7 May 2024, 1:30 pmClosed
PR & CC
TANK FOUNDATION WORKS TK 313 314 264 at HPCL Mumbai Refinery
2400011623-HD-06000
5100011623
Open Tender
Mumbai, Maharashtra
₹0
₹9.6 L
7 May 2024
15 Apr 2024
7 May 2024
7 May 2024
15 Apr 2024 - 22 Apr 2024
| Item No | Item Title | Description | Qty | Unit |
|---|---|---|---|---|
| 1 | Exc soil 0-1.5m | Exc soil 0-1.5m — xcavation (upto 1.5m depth) for foundations, trenches, drains, roads etc. in all types of soil, levelling/ compaction of the excavat surface etc. all complete. Soil/soft murrum will be classified as which can be removed easily by using axes, pick-axe/crow bars/sho ls etc." | - | cubic meter |
| 2 | Exc soil 1.5-3m | Exc soil 1.5-3m — xcavation (1.5m to 3m depth) for foundations, trenches, drains, roads etc. in all types of soil including soft murrum, levelling / c paction of the excavated surface etc. all complete. Soil/soft murrum will be classified as which can be removed easily by using axes pick-axe/crow bars/shovels etc." | - | cubic meter |
| 3 | Exc soft rock 0-1.5m | Exc soft rock 0-1.5m — cavation (upto 1.5m depth) for foundations, trenches, drains etc. in all types of hard murrum, soft rock, leveling /compaction of th excavated surface etc. all complete | - | cubic meter |
| 4 | Exc soft rock 1.5-3m | Exc soft rock 1.5-3m — cavation (1.5m to 3m depth) for foundations, trenches, drains etc. in all types of hard murrum, soft rock, leveling /compaction of t excavated surface etc. all complete. | - | cubic meter |
| 5 | Exc hard rock 1.5-3m | Exc hard rock 1.5-3m — xcavation (upto 1.5m depth)for foundations, trenches, drains, roads etc. in all types of HARD ROCK by chiselling / USING MECHANICAL UIPMENT including stacking the useful boulders / rock within the premises as directed. (Measurements shall be by stacks, less 50% vo s OR Initial and final levels of the excavated area as per the decision of E-IC) (Rocks which cannot be removed by PICK / AXES and O WEDGING and which would require BREAKER OR EQUIVALENT EQUIPMENT will be classified as HARD ROCK)." | - | cubic meter |
| 6 | Exc hard rock 1.5-3m | Exc hard rock 1.5-3m — xcavation (1.5m to 3m depth) for foundations, trenches, drains, roads etc. in all types of HARD ROCK by chiselling / USING MECHANICA EQUIPMENT including stacking the useful boulders / rock within the premises as directed. (Measurements shall be by stacks, less 50% ids OR Initial and final levels of the excavated area as per the decision of E-IC) (Rocks which cannot be removed by PICK / AXES and R WEDGING and which would require BREAKER OR EQUIVALENT EQUIPMENT will be classified as HARD ROCK)." | - | cubic meter |
| 7 | Backfilling | Backfilling — ackfilling with excavated earth/ available earth IN THE REFINERY in the pit / trenches/foundations/roads etc. includes full compacti , either with manual ramming/ roller as per site condition" | - | cubic meter |
| 8 | Disposal outside MR | Disposal outside MR — isposal to a BMC designated/private dumping location, proof of outside disposal to be produced like Out Going gate Pass of Refinery BMC Challan etc.whichever is applicable. This item will be extra over and above the items of excavation/ dismantling etc. for the di osal of excess/surplus debris/ earth generated at the site on the actual qty. of excavation/dismantling irrespective of the qty to b disposed. Payment shall be made to vendor based on initial and final levels of the excavated area which shall also be reconciled wit truck measurements (reduced by 30% for voids). The minimum of both will be payable. DISPOSAL AREAS OUTSIDE PLANT BOUNDARY TO BE ARRA ED BY THE CONTRACTOR. Royalty & taxes as applicable for disposal outside plant limits to be borne by the Contractor" | - | cubic meter |
| 9 | RMC M5 or 1:5:10 | RMC M5 or 1:5:10 — oviding and laying PLAIN CEMENT CONCRETE for all depths below and upto plinth level in foundations, drains, fillings, non-suspended oors, pavements & ramps or any other works etc. including shuttering, tamping, ramming, vibrating, curing etc. all as specified in a shape, position, thickness and finishing the top surface rough or smooth as specified and directed all complete. OR nominal mix of 5:10 by mass (1 Cement : 5 Coarse Sand : 10 Crushed Stone Aggregates/Gravels) with 20mm and down size graded crushed stone aggaregat /gravels. ALL MATERIALS INCLUDING CEMENT SUPPLIED BY THE CONTRACTOR. | - | cubic meter |
| 10 | RMC M20 or 1:1.5:3 | RMC M20 or 1:1.5:3 — oviding and laying PLAIN CEMENT CONCRETE for all depths below and upto plinth level in foundations,drains, fillings, non-suspended f ors, pavements & ramps or any other works etc. including shuttering, tamping, ramming, vibrating, curing, etc. all as specified in a shape, position, thickness and finishing the top surface rough or smooth as specified and directed all complete for concrete grade 0 with 20mm and down size graded crushed stone aggaregates/Gravels. OR nominal mix of 1:1.5:3 by mass (1 Cement : 1.5 Sand : 3 Crush Stone Aggregates/Gravels) with 20mm and down size graded crushed stone aggaregates/gravels. ALL MATERIALS INCLUDING CEMENT SUPPLIED Y THE CONTRACTOR. | - | cubic meter |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
2400011623-HD-06000.pdf
TENDER_DOCUMENT • 15.81 MB
Download all tender documents and submit your bid