| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹85.3 LAdmitted-Finance | L1 | Admitted-Finance | |
| 2 | L2₹85.5 L+₹25,398 (0.30%)Admitted-Finance | L2 | Admitted-Finance | |
| 3 | L3₹92.2 L+₹6.9 L (8.10%)Admitted-Finance | L3 | Admitted-Finance | |
| 4 | L4₹93.0 L+₹7.7 L (9.04%)Admitted-Finance | L4 | Admitted-Finance | |
| 5 | L5₹97.0 L+₹11.8 L (13.8%)Admitted-Finance | L5 | Admitted-Finance |
| Sl No | Description | Qty | Unit | KEWAL KRISHAN GUPTA, GOVT CONTRACTOR L1 | KAMAL JEET L2 | Devinder Singh Sambyal L3 | naminder kumar govt. contractor L4 | M/S Gopal Singh Contractor L5 | Shakti Singh L6 | SH ASHWANI KUMAR L7 | JASVIR SINGH L8 | M/S SUCREEV SINGH GOVT CONTRACTOR L9 | SUNIL KUMAR L10 | PEER BABA ASSOCIATES L11 | PAWAN KUMAR L12 | balvinder slathia L13 | SUMANT SINGH JAMWAL L14 | sanjeev singh L15 | Mahmood Khan Govt. Contractor L16 | Shiv Kumar Khajuria L17 | Shah Nawaz L18 | M/S KULBIR SINGH L19 | Satish Samyal L20 | Zaffer Iqbal Contractor L21 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1.00 | Earth work in rough excavation earth in layers not exceeding 20 cm in depth breaking clause, watering with each layer half ton roller wooden steel ramming and rolling every third top layer with power road of minimum 8 ton and dressing up in embankment for lead upto 50 m and lift upto 1.50m in all kinds of soil. | 485 | Cum | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 2.00 | Providing and filling RBM including loading, unloading, carriage in layers 20 cm depth consolidation with 8-10 ton Road Roller, watering, dressing complete in all respects including all sort of taxes as per item no.1 (B) | 22,000 | Cum | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 3.00 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work upto plinth level. 1:4:8 (1 cement: 4 coarse sand: 8 graded stone aggregate 40 mm nominal size). | 53.75 | Cum | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 4.00 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering- All works upto plinth level 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20mm nominal size. | 1,826 | Cum | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 5.00 | Centering and shuttering including strutting propping and removal of form work for foundation footings bases of column and walls (any thickness) | 3,169 | Sqm | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 6.00 | 12mm thick plaster in 1:4 | 1,714 | Sqm | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 7.00Carriage of material by mechanical transport:- | ||||||||||||||||||||||||
| 7.01 | Sand | 1,868 | Cum | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 7.02 | Stone aggregate | 1,876 | Cum | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 8.00 | Dumping of stones horizontally back of R/wall excluding cost of stones | 900 | Cum | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
Tender Value
₹1.9 Cr
EMD Value
₹3.7 L
Closing Date
15 Feb 2020, 4:00 pmClosed
ER. AGNINDER BAKSHI
O/o EXECUTIVE ENGINEER, SIDCO CONTSTRUCTION DIVISION BARI BARHAMAN
Construction of Retaining wall, Parapit, preparation of formation level by way of RBM filling and Earthwork I cutting of Road connectivity Phase Ist with Phase-II from Rd 0-450 mtrs at Industrial Growth Centre Samba.
2020_SIDCO_91794_10
E- NIT No 23 of 2019-20 Dt 16-01-2020.
Open Tender
Civil Works
Item Rate
40 days
SAMBA
Please refer Tender documents.
3 documents required · 3 mandatory
₹8,000
EXECUTIVE ENGINEER, SIDCO CONSTRUCITON DIVSION BB
₹3.7 L
27 Feb 2020
6 Feb 2020
17 Feb 2020
6 Feb 2020
15 Feb 2020
6 Feb 2020
Amount
Earth work in rough excavation earth in layers not exceeding 20 cm in depth breaking clause, watering with each layer half ton roller wooden steel ramming and rolling every third top layer with power road of minimum 8 ton and dressing up in embankment for lead upto 50 m and lift upto 1.50m in all kinds of soil.
Providing and filling RBM including loading, unloading, carriage in layers 20 cm depth consolidation with 8-10 ton Road Roller, watering, dressing complete in all respects including all sort of taxes as per item no.1 (B)
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work upto plinth level. 1:4:8 (1 cement: 4 coarse sand: 8 graded stone aggregate 40 mm nominal size).
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering- All works upto plinth level 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20mm nominal size.
Centering and shuttering including strutting propping and removal of form work for foundation footings bases of column and walls (any thickness)
12mm thick plaster in 1:4
Carriage of material by mechanical transport:-
Stone aggregate
Dumping of stones horizontally back of R/wall excluding cost of stones
Supply of stones, Boulders of nominal size (including carriage )
KAMAL JEET
Devinder Singh Sambyal
naminder kumar govt. contractor
M/S Gopal Singh Contractor
Shakti Singh
SH ASHWANI KUMAR
JASVIR SINGH
M/S SUCREEV SINGH GOVT CONTRACTOR
SUNIL KUMAR
PEER BABA ASSOCIATES
PAWAN KUMAR
balvinder slathia
SUMANT SINGH JAMWAL
sanjeev singh
Mahmood Khan Govt. Contractor
Shiv Kumar Khajuria
Shah Nawaz
M/S KULBIR SINGH
Satish Samyal
Zaffer Iqbal Contractor
stage.html
html • 0.06 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.05 MB
BOQ_173152.xls
BOQ • 0.27 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .