Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹13.9 LAccepted-Finance | L1 | Accepted-Finance L1 bidder |
| Sl No | Description | Qty | Unit | GANDHI LATHA L1 |
|---|---|---|---|---|
| 1.00Improvement works | ||||
| 1.01 | Dismantling of existing Brick in cement mortar walls under 3m high including cost of all materials, hire charges for tools and plants, clearing the debris away, needed safety arrangements, all leads, lifts etc complete. | 3.04 | cum | 300 ₹912 Lowest |
| 1.02 | Dismantling of existing sunshades under 3m high including cost of all materials, hire charges for tools and plants, clearing the debris away, needed safety arrangements, all leads, lifts etc complete. | 1.65 | cum | 300 ₹495 Lowest |
| 1.03 | Dismantling the Ex.IWC and surki around the closet and clearing the site and disposing the debris 1 Km away including the cost of all labour, lead, lift, T&P etc complete. | 1 | No | 300 ₹300 Lowest |
| 1.04 | Dismantling the Ex.wash basin and clearing the site and disposing the debris 1 Km away including the cost of all labour, lead, lift, T&P etc complete. | 1 | No | 200 ₹200 Lowest |
| 1.05 | Dismantling of existing stained damaged floor & wall tiles without any damage to the existing structure including cost of labour, T & P safety arrangements, cleaning the site,lead,lift etc complete. | 61.2 | sqm | 200 ₹12,240 Lowest |
| 1.06 | Clean removal of cement plaster from existing inner wall sides and removing of cement plaster wastages from premises as directed by the site engineer including cost of all labours, materials, lead, lift, etc., complete. | 82.14 | sqm | 400 ₹32,856 Lowest |
| 1.07 | Chipping of the concrete and roughening the surface without any damage to the concrete portion including cost for clearing the debris, all labourers, hire charges for tools needed safety including cost for clearing the debiris, all labourers, hire charges for tools needs safety arrangements all leads, lifts etc. Complete. | 185.73 | sqm | 300 ₹55,719 Lowest |
| 1.08 | Providing double Plastering with Cement mortar in CM 1:3 mixed with conplast 150 ml/bag of cement and some admixtures such as reebacklenss RR for removing the rust from the existing reinforcement,NITOZING primer for bonding agent to ceiling portion 12mm thick after cleaning the chipping area including cost of all materials lead, lift etc complete.(Double plastering) | 94.13 | sqm | 3,000 ₹2,82,390 Lowest |
| 1.09 | Providing micro concrete with Cleaning rust from the existing exposed reinforcement areas using by the reeback lens RR, application of one coat NITOZINC PRIMER over reinforcemt for strengthing of steel, Plastering with Cement mortar in CM 1:3 for second coat and applicaion of non-shrink cementenious micro concreting (water : powder = 0.15) etc., including cost of all material, labour, lead, lift T&P etc., complete. (micro concrete) as pe the instruction of site engineer. | 92.32 | sqm | 300 ₹27,696 Lowest |
Tender Value
Refer Docs
EMD Value
₹13,802
Closing Date
21 Sept 2026, 2:00 pmClosed
SE/MEDC/METRO/MADURAI
TNEB Complex, Race Course Road, K.Pudur, Madurai
Estimate for Improvement works by providing galvalume sheet sunshade and allied Civil works at Control room of 33/11 KV Anna Bus stand SS in Madurai Metro EDC, Madurai District.
2026_EB_700547_1
SE/MEDC/METRO/MDU - 012/2026 - 27
Open Tender
Civil Works
Item Rate
Madurai
as in specification
2 documents required · 2 mandatory
₹0
₹13,802
Yes
7 Oct 2026
2 Sept 2026
22 Sept 2026
2 Sept 2026
21 Sept 2026
2 Sept 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Improvement works | |||||
| 1.01 | Dismantling of existing Brick in cement mortar walls under 3m high including cost of all materials, hire charges for tools and plants, clearing the debris away, needed safety arrangements, all leads, lifts etc complete. | 3.04 | cum | - | - |
| 1.02 | Dismantling of existing sunshades under 3m high including cost of all materials, hire charges for tools and plants, clearing the debris away, needed safety arrangements, all leads, lifts etc complete. | 1.65 | cum | - | - |
| 1.03 | Dismantling the Ex.IWC and surki around the closet and clearing the site and disposing the debris 1 Km away including the cost of all labour, lead, lift, T&P etc complete. | 1 | No | - | - |
| 1.04 | Dismantling the Ex.wash basin and clearing the site and disposing the debris 1 Km away including the cost of all labour, lead, lift, T&P etc complete. | 1 | No | - | - |
| 1.05 | Dismantling of existing stained damaged floor & wall tiles without any damage to the existing structure including cost of labour, T & P safety arrangements, cleaning the site,lead,lift etc complete. | 61.2 | sqm | - | - |
| 1.06 | Clean removal of cement plaster from existing inner wall sides and removing of cement plaster wastages from premises as directed by the site engineer including cost of all labours, materials, lead, lift, etc., complete. | 82.14 | sqm | - | - |
| 1.07 | Chipping of the concrete and roughening the surface without any damage to the concrete portion including cost for clearing the debris, all labourers, hire charges for tools needed safety including cost for clearing the debiris, all labourers, hire charges for tools needs safety arrangements all leads, lifts etc. Complete. | 185.73 | sqm | - | - |
| 1.08 | Providing double Plastering with Cement mortar in CM 1:3 mixed with conplast 150 ml/bag of cement and some admixtures such as reebacklenss RR for removing the rust from the existing reinforcement,NITOZING primer for bonding agent to ceiling portion 12mm thick after cleaning the chipping area including cost of all materials lead, lift etc complete.(Double plastering) | 94.13 | sqm | - | - |
| 1.09 | Providing micro concrete with Cleaning rust from the existing exposed reinforcement areas using by the reeback lens RR, application of one coat NITOZINC PRIMER over reinforcemt for strengthing of steel, Plastering with Cement mortar in CM 1:3 for second coat and applicaion of non-shrink cementenious micro concreting (water : powder = 0.15) etc., including cost of all material, labour, lead, lift T&P etc., complete. (micro concrete) as pe the instruction of site engineer. | 92.32 | sqm | - | - |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.28 MB
BOQ_842057.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .