Tender Value
₹37.4 L
EMD Value
₹3.7 L
Closing Date
23 Jun 2026, 12:00 pm
EXECUTIVE ENGINEER MINOR IRRIGATION DIVISION AGRA
EXECUTIVE ENGINEER MINOR IRRIGATION DIVISION AGRA BAROLI AHEER AGRA
BHANDANA VALA TALAB, VILLAGE SIKATARA, BLOCK PINAHAT, DISTT AGRA.
2026_UPMID_1154685_1
TENDER NO-03 POND
Open Tender
Civil Works - Others
90 days
PINAHAT
AS PER TENDER NOTICE
2 documents required · 2 mandatory
₹854
Chief Finance and Account Officer,Nagar Nigam
₹3.7 L
Yes
OFFICE OF EEMI AGRA
28 May 2026
28 May 2026
23 Jun 2026
28 May 2026
23 Jun 2026
28 May 2026
28 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1POND EXCAVATION WORK | ||||||
| 1.01 | SITE CLEARANCE OF POND | 6,882 | M² | 3.3 | ₹22,710.6 | BI01010001010000000000000515BI0100001113 |
| 1.02 | E/W IN EXCAVATION OF ORDINARY SOIL BY POCKLAIN MACHINE & SHIFTING OF TOTAL EXCAVATED EARTH/ SOIL FOR MAKING BUND/ OUTSIDE POND. | 25,806 | m³ | 105 | ₹27,09,630 | BI01010001010000000000000515BI0100001118 |
| 1.03 | COMPACTION OF EXCAVATED SOIL BY MACHINE AT BUND AND DRESSING OF BUND BY MANUAL LABOUR INCLUDING ALL T&P | 13,207.5 | m³ | 14 | ₹1,84,905 | BI01010001010000000000000515BI0100001122 |
| 1.04 | DEWATERING BEFORE AND DURING THE WORK IN HOURS, BY 8 HP DESEL PUMP SET WITH T&P ETC | 25 | Hrs | 240 | ₹6,000 | BI01010001010000000000000515BI0100001123 |
| 2CONSTRUCTION OF TWO INLET , ONE OUTLET AND ONE RAMP | ||||||
| 2.01 | EARTH WORK IN EXCAVATION IN TRENCHES FOR FOUNDATIONIN IN ORDINARY SOIL ( LOAM CLAY OR SAND) INCLUDING LIFT UPTO 2M LEAD UP TO 10M. IT SHALL INCLUDING DRESSING OF SIDES, RAMMING OF BOTTOM AND DISPOSAL OF SURPLUS EXCAVATED EARTH WITHIN A LEAD. | - | m³ | 100 | - | - |
| 2.02 | PROVIDING AND LAYING IN CEMENT CONCRETE 1:3:6 (1 CEMENT, 4C/SAND, 8STONE AGGREGATEC 40MM. NOMINAL SIZE) AND CURING COMPLETE. IT SHALL INCLUDE FOR COST OF FROM WORK IN FOUNDATION AND FLOORS. | - | m³ | 5,900 | - | - |
| 2.03 | CLASS-150 BRICK WORK IN 1:4(1 CEMENT AND 4 COARSE SAND OF 1.25 FINENESS MODULOUS) MORTAR IN FOUNDATION AND PLINTH. IT SHALL INCLUDE FOR SUPPLY OF ALL MATERIALS, LABOUR & TOOLS AND PLANTS, ETC. REQUIRED FOR PROPER COMPLETION OF THE WORK. | - | m³ | 6,450 | - | - |
| 2.04 | P/L OF C.C. IN 1:2:4 IN & TOP OF WALL WITH CEMENT COARSE SAND & 20MM STONE GRIT I/C ALL LABOUR & MATERIAL CHARGES. | - | m³ | 6,600 | - | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html