direction & as specified by site incharge including all labors, materials T& P etc. complete. | 28.79 | Sqm | - | - | BI01010001010000000000000515BI0100001118 |
| 1.04 | Carefully removing loose, cracked bulged or structurally unsound masonry from the wall portions and stacking the usable material for reconstruction at all heights and levels, including raking out joints, removing deteriorated material without disturbing sound portions of the original fabric and cleaning the exposed surface thoroughly of dust, loose mortar, vegetation, salts and other foreign materials by brushing and preparing the surface in connection for subsequent repair rebuilding in matching masonry, disposing debris 100m from the site and conservation as directed by Engineer-in-Charge as per direction & as specified by site incharge including all labors, T& P etc. complete.. | 8.5 | Cum | - | - | BI01010001010000000000000515BI0100001119 |
| 1.05 | Reconstruction of wall masonry in approved as per original, in place of deteriorated masonry at all heights and levels, including dressing of stones to required shapes and sizes, laying in proper courses with through stones and bonding stones, maintaining alignment, levels and plumb and ensuring proper interlocking of masonry, including preparation of lime mortar in specified proportion(1:1:1, Lime: surkhi:sand)(using matured lime putty, sand and approved traditional additives where required filling joints, where necessary, curing and finishing to match the existing historic fabric, in connection with conservation and reconstruction works associated with the proposed works, complete as per direction of Engineer in charge as per direction & as specified by site incharge. (this is conservation work on a protected monument and the vendor have to follow all the conservation principles and methodology for material preparation and quality as approved by the site incharge and the directions of site in charge until completion) including all labors, materials T& P etc. complete. | 8.5 | Cum | - | - | BI01010001010000000000000515BI0100001120 |
| 1.06 | Cleaning of existing boundary wall surface including removal of loose mortar, dust, dirt, old flaking paint, fungal deposits and other foreign materials by manual means using soft brushes, scrapers, complete as per direction. Repair of damaged portions of boundary wall including dismantling of loose and deteriorated plaster, filling of cracks and cavities with suitable cement mortar matching existing surface, replacement of damaged masonry wherever required and curing complete to restore the wall to original. Providing and applying 2 or more coats of approved exterior grade weather- resistant paint over prepared surface including primer coat, surface preparation, labors, tools and plants, transportation, and all incidentals complete as per specifications and directions of Engineer in charge as per direction & as specified by site incharge including all labors, materials T& P etc. complete. | 1,553.07 | Sqm | - | - | BI01010001010000000000000515BI0100001121 |
| 1.07 | Supplying, installing, testing, and commissioning (SITC) of a Commercial Reverse Osmosis (RO) based water purification system of 500 LPH (litres per hour) rated capacity, with chiller/water cooler of suitable capacity(with 03 to 04 drinking water taps) designed for continuous operation for public/ tourist utility, complete in all respect as per approved specification and direction of the Engineer-in-Charge including all labors, materials T& P etc. complete.. | 4 | Job | - | - | BI01010001010000000000000515BI0100001122 |
| 1.08 | Fabricating, supplying, transporting and erecting a Mild Steel (MS) ramp of size 25.50 m × 1.50 m for visitor access to the tower of silence entrance including cutting, hoisting, fixing in position and applying priming coat of approved primer complete in all respects and as directed by the Engineer-in-Charge.(MS Box Pipe 120x120x5 for vertical column, ISMC100 for longitudinal horizontal support, MS angle 50x50x5 for transverse horizontal support at every 1m and longitudinal support at centre of ramp) as per direction & as specified by site incharge including all labors, materials T& P etc. complete. | 1,612.88 | Kg | - | - | BI01010001010000000000000515BI0100001123 |
| 1.09 | Fixing WPC (Wood Plastic Composite) decking sheets/boards of approved quality and thickness (approx. 20–25 mm) on chequered Plates over the above mentioned MS structural frame, fixed with suitable SS fasteners/hidden clips system, complete in all respects. The decking shall be laid with proper gaps to allow thermal expansion and drainage. as per direction & as specified by site incharge including all labors, materials T& P etc. complete. | 38.25 | Sqm | - | - | BI01010001010000000000000515BI0100001124 |
| 1.1 | Applying two coats of Oil Paint of approved brand to door & windows of saint paul’s church after cleaning the old surface including throughly brushing the surface to remove all dirt, dust, erection and dismantling of scaffolding, cost & conveyance of materials & labour charges etc. complete including all labors, materials T& P etc. complete. | 477.74 | M2. | - | - | BI01010001010000000000000515BI0100001125 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 21.07 MB
signedtenderdoc.pdf
Tender Documents • 21.06 MB
BOQ_957878.xls
BOQ • 0.34 MB
Download all tender documents and submit your bid