| 1 | 1₹7.0 CrAccepted-Finance PURULIA | WEST BENGAL | 723101 | ₹7.0 Cr | 1 | Accepted-Finance Technical and financial bid are in order. |
| 2 | 2₹7.9 Cr+₹91.2 L (13.1%)Accepted-Finance 2ND FLOOR 9 EZRA STREET KOLKATA WEST BENGAL 700001 | KOLKATA | KOLKATA | WEST BENGAL | 700001 | ₹7.9 Cr+₹91.2 L (13.1%) | 2 | Accepted-Finance Technical and financial bid are in order. |
Tender Value
₹6.9 Cr
EMD Value
₹13.7 L
Closing Date
11 Apr 2023, 3:00 pmClosed
EE, NACD, APWD, Mayabunder
EE, NACD, APWD, Mayabunder
Upgradation of Rural Road under Special Financial Assistance (SFA) at Mayabunder, North and Middle Andaman (HNRRR1106B, HNRRR1107B, HNRRR1101B and HNRRR1108B). (Total length 8.02 Km) (for 04 Works)
2023_APWD_9773_1
NIT NO.90/2022-23/EE/NACD
Open Tender
Civil Works - Roads
Works
540 days
EE, NACD, APWD, Mayabunder
Please refer Tender documents.
12 documents required · 12 mandatory
₹0
₹13.7 L
SE, CC-I, APWD, Port Blair
26 Apr 2023
16 Mar 2023
12 Apr 2023
16 Mar 2023
11 Apr 2023
16 Mar 2023
27 Mar 2023
Amount
Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per Technical Specification Clause 201 MORD . including contractors profit & Over head charges, etc., complete.
Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material with all lifts and lead upto 1000 m as per Technical Specification Clause 501.2.2 of MORD including contractors profit & Over head charges, etc., complete.
Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base course on a well prepared sub-base and compacting with Vibratory Roller 80-100 kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400.11 & 400.12 and Technical Specification Clause 406 MORD, including contractors profit & Over head charges etc., complete.
Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical Specification Clause 502 MORD (for use on Wet mix macadam & WBM) ,including contractors profit & Over head charges, etc., complete for Prime Coat
Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared granular surfaces treated with primer & cleaned with Hydraulic broom as per Technical Specification Clause 503 MORD, including contractors profit & Over head charges, etc., complete for Tack Coat
Providing and laying bituminous concrete 40 mm compacted thickness (8% of shredded waste plastic) with 40-60 TPH batch type hot mix plant producing an average output of 35 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder VG-30 @ 5.4 to 5.6 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 509 complete in all respects. Note: The Basic Rate of Shredded Waste plastic rates are provided by A&N Administration [Office order No.152, dated 10th January 2019].
Excavation for roadway in soil by mechanical means including cutting and pushing the earth to site of embankment upto a distance of 100 m, including trimming bottom and side slopes in accordance with requirements of lines, grades and cross-sections as per Technical Specification Clause 302.3 MORD. including contractors profit & Over head charges etc., complete
Construction of granular sub-base by providing well graded material(Table 400.1-A) with Grading III Material(HBG M/C +Stone dust) CBR Value not less than 20 and PI Value less than 6 spreading in uniform layers with Tractor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with Vibratory Roller to achieve the desired density, complete as per Technical Specification Clause 401 MORD including contractors profit & Over head charges, etc., complete.
Providing, laying, spreading and compacting stone aggregates of specific sizes for Grading 2 material to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with Vibratory roller 80-100 kN in stages to proper grade and camber, applying and brooming, stone screening/binding materials to fill-up the interstices of coarse aggregate, watering and compacting to the required density grading 2 as per Technical Specification Clause 405 MORD. For compacted thickness of 75 mm. including contractors profit & Over head charges, GST etc., complete for Grade II
Construction of un-reinforced, plain cement concrete pavement, thickness as per design, over a prepared sub base, as per Clause 1501.2.2 M30 (Grade), coarse and fine aggregates conforming to IS : 383, maximum size of coarse agregate not exceeding 25mm and cement content in the mix to be 350 kg /cum (Ordinary portland cement ) with minimum water cement ratio of 0.45, mixed in a concrete mixer and appropeiate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 mictron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with sholvels, rakes, compacted using needle, scareed and plate vibrators and finished in continuous operation including provision of contraction and construction joints, applying debonding strips, primer bitumenous sealant, admixers as adopted, curing of concrete slabs for 14- days, curing compound (where specified) and water finishing to lines and grade as per drawing and Technical Specification Clause 1501.22 MORD including cost of materials, labour charges, conveyance, hire charges of machinaries etc complete as per direction of Engineer in charge for CC pavement inlcuding contractors profit & Over head charges, etc., complete For 160mm thick with 2.50 m joint spacing.
