| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹1.2 CrAccepted-Finance | ₹1.2 Cr | L-1 | Accepted-Finance Admitted |
| 2 | L-2₹1.2 Cr+₹86,282.86 (0.70%)Accepted-Finance | ₹1.2 Cr+₹86,282.86 (0.70%) | L-2 | Accepted-Finance Admitted |
| 3 | L-3₹1.2 Cr+₹2.1 L (1.74%)Accepted-Finance GRAM POST SATHIYAV MUBARAKPUR DISTRICT AZAMGARH | AZAMGARH | UTTAR PRADESH | 223221 | ₹1.2 Cr+₹2.1 L (1.74%) | L-3 | Accepted-Finance Admitted |
Tender Value
₹1.2 Cr
EMD Value
₹1.3 L
Closing Date
21 Jan 2022, 4:00 pmClosed
Superintending Engineer
Electricity Transmission Circle, 220 KV S/S Natwa, Mirzapur
Construction of 132 KV D/C Obra-Dalla Diversion line under Electricity Transmission Division, Robertsganj
2022_UPTCL_669357_1
short term T. No. 41/2021-22/ETC/Mzp
Open Tender
Electrical Works
Fixed-rate
90 days
Robertsganj
As per tender specification
2 documents required · 2 mandatory
₹11,800
Executive Engineer, ETD, Mirzapur
₹1.3 L
27 Jan 2022
1 Jan 2022
22 Jan 2022
1 Jan 2022
21 Jan 2022
1 Jan 2022
Amount
Benching volume
Normal soil
Fissured Rock
Cost of excavation of 132 kv Gantry foundation pits including all earth work back fillling, ramming and levelling etc including cost of borrowed soil if required.
Cost of concreting with 1:2:4 mix concreting for all type of foundation including cost of cement , sand ,stone ballast, dewatering, forming, shoring shuttering and curing but excluding cost of installation of reinforcement bars.
Cost of concreting with 1:3:6 mix concrete for all type of foundation including cost of cement , sand , stone ballast, dewatering forming, shoring and shuttering and curing but excluding cost of installation of reinforcement bars.
Installation of steel reinforcement bars in RCC foundation including cost of steel reinforcement bars with cutting, bending, placing, binding etc .
Erection of super structure of all types of towers and their extensions wherever required including all work above ground level excluding hoisting of insulators, hardware and accessories but including fitting of number plate, danger plate, phase plate and punching of bolts ( Wt. of tower is excluding the weight of stub, washers, nuts & bolts etc. )
Tack welding of all the bolts upto the height of one section of tower or 5 meter from ground level whichever is higher and application of zinc rich aluminium paint on the affected surface including cost of all material and T&P etc.
Laying ,Stringing ,tensioning clamping,jointing etc of ACSR Panther conductor including hoisting of insulators, fitting of all necessary hardware and accessories i.e, fittings armour rods,vibration dampers etc etc. of all six conductor for all six phases.
Laying & Stringing of one no. 7/3.25 mm GS earthwire with all necessary hardware and accessories including clamping, jointing etc
Grounding work for counterpoise earthing.
De-stringing of all six phase ACSR conductor and earthwire safely and wrapping it in drums. Work includes removal of all hardwares and accessories & thereafter transportaion of these to UPPTCL store.
Dismantling of towers of existing line including removalof tack welded nut & bolts & thereafter transportaion of these to UPPTCL store and proper stacking.
Protection of tower footings.
Random rubble stone masonary including excavation (1:6) mortar
M 15 (1:2:4) mixed concrete for top seal cover of revetment.
Back filling and Gap levelling
Rama Power construction
M/S SHANTI ENTERPRISES
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .