Tender Value
₹2.4 Cr
EMD Value
₹4.8 L
Closing Date
14 Jul 2026, 3:00 pm6d left
Executive Engineer
O/o Executive Engineer, PWD Division M-413, Under Ring Road Bypass Flyover, Opp. IGI Stadium Gate No. 9, New Delhi-110002
Construction of Precast RCC Storm Water Drain from Shantivan Red Light Service Lane to Vijay Ghat Drain under Sub Division-3 of Division (C and ND)- Roads during 2025-26.
2026_PWD_294977_1
55/SE/C and ND/PWD/2025-26 (Modified)
Open Tender
Civil Works - Roads
90 days
Sub. Division-3
Please refer Tender documents.
13 documents required · 13 mandatory
₹0
₹4.8 L
7 Jul 2026
7 Jul 2026
14 Jul 2026
7 Jul 2026
14 Jul 2026
7 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 0.0 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means over areas (exceeding 30cm in depth, 1.5m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth, lead up to 50m and lift up to 1.5m, as directed by Engineer-in-Charge. | - | - | - | - |
| 0.0 | All kinds of soil. | 1,188 | Cum | 177.5 | ₹2,10,870 |
| 0.0 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m. | 594 | Cum | 196 | ₹1,16,424 |
| 0.0 | Centering and shuttering including strutting, propping etc. and removal of form work for : | - | - | - | - |
| 0.0 | Foundations, footings, bases for columns | 135 | Sqm | 392.15 | ₹52,940.25 |
| 0.0 | Providing and laying in position ready mixed or site batched design mix cement concrete for plain cement concrete work; using coarse aggregate and fine aggregate derived from natural sources, Portland Pozzolana/ Ordinary Portland /Portland Slag cement, admixtures in recommended proportions as per IS: 9103 to accelerate / retard setting of concrete, to improve durability and workability without impairing strength; including pumping of concrete to site of laying, curing, carriage for all leads; but excluding the cost of centering, shuttering and finishing as per direction of the engineer-in-charge; for the following grades of concrete.
Note: Extra cement up to 10% of the minimum specified cement content
in design mix shall be payable separately. In case the cement content in design mix is more than 110% of the minimum specified cement content, the contractor shall have discretion to either re-design the mix
or bear the cost of extra cement | - | - | - | - |
| 0.9 | All works upto plinth level :
Concrete of M10 grade with minimum cement content of 220 kg /cum | 162 | Cum | 8,835.15 | ₹14,31,294.3 |
| 0.0 | Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge. | - | - | - | - |
| 0.9 | Nominal concrete 1:3:6 or richer mix (including equivalent
design mix) | 101 | Cum | 2,434.25 | ₹2,45,859.25 |
| 0.0 | Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge.. | - | - | - | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 4.52 MB
NIT.pdf
Tender Documents • 4.50 MB
BOQ_392419.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid