Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.3 CrAccepted-Finance 5 255 1 EB COLONY SALAIPUDUR KOVILPATTI 628 503 | KOVILPATTI | THOOTHUKUDI | TAMIL NADU | 628503 | ₹1.3 Cr | L1 | Accepted-Finance lowest rate |
| 2 | L2₹1.5 Cr+₹22.7 L (17.9%)Accepted-Finance | ₹1.5 Cr+₹22.7 L (17.9%) | L2 | Accepted-Finance highest rate |
| 3 | Rejected-Technical | - | - | Rejected-Technical BQR condition not satisfied |
| Sl No | Description | Qty | Unit | SHIVANI LAKSHMI CONSTRUCTION L2 | aakash construction L1 |
|---|---|---|---|---|---|
| 1.00 | Clearing juliflora jungle with uprooting including cost of all labour, lead, lift, etc., complete. | 280 | m² | 9 ₹2,520 Lowest | 9 ₹2,520 Lowest |
| 2.00 | Earth work excavation for foundation in all type of soils with an initial lead of 10 m and lift of 2 m for Road work, Fencing, Retaining wall, Gate pillar work including shoring, barricade arrangements and dewatering charges etc., complete. | 139.01 | m³ | 106.25 ₹14,769.81 | 106 ₹14,735.06 Lowest |
| 3.00 | Earthwork excavation and depositing on bank for foundation with initial lead of 10 m & initial lift of 2m in hard stiff clay, stiff black cotton hard red earth, shales, murram, gravel stoney earth, earth mixed with small size bouldersfor Control room, Cable duct, Culvert including shoring, barricade arrangements and dewatering charges etc., complete. | 207.4 | m³ | 250 ₹51,850 | 213 ₹44,176.2 Lowest |
| 4.00 | Earth work excavation for foundation in all type of soils with an initial lead of 10m and lift of 2m-MR and DMR not requiring blasting for Road work, Fencing, Retaining wall, Gate work including shoring, barricade arrangements and dewatering charges etc., complete. | 79 | m³ | 300 ₹23,700 | 277 ₹21,883 Lowest |
| 5.00 | Earthwork excavation for foundation and depositing on bank with initial lead of 10m & initial lift of 2m in soft disintegrated rock laterite soft rock or kankar not requiring blasting for Control room, Cable duct, Culvert including shoring, barricade arrangements and dewatering charges etc., complete. | 155.55 | m³ | 350 ₹54,442.5 | 317 ₹49,309.35 Lowest |
| 6.00 | Earthwork excavation for foundation in medium rock and dense medium rock requiring blasting for Control room, Cable duct, Culvert including shoring, barricade arrangements and dewatering charges etc., complete. | 155.55 | m³ | 556 ₹86,485.8 Lowest | 556 ₹86,485.8 Lowest |
| 7.00 | Earth work excavation foundation in all type of soils with an initial lead of 10m and lift of 2m-Hard rock requiring blasting for Culvert, Retaining wall, Gate work including shoring, barricade arrangements and dewatering charges etc., complete | 36 | m³ | 1,000 ₹36,000 | 594 ₹21,384 Lowest |
| 8.00 | Supplying and filling of M sand in foundation and basement with well watering and consolidation as per specn. including cost of all materials labour, lead, lift, etc., complete. (As instructed by the Engineer at site) | 85.82 | m³ | 1,437 ₹1,23,323.34 Lowest | 1,437 ₹1,23,323.34 Lowest |
| 9.00 | PCC 1:3:6 mix using 40mm HBS machine crushed metal for foundation including cost of all labour, materials, lead, lift, curing, dewatering, etc., complete. | 150.5 | m³ | 5,017 ₹7,55,058.5 Lowest | 5,017 ₹7,55,058.5 Lowest |
| 10.00 | PCC 1:3:6 mix using 20mm HBS machine crushed metal for foundation including cost of all labour, materials, lead, lift, curing, dewatering etc., complete. | 2.6 | m³ | 5,388 ₹14,008.8 Lowest | 5,388 ₹14,008.8 Lowest |
Tender Value
Refer Docs
EMD Value
₹1.5 L
Closing Date
9 Oct 2025, 2:00 pmClosed
Chief Engineer, D, Tirunelveli
Office of the Chief Engineer , Distribution, Tirunelveli Region, Sivanthipatti Road, Tirunelveli-627011
Construction of Control room, Cable Duct, Revetment Wall, approach road, road Culvert, Yard filling, Fencing ,Bore well, water pipe line arrangements for earth pit, metal filling and entrance gate for the establishment of RAYAGIRI 33/11 KV SS in T
2025_EB_607870_1
CE/D/Tin/EE/Civil-03/2025-26
Open Tender
Civil Works
Item Rate
270 days
Rayagiri
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹1.5 L
Yes
21 Nov 2025
24 Sept 2025
10 Oct 2025
25 Sept 2025
9 Oct 2025
25 Sept 2025
25 Sept 2025 - 3 Oct 2025
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .