Loading…
Loading…
Tender Value
₹47.7 L
EMD Value
₹95,000
Closing Date
7 Sept 2026, 3:00 pm
Deputy General Manager (Civil)
BSPS Surangani
Repairing and Maintenance of damaged existing water drain and gabion structure located at upper side of Left and Right Bank of Baira Dam, Baira Siul Power Station
2026_NHPC_922388_1
NH/BSPS/CC/CW/15/2026-27/247 Dated 17/08/2026
Open Tender
Civil Works
Works
90 days
BSPS Surangani
Please refer Tender documents.
8 documents required · 8 mandatory
₹590
NHPC LTD
₹95,000
17 Aug 2026
17 Aug 2026
11 Sept 2026
17 Aug 2026
7 Sept 2026
17 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Surface dressing of the ground including removing vegetation and in-equalities not exceeding 15 cm deep and disposal of rubbish, leadup to 50m and lift upto 1.5 m. All kinds of soil | 3,380 | Sqm | 17.28 | ₹58,406.4 |
| 2 | Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth,1.5 m in width as well as10 sqm on plan) including getting out and disposal of excavated earth lead upto 50mand liftupto1.5m,as directed by Engineer-in-charge. All kinds of soil. | 380 | Cum | 161.72 | ₹61,453.6 |
| 3 | Random rubble masonry with hardstone in foundation andplinth including levellingupwithcement concrete 1:6:12 (1cement : 6 coarsesand : 12gradedstone aggregate 20 mm nominal size) upto plinth level with :Cement mortar 1:6 (1 cement : 6 coarse sand) | 160 | Cum | 6,172.91 | ₹9,87,665.6 |
| 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:1½:3 (1 Cement: 1½ coarse sand) : 3 graded stone aggregate 20 mm nominal size) | 213.74 | Cum | 7,868.36 | ₹16,81,783.27 |
| 5 | Centering and shuttering including strutting, propping etc. and removal of form for :Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc. | 1,058.8 | Sqm | 507.36 | ₹5,37,192.77 |
| 6 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.Thermo-MechanicallyTreatedbarsofgrade Fe-500D or more. | 1,527.74 | Kg | 94.82 | ₹1,44,860.31 |
| 7 | 15mmcement plaster on roughsideof singleor half brick wall of mix: 1:4 (1 cement: 4 coarse sand) | 599 | Sqm | 260.98 | ₹1,56,327.02 |
| 8 | Providing & making Gabion structure with Mechanically Woven Double Twisted Hexagonal Shaped Wire mesh Gabion Boxes as per IS 16014:2012,MORTH Clause 2500, of required size, Mesh Type 10x12 (D=100 mm with tolerance of ± 2%) Zinc coated, Mesh wire diameter 3.0 mm, mechanically edged/selvedged with partitions at every 1m interval and shall have minimum 10 numbers of openings per meter of mesh perpendicular to twist, tying with lacing wire of diameter 2.2mm, supplied @ 3% by weight of Gabion boxes, filled with boulders with least dimension of 200 mm, as per drawing, all complete as per direction of Engineer-in-charge. | 308 | Cum | 3,707 | ₹11,41,756 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.12 MB
TendDoccw15.pdf
Tender Documents • 6.58 MB
BOQ_969288.xls
BOQ • 0.25 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].