Shotcreting R.C.C columns, beams and slabs etc. in layers with approved design mix concrete having the specified minimum characteristic compressive strength [with ordinary portland cement, coarse sand and graded stone aggregate of 10 mm maximum size in proportion as per design criteria] including the cost of centering and shuttering at edges and corners etc. as directed by Engineer-in-charge. Note : Rates shall include the providing necessary ground wires etc. the levelling gauges, if used be paid for separately, Payment under this item shall be made only after proper wet curing has been done and surface has been satisfactorily evaluated by sounding/tapping with a blunt metal instrument.
25mm thick in Grade M 25 with cement content not less than 330 kg per cum.
Construction of unlined surface drains of average cross-sectional area 0.40 sqm in soil to specified lines, grades, levels and dimensions. Excavated material to be used in embankment with a lift upto 3m and lead of 50 m (average lead 25 m) as per Technical Specification Clause 307.
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material as per Technical Specification 305 MORD / 304 MORTH, including contractors profit & Over head charges, etc., complete- For Foundations.
Providing concrete for plain concrete M-10 grade in open foundations using 40 mm nominal size hard stone aggregate (HBG), mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100 MORTH ,including contractors profit & Over head charges, etc., complete For levelling.
Reinforced cement concrete M20 grade (Design Mix) using 20 & 10mm metal (HBG) mechanically mixed in substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1206 MORD and 1500, 1700 & 2200 MORTH ,including contractors profit & Over head charges, etc., complete (upto 5m height)
Supplying, fitting and placing HYSD bar reinforcement (Fe 415) in substructure complete as per drawings and technical specification Clauses 1001 & 1206 MORD / Sections 1600 & 2200 MORTH for Bars below 36 mm dia including over laps and wastage, where they are not welded ,including contractors profit & Over head charges, etc., complete- For Sub Structures
Plastering with cement mortar (1:4) 15 mm thick, in substructure as per technical specification Clauses 613.4 & 1206 MORD including cost and conveyance of all materials, Overheads & contractor's profit, etc., complete.
Reinforced cement concrete M15 grade kilometre stone/local stone of standard design as per IRC:8 fixing in position including painting and printing, etc as per drawing and Technical Specification Clause 1703 MORD / 804 MORTH including contractors profit & Over head charges, GST etc., complete
Ordinary Kilometer Stone (Precast)
200 m / Hectometer stone (precast)
Painting lines, Dashes, Arrows, etc. on Road in Two Coats on New Work
Painting lines, dashes, arrows, etc. on roads in two coats on new work with ready mixed road marking paint conforming to IS:164 on bituminous/concrete surface, including cleaning the surface of all dirt, dust and other foreign matter, demarcation at site and traffic control as per drawing and Technical Specification Clause 1702
Providing and fixing of semi-reflective cautionery, mandatory and informatory boards as per IRC:67 made of 1.5mm thick MS sheet duly stove enamelled paint in white colour in front and grey colour on back with red reflective boarder of 65mm width and required letters and figures with reflective engineering grade tape as per clause 1701.3.8 of MORD for rural roads specification of required shade and colour supported and welded on 47x47mm of 12 SWG square tube of 3050mm height duly strenthened by 25x5mm MS flat iron on edges on back firmly fixed to ground by means of properly designed foundations with M-15 grade CC 450x450x600 mm , 600mm below ground level as per approved drawings and technical specification Clause 1701.2.2 of MORD including contractors profit & Over head charges, including CPOH, cess & GST etc., complete with 600X 600 mm size MS sheet
i) Providing Cautionary Board at Curves ii) SFA logo board iii) Indicative board
Provision towards citizen Boards
Provision towards Mtc Boards
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202 MORD, including contractors profit & Over head charges, etc., complete.
Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1.
Removal of unsuitable soil including excavation, loading and disposal upto 1000 m lead but excluding compaction ground supporting embankment subgrade replacement by suitable soil, which shall be paid separately as per Clause 303.5.2 as per Technical Specification Clause 302.3.11
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material as per Technical Specification 305 MORD / 304 MORTH, including contractors profit & Over head charges, etc., complete- For Foundations
1 Row 2 Row
Providing concrete for plain concrete in open foundation using 40mm nominal size har stone aggregate (HBG), mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days complete as per drawings and technical specification's clause 802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100 MORTH including contractor's profits and overhead charges etc for complete levelling course.
1 Row 2 Row
Providing concrete for plain concrete M15 grade for pipe beddeing using 40mm hard stone aggregate (HBG), mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days complete as per drawings and technical specification's clause 802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100 MORTH including contractor's profits and overhead charges etc for complete levelling course.
1 Row 2 Row
Providing concrete for plain concrete M15 grade using 40, 20 & 10 mm metal (HBG) mechanically mixed in foundation complete as per the drawing and technical specification clauses 802, 804, 805, 806, 807, 1202 & 1203 MORD and 1500, 1700 & 2200 MORTH including contractor's profits and overhead charges etc. complete.
1 Row 2 Row
Providing and laying reininforcement cement conrete pipe NP3 for culverts on 1st class bedding of granule material including fixing collar with cement morta 1:3 but excluding exavation protection works, back filing, concrete and machinery works in head wall and parapets. technical specification Clause 1101.6 MORD including contractor's profit and overhead charges etc complete for pipe culverts.
1 Row 2 Row
Providing concrete for plain concrete M15 grade using 40, 20 & 10 mm metal (HBG) mechanically mixed in substructure complete as per the drawing and technical specification clauses 802, 804, 805, 806, 807, 1202 & 1206 MORD and 1500, 1700 & 2200 MORTH including contractor's profits and overhead charges etc. complete.
1 Row 2 Row
Providing and laying boulder apron for bed protection with stone boulder of minimum size and wieght as per Table 1300.1 no fragment weighing less than 25/40 kg laid dry complete as per drawing and technical specifications Clause 1301 MORD/ 2503 MORTH including contractor's profit & Over head charge etc. complete.
1 Row 2 Row
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material as per Technical Specification 305 MORD / 304 MORTH, including contractors profit & Over head charges, etc., complete- For Foundations
Providing concrete for plain concrete in open foundations using 40 mm nominal size hard stone aggregate (HBG), mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100 MORTH ,including contractors profit & Over head charges, etc., complete For levelling course
P.C.C grade M 10
Plain cement concrete M 15 grade using 40,20 & 10mm metal (HBG) mechanically mixed in substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1206 MORD and 1500, 1700 & 2200 MORTH ,including contractors profit & Over head charges, etc., complete-
For Abutments & wing walls of slab culvert, Retaining walls
Providing weep holes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification Clauses 614, 709, 1206.6 MORD / 2706 & 2200 MORTH including contractors profit & Over head charges, etc., complete
Routine Maintenance after completion of work (i) Routine maintenance cost for 1st Year (6,13,498.00 (ii) Routine maintenance cost for 2nd Year (7,45,925.00 ) (iii) Routine maintenance cost for 3rd Year (9,25,044.00) (iv) Routine maintenance cost for 4th Year (11,04,637.00) (v) Routine maintenance cost for 5th Year (12,90,988.00) Total of Maintenance Cost for 05 Years (46,80,092.00) (Same rate to be quoted i.e. 46,80,092.00) [NOTE: For routine maintenance, the unit rate indicated by the authority shall apply. The bidder is required to accept these rates. Further, the payment shall be performance based.
Surendra Infrastructure Pvt. Ltd.
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .