| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹2.7 CrAdmitted-Finance | -28.88% | ₹2.7 Cr | L1 | Admitted-Finance |
| 2 | L2₹3.0 Cr+₹29.7 L (11.1%)Admitted-Finance | -20.99% | ₹3.0 Cr+₹29.7 L (11.1%) | L2 | Admitted-Finance |
Tender Value
₹3.8 Cr
EMD Value
₹7.5 L
Closing Date
27 Jan 2026, 6:00 pmClosed
XEN
UIT DAUSA BANDIKUI
Nit No EE/06/2025-26
2026_UITDB_525552_1
Nit No EE/06/2025-26
Open Tender
Civil Works
Percentage
180 days
DAUSA
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,000
Yes
UIT DAUSA BANDIKUI
₹7.5 L
Yes
27 Apr 2026
7 Jan 2026
28 Jan 2026
7 Jan 2026
27 Jan 2026
7 Jan 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Clearing and Grubbing Road Land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm in thickness as per MoRD Specification Clause 201. By Mechanical Means In area of non thorny jungle. | 15.81 | Hec | 12,513 | ₹1,97,836.79 |
| 2 | Survey of Proposed road including printout of Plan, L-Section & Cross section on A-3 size paper in three copies & one soft copy of approved media (For L-Section levels are to be taken at an interval of 25m on plain terrain and 10m on rolling & at CD works) including computation of quantities of earth work in cutting / filling as per L-Section & Cross section | - | Km | 2,265 | - |
| 3 | Excavation in Soil using Hydraulic Excavator and Tippers with disposal upto 1000 m - Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross-sections, and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m as per MoRTH Specification Clause 301.3. | - | CUM | 31 | - |
| 4 | Construction of Embankment with Material Obtained from Roadway
Cutting - Construction of embankment with approved materials deposited at site obtained from roadway cutting and excavation from drain and foundation or other structures graded and compacted to meet requirement of Tables 300- 1 and 300-2 as per MoRTH Specification Clause 305.3. | - | CUM | 40 | - |
| 5 | Construction of Embankment with Material Obtained from Borrow Pits - Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300-1 and 300-2 with a lead upto 50 m as per MoRTH Specification Clause 305.3. | - | Cum | 58 | - |
| 6 | Carriage of material from quarry / crusher to work site including loading, unloading and stacking all complete.Earth, Sand, Lime, Morrum manure or sludge Add for each 1 Km beyond Ist Km (upto 5 Km.)
NOTE - 1. Rates are for net quantities after deduction of voids
2. Part of Km beyond 1 Km. will be treated as under :
1.499 = 1.00 Km. 1.501 Km. = 2.00 Km
3. The rates are inclusive of loading and unloading
4. The rates are inclusive stacking if stacking not required no deduction shall be made | - | Cum | 47.3 | - |
| 7 | Carriage of material from quarry / crusher to work site including loading, unloading and stacking all complete.Earth, Sand, Lime, Morrum manure or sludge Add for each 1 Km beyond Ist Km
NOTE - 1. Rates are for net quantities after deduction of voids
2. Part of Km beyond 1 Km. will be treated as under :
1.499 = 1.00 Km. 1.501 Km. = 2.00 Km
3. The rates are inclusive of loading and unloading
4. The rates are inclusive stacking if stacking not required no deduction shall be made | - | Cum | 79.55 | - |
| 8 | Granular Sub-base with Well Graded Material (Table 400-1) - By Mix in place mathod
Construction of granular sub-base by providing well graded material, spreading in uniform layers with Tractor Mount Grader onprepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per MoRD Specification Clause 401.
For Grading I Material. | - | Cum | 512 | - |
| 9 | Wet Mix Macadam - Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base course on a well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400-11 & 400-12 and MoRTH Specification Clause 406.
By Mechanical Means with all lead. | - | CUM | 1,147 | - |
| 10 | Supply & fixing of M-20 grade precast cement concrete Kerb or Dand upto 60 cm length over 20mm thick base of cement mortar1:6 including jointing earthwork, pointing & jointing with cement mortar 1:4 of size (22.5 x 25) x 30 cm2. Kerb. | - | P. Rmt | 505 | - |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.26 MB
tdee06.pdf
Tender Documents • 0.99 MB
BOQ_937845.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .