| 1 | L-1₹48.3 LAccepted-AOC V P O JHAKRI TEHSIL RAMPUR DISTT SHIMLA | SHIMLA | HIMACHAL PRADESH | 171001 | L-1 | Accepted-AOC Work awarded to lowest Contractor. Hence, EMD may be released in his favour. | |
| 2 | L-2₹53.3 L+₹1.4 L (2.62%)Rejected-Finance | L-2 | Rejected-Finance Due to L-2. Hence EMD may be released |
Tender Value
₹47.2 L
EMD Value
₹95,000
Closing Date
29 Jun 2024, 5:30 pmClosed
Executive Engineer
Executive Engineer, Kalpa Division, HPPWD Kalpa, Distt. Kinnauar HP
Balance work for C/O Govt. Middle School Building at Charang in District Kinnaur (HP) (SH- C/O Frame work and masonry work of building portion, C/O Septic Tank and Soak pit
2024_PWD_89148_6
PW-KNR-E-Tender/24-913-25 dated 07-06-2024
Open Tender
Civil Works - Buildings
Item Rate
365 days
Charang, under Moorang Sub Division
Please refer Tender documents.
7 documents required · 7 mandatory
₹2,000
₹95,000
13 Sept 2024
15 Jun 2024
1 Jul 2024
15 Jun 2024
29 Jun 2024
15 Jun 2024
Amount
Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (within all lead and lift) , including dressing of sides and ramming of bottoms, including getting out the excavated soil and disposal of surplus excavated soil as directed, All kind of soil, including carriage of materials through all modes of transportation with in all leads and lifts, as per PWD specifications and as per direction of the Engineer-in-charge.
Centering and shuttering including strutting, propping etc. and removal of form for : including carriage of materials through all modes of transportation with in all leads and lifts, as per PWD specifications and as per direction of the Engineer-in-charge.
Foundations, footings, bases of columns, etc. for mass concrete
Suspended floors, roofs, landings, balconies and access platform
Suspended floors, roofs, landings, balconies and access platform
Columns, Pillars, Piers, Abutments, Posts and Struts.
Lintels, beams, plinth beams, girders, bressumers and cantilevers
Edges of slabs and breaks in floor and walls
Edges of slabs and breaks in floor and walls
Cornices and mouldings
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:5:10 (one cement : five fine sand : Ten graded stone) aggregate 40 mm (Forty millimeter) nominal size, including carriage of materials