| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹52.7 LAccepted-AOC | ₹52.7 L | L1 | Accepted-AOC Due to lower rate in BOQ |
Tender Value
₹53.0 L
EMD Value
₹4.7 L
Closing Date
5 Mar 2026, 12:00 pmClosed
Superintending Engineer
Office of the Superintending Engineer, BSR Circle, PWD, Bulandshahr
ReConstruction work in BRC Dankaur District Gautambudhnagar
2026_CEMRT_1120123_1
2115/96M(IV)-BSR CIRCLE/2025-26 DATE 17.02.2026
Open Tender
Civil Works - Buildings
Fixed-rate
270 days
Gautambudhnagar
Please refer Tender documents.
3 documents required · 3 mandatory
₹2,714
₹4.7 L
Bulandshahr
18 Aug 2026
26 Feb 2026
5 Mar 2026
26 Feb 2026
5 Mar 2026
26 Feb 2026
28 Feb 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator)/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-incharge. All kinds of soil. Including cost of, all material, labour, T&P, Labour cess, all taxes complete. But excluding GST. 2023 DSR No. 2.6.1 | 264 | Cum. | 130 | ₹34,320 |
| 2 | Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete.Including cost of, all material, labour, T&P, Labour cess, all taxes complete. But excluding GST. 2023 DSR No. 2.27 | 20.47 | Cum. | 1,650 | ₹33,775.5 |
| 3 | Treatment of soil under existing floors using chemical emulsion @ one litre per hole, 300 mm apart including drilling 12 mm diameter holes and plugging with cement mortar 1 :2 (1 cement : 2 Coarse sand) to match the existing floor:
With Chlorpyriphos/Lindane E.C. 20% with 1% concentration. Including cost of, all material, labour, T&P, Labour cess, all taxes complete. But excluding GST. 2023 DSR No.2.35.3.1 | - | Sqm | 240 | - |
| 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :
1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources). Including cost of, all material, labour, T&P, Labour cess, all taxes complete. But excluding GST. 2023 DSR No. 4.1.8 | 24.6 | Cum. | 5,200 | ₹1,27,920 |
| 5 | Centering and shuttering including strutting, propping etc. and removal of form for : DSR NO. 5.9
Foundations, footings, bases of columns, etc. for mass concrete : Including cost of, all material, labour, T&P, Labour cess, all taxes complete. But excluding GST. 2023 DSR NO. 5.9.1 | 34.9 | Sqm | 300 | ₹10,470 |
| 6 | Suspended floors, roofs, landings, balconies and access platform Including cost of, all material, labour, T&P, Labour cess, all taxes complete. But excluding GST. 2023 DSR NO. 5.9.3 | 167 | Sqm. | 720 | ₹1,20,240 |
| 7 | Lintels, beams, plinth beams, girders, bressumers and cantilevers. Including cost of, all material, labour, T&P, Labour cess, all taxes complete. But excluding GST. 2023 DSR NO. 5.9.5 | 300 | Sqm | 575 | ₹1,72,500 |
| 8 | Columns, Pillars, Piers, Abutments, Posts and Struts. Including cost of, all material, labour, T&P, Labour cess, all taxes complete. But excluding GST. 2023 DSR NO. 5.9.6 | 124 | Sqm | 750 | ₹93,000 |
| 9 | Edges of slabs and breaks in floors and walls Under 20 cm wide. Including cost of, all material, labour, T&P, Labour cess, all taxes complete. But excluding GST. 2023 DSR NO. 5.9.16.1 | 67 | Rmt | 160 | ₹10,720 |
| 10 | Extra for additional height in centering, shuttering where ever required with adequate bracing, propping etc., including cost of de-shuttering and decentering at all levels, over a height of 3.5 m, for every additional height of 1 metre or part thereof (Plan area to be measured). Including cost of, all material, labour, T&P, Labour cess, all taxes complete. But excluding GST. 2023 DSR NO. 5.11.1 | 136 | Sqm | 300 | ₹40,800 |
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.35 MB
Tendernotice_2.pdf
PDF • 1.04 MB
BOQ_2083409.xls
BOQ • 0.50 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .