THE PROJECT DIRECTOR DRDA, DINDIGUL
THE PROJECT DIRECTOR DRDA, DINDIGUL
Dindigul Dist - 14th Central Finance Commission 2019-20 - Kodaikanal block road works TN-05-203
2020_RDTN_174589_1
DIPR/2668/Tender/2020 TN-05-203
Open Tender
Civil Works - Roads
Item Rate
180 days
DINDIGUL
Dindigul Dist - 14th Central Finance Commission 2019-20 - Kodaikanal block road works TN-05-203
5 documents required · 5 mandatory
₹0
₹41,000
THE PROJECT DIRECTOR DRDA, DINDIGUL
9 Sept 2020
4 Aug 2020
19 Aug 2020
4 Aug 2020
19 Aug 2020
4 Aug 2020
4 Aug 2020
Amount
Part 1 : Upgradation of the road from Attuvampatty-society road (via) Annaisathya Colony road KM 0/0 - 0/600 H/O Vilpatty. (PUR 194) Estimate Amount Rs.40.20 Lakhs.
Clearing the Scrub jungle clearence including all labour charges for burryingng and burning etc.,
Earth work excavation and depositing on bank within initial lead and lift in hard gravelly soil for Cutting sidedrain etc, complete. as per SS20 A
Providing & Laying gravel for side bermes including all cost and conveyance of all material and labour charge etc complete
Providing and laying the WBM 75mm compacted thickness with Grade-II metal using 1:00 cum of 63-11.20 mm IRC HBG. Metal with 0.24 cum gravel mix blind age per 10sqm of 100 mm thickness. The value of below 6% including cost and conveyance of materials and stacking them at the site to the departmental gauge for pre measurement, labour charges for spreading metal and gravel hand packing to chamber with all leads for water and compaction by 8-10 tonne power roller including hire charges and fuel charges for power roller water sprinkler and all other tools and plants employed Barricading etc., complete as per clause 404 of MOST specification.
Providing and laying the WBM 75mm compacted thickness with Grade-III metal using 1:00 cum of 63-11.20 mm IRC HBG. Metal with 0.24 cum gravel mix blind age per 10sqm of 100 mm thickness. The value of below 6% including cost and conveyance of materials and stacking them at the site to the departmental gauge for pre measurement, labour charges for spreading metal and gravel hand packing to chamber with all leads for water and compaction by 8-10 tonne power roller including hire charges and fuel charges for power roller water sprinkler and all other tools and plants employed Barricading etc., complete as per clause 404 of MOST specification.
Applying Tack coat using 4 kg of Emulson Bitumen over the existing wbm surface including all labour charges for applying the Emulson bitumen including all labour charges for applying and all hire and fuel for all tools and plants employed etc complete.
Providing Premix and Seal coat using with 0.18 cum of 13.2 mm,11.20 mm IRC chips pre mixed with 13.43 kg of 80/100 Packed Bitumen & using 1.168 kg of Plastic waste for 10 sqm with seal coat using 6.70 mm IRC chips pre mixed with 9.8 kg of 80/100 Packed Bitumen. including all labour charges for premixing and laying and consolidated with 8/10 MT poer roller all hire and fuel for all tools and plants employed and all other incidential charges etc complete
Supply of Hectameter stone of size 0.9 x 0.15 x 0.15 meter
Sub Estimate for CC
Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse an including cost of all materials and labour charges for mixing, laying, compacting and curing etc. complete
Provision for Bitumen pad including all fixing and all labour charges and etc complete.
Sub Estimate for CC Side Drain
Earth work excavation for structures as per drawing and technical specifications clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50m, dressing of sides and bottom and backfilling in trenches with excavated suitable material
Cement concrete mix 1:4:8 using 40mm ISS size HBG including cost and conveyance of all materials to site including cost of cement and labour for mixing , laying,watering and curing and compacting concrete and labour for formwork and all other incidental charges such as baling out water providing protective bunds coffer dams etc.,complete for foundation concrete.
CC 1:2:4 mix using 20 mm ISS size HBG including cost and conveyance of all materials to site including cost of cement and labour for mixing , laying,watering and curing and compacting concrete and labour for formwork and all other incidental charges such as baling out water providing protective bunds coffer dams etc.,complete
Provosion for Botumen pad including all fixing and all labour chargers etc., complete
Providing and Fixing Name Board
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
S THAVAMANI
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .