| 1 | L1₹2.8 LAccepted-AOC 01 KHANRA DEULGRAM BAGNAN DEULGRAM BAGNAN HOWRAH WEST BENGAL 711303 | HOWRAH | WEST BENGAL | 711303 | ₹2.8 L | L1 | Accepted-AOC lowest bid |
| 2 | L2₹2.8 L+₹2,805 (1.00%)Rejected-Finance | ₹2.8 L+₹2,805 (1.00%) | L2 | Rejected-Finance high bid |
| 3 | L3₹2.8 L+₹1,402 (0.50%)Rejected-Finance | ₹2.8 L+₹1,402 (0.50%) | L3 | Rejected-Finance high bid |
Tender Value
₹2.8 L
EMD Value
₹5,700
Closing Date
7 Jul 2026, 11:00 amClosed
Executive Engineer(Civil)
Office Of The Executive Engineer ( C ), Borough - XV, Kolkata Municipal Corporation, E/3, Circular Garden Reach Road Kolkata-700024.
REMOVAL OF SILT FROM NIKASHI DRAIN WITH ANCILERY WORKS AT SANTOSHPUR ROAD, UMESH NEOGY ROAD, DEWAN BAGAN, SHIMPUKUR LANE ETC IN WARD NO-136, UNDER BR-XV
2026_KMC_1029701_1
KMC/EE(C)/Br- XV/136/002/2026-2027/R(2nd Call)
Open Tender
CIVIL WORKS
Percentage
150 days
Borough XV office
please prefer tender document
4 documents required · 4 mandatory
₹0
₹5,700
18 Aug 2026
27 Jun 2026
9 Jul 2026
27 Jun 2026
7 Jul 2026
27 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Supplying empty Cement bags in good condition. | 3.5 | NOS | 330 | ₹1,155 |
| 2 | MATERIALS AND LABOUR 1. Building (A) Materials delivered and stacked at site: 6)d)Silver Sand. Note: 1. The above rates are inclusive of all charges such as Royalty, Supervision Charges, etc. and also include allowance for sinkage, as applicable, and/or shrinkage and 10% Contractor?s Profit but exclusive of GST 2. Rates for Sand and Brick/ Jhama/ Bats items are complete rates at site and no other costs need to be considered. For other items, necessary loading-unloading & carriage charges are admissible. 3. Laterrite Boulder &Moorum are available in the districts as mentioned in Sl. No. ? 23 & 24 respectively, remaining districts may add necessary carriage cost as applicable. | 12.14 | M3 | 667 | ₹8,097.38 |
| 3 | Filling empty Cement bags with dry earth or sand stitching the bag(cost of the thread include) and carrying and placing them in position and all incidental charges complete but excluding cost of sand and gunny bags. | 3.5 | NOS | 350 | ₹1,225 |
| 4 | DEWATERING OF DRAINAGE WATER FROM SURFACE DRAIN BY 3''DIA PUMP | 240 | HR | 70 | ₹16,800 |
| 5 | MATERIALS AND LABOUR ETC.(C)-(I) MISCELLANEOUS 28.Cleaning rubbish, sludge, weeds scum, liquid earth, mud etc.etc.from road side masonary drain/ hume pipe drain/ culvert etc. by mathor labour after removing concrete.Slab/manhole cover etc.without damaging the same and refixing the same properly after cleaning as necessary and removing thesludge etc.etc.by using iron pans,buckets including all labour, tools & plants including removing the spoils in dry condition and disposing thesame by truck beyond the road side in conformity with municipal/corporation rules for such disposal including loading into truck and cleaning the road side in all respects as per direction of the Engineerin- Charge. (Payment will be made on the basis of actual stack measurment of spoils in dry condition at roadside) | 273.31 | M3 | 289 | ₹78,986.88 |
| 6 | (C) III: Labour Rate for Sanitary and Plumbing 4.Methor Mazdoor NOTE:The above rates are exclusive of 10 % profit and 1% Labour welfare cess, which would be admissible to the Contractor, but contractual percentage will not be applicable on the above rates.Page 113 of 124 | 480 | EA | 296 | ₹1,42,080 |
| 7 | MATERIALS AND LABOUR 1. Building (B) Labour Rates Per Diem : 3)Mazdoor (Male). Note: (I)The above rates of labour are exclusive of 10% contractors profit and 1% Labour welfare cess which would be admissible to the Contractors, but contractual percentage will not be applicable. (II) The workersemployed on high rise building or any structure over 30 ft in height and also workers engaged in Tunnel shall be paid 20% extra wages. | 120 | EA | 245 | ₹29,400 |
| 131 | Estimated amount | - | - | - | - |
| 134 | 1% LWC | - | LS | 2,443.73 | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.34 MB
TENDER.pdf
Tender Documents • 0.58 MB
BOQ_2528759.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .