Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹16.3 LAccepted-AOC | L1 | Accepted-AOC ACCEPT | |
| 2 | L2₹16.7 L+₹33,347.08 (2.04%)Rejected-AOC | L2 | Rejected-AOC REJECT | |
| 3 | L3₹16.7 L+₹33,574.60 (2.06%)Rejected-AOC | L3 | Rejected-AOC REJECT |
| Sl No | Description | Qty | Unit | M.Rajendran L2 | R.Rajan L3 | CHITHRAVARSINI AND CO L1 |
|---|---|---|---|---|---|---|
| 1.00 | Dismantling the existing damaged Brick or stone in cement mortar walls under 3 mtr height etc., as per the direction of departmental officers etc., complete | 11 | m3 | 289 ₹3,179 | 291 ₹3,201 | 283 ₹3,113 Lowest |
| 2.00 | Providing Pile foundation of size 300 mm dia using augur including labour charges and all other tools and plants charges etc. , as per direction of dept officers | 11 | m | 277 ₹3,047 | 278 ₹3,058 | 272 ₹2,992 Lowest |
| 3.00 | Earth work excavation in all kinds of soil including sand, silt, wet sand under water, black cotton, stiff black cotton, clay, hard stiff clay, hard red earth, murram, stoney earth, gravel and shales etc. excepting all kinds of rock and boulders exceeding 0.014 c.u.m. in volume including rough dressing and dumping the excavated materials away from work site manually within 50m initial lead and 2m initial lift as per the direction of Engineer-in-charge. | 60 | m3 | 185 ₹11,100 | 185 ₹11,100 | 181 ₹10,860 Lowest |
| 4.00 | Cement concrete 1:4:8 (0ne cement, four sand and eoght aggregate) using 40 mm gauge hard broken granite stome jelly for all CC items of work excluding centering, shuttering and cost of reinforcement grill but inlcuding curing finishing etc., complete fixtures in CC works wherever necessary as directed by departmental officers etc., | 4 | m3 | 5,701 ₹22,804 | 5,730 ₹22,920 | 5,590 ₹22,360 Lowest |
| 5.00 | Supplying fabrications and placing in position RTS rods in various dia including cutting and bending tying of grills placing in position binding wire etc. completed | 30 | Qtl | 9,508 ₹2,85,240 | 9,554 ₹2,86,620 | 9,321 ₹2,79,630 Lowest |
| 6.00 | Centering with steel shutters including studding with sides and support RCC column, footing, plinth beam, stair case in all floors as per the direction of departmental officers etc., complete | 209 | m2 | 1,134 ₹2,37,006 | 1,140 ₹2,38,260 | 1,112 ₹2,32,408 Lowest |
| 7.00 | Supply and erecting centering for sides and soffits including supports for plane surfaces such as RCC slabs, Rectangular beems, Tee (or) ECC Beam, Lintel, Bed Block, Staircase waist and landing slabs landing beams, canopy etc., complete as directed. | 28 | m2 | 1,361 ₹38,108 | 1,368 ₹38,304 | 1,334 ₹37,352 Lowest |
| 8.00 | Reinforced Cement concrete 1:1.5:3 mix (one cement, oneand half sand, Three metal ) using 20mm size hard broken stones from approved quarry complying with standard specification | 12 | m3 | 8,927 ₹1,07,124 | 8,971 ₹1,07,652 | 8,751 ₹1,05,012 Lowest |
| 9.00 | Fly ash Brick work in CM 1:5 (one cement & five sand) using size 9"X4 3/8"X 2 3/4" including finishing, curing, etc., complete complying with standard | 24 | m3 | 7,271 ₹1,74,504 | 7,307 ₹1,75,368 | 7,128 ₹1,71,072 Lowest |
| 10.00 | Filling with Well Gravel including watering and consolidation as per direction of departmental officers etc. completed. | 12 | m3 | 49 ₹588 | 49 ₹588 | 48 ₹576 Lowest |
Tender Value
₹19.5 L
EMD Value
₹19,500
Closing Date
8 Aug 2025, 3:00 pmClosed
The Commissioner, Coimbatore Corporation
Coimbatore Corporation, Main Office, Big bazaar street, Town hall, Coimbatore-1
Construction of Additional room, Toilet, Compound wall and Additional improvement works to the ICDS Centers 404 405 at Selvapuram North housing unit in ward no 78 South zone.
2025_MAWS_587208_9
e41/2025
Open Tender
Civil Works
Works
150 days
Coimbatore corporation
AS PER THE TENDER DOCUMENT
4 documents required · 4 mandatory
₹0
₹19,500
6 Nov 2025
30 Jul 2025
8 Aug 2025
30 Jul 2025
8 Aug 2025
30 Jul 2025
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .