| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹14.9 LAdmitted-Finance | -14.00% | ₹14.9 L | L1 | Admitted-Finance |
| 2 | L2₹15.4 L+₹41,706.84 (2.79%)Admitted-Finance | -11.60% | ₹15.4 L+₹41,706.84 (2.79%) | L2 | Admitted-Finance |
| 3 | L3₹15.6 L+₹69,511.39 (4.65%)Admitted-Finance | -10.00% | ₹15.6 L+₹69,511.39 (4.65%) | L3 | Admitted-Finance |
| 4 | L4₹16.0 L+₹1.0 L (6.98%)Admitted-Finance | -8.00% | ₹16.0 L+₹1.0 L (6.98%) | L4 | Admitted-Finance |
| 5 | Not Admitted-Fee/PreQual/Technical | - | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹17.4 L
EMD Value
₹34,756
Closing Date
20 May 2026, 3:00 pmClosed
Executive Engineer
O/o Inspector General, Frontier Hqr SSB Siliguri
Upgradation and construction of existing internal road at Bn Hqr of 69 Bn SSB Pakyong under Frontier Hqr SSB Siliguri
2026_SSB_908279_1
FTRS/40/26
Open Tender
Civil Works
Percentage
270 days
69 Bn SSB Pakyong
As Per NIT
2 documents required · 2 mandatory
₹0
₹34,756
FTR HQR SSB Siliguri
2 Jun 2026
12 May 2026
21 May 2026
12 May 2026
20 May 2026
13 May 2026
13 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as
well as 10 sqm on plan) including getting out and disposal of excavatedearth lead upto 50 m and for all lift, as directed by Engineer-in-charge.All kinds of soil | 143.1 | cum | 241.79 | ₹34,600.15 |
| 2 | Providing and laying in position cement concrete of specified gradeexcluding the cost of centering and shuttering - All work up to plinthlevel :1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from
natural sources : 8 graded stone aggregate 40 mm nominalsize derived from natural sources) | 7.38 | cum | 9,279.31 | ₹68,481.31 |
| 3 | Providing and laying cement concrete in retaining walls, return walls,walls (any thickness) including attached pilasters, columns, piers,abutments, pillars, posts, struts, buttresses, string or lacing courses,parapets, coping, bed blocks, anchor blocks, plain window sills, fillets,sunken floor etc., up to floor five level, excluding the cost of centering,shuttering and finishing:1:3:6 (1 cement : 3 coarse sand (zone-III) derived fromnatural sources : 6 graded stone aggregate 20 mm nominal
size derived from natural sources | 6.3 | cum | 12,683.99 | ₹79,909.14 |
| 4 | Centering and shuttering including strutting, propping etc. and removalof form work for :Foundations, footings, bases for columns | 14.5 | sqm | 534.19 | ₹7,745.76 |
| 5 | Providing and laying in position specified grade of reinforced cementconcrete, excluding the cost of centering, shuttering, finishing andreinforcement - All work up to plinth level :1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived fromnatural sources : 3 graded stone aggregate 20 mm nominalsize derived from natural sources) | 44.83 | cum | 12,322.12 | ₹5,52,400.64 |
| 6 | Centering and shuttering including strutting, propping etc. and removalof form for Foundations, footings, bases of columns, etc. for mass
concrete | 25.44 | sqm | 534.19 | ₹13,589.79 |
| 7 | Centering and shuttering including strutting, propping etc. and removalof form for Walls (any thickness) including attached pilasters,
butteresses, plinth and string courses etc. | 161.34 | sqm | 1,157.65 | ₹1,86,775.25 |
| 8 | Centering and shuttering including strutting, propping etc. and removalof form for Suspended floors, roofs, landings, balconies and access
platform | 18.08 | sqm | 1,263.1 | ₹22,836.85 |
| 9 | Steel reinforcement for R.C.C. work including straightening, cutting,bending, placing in position and binding all complete upto plinth level Thermo-Mechanically Treated bars of grade Fe-500D or
more. | 4,278.58 | kg | 148.91 | ₹6,37,123.35 |
| 10 | Random rubble masonry with hard stone in foundation and plinth includinglevelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12graded stone aggregate 20 mm nominal size) upto plinth level with :7.1.1 Cement mortar 1:6 (1 cement : 6 coarse sand) | 13.46 | cum | 9,979.38 | ₹1,34,322.45 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.61 MB
BOQ_954795.xls
BOQ • 0.38 MB
TenderROAD.pdf
Tender Documents • 1.60 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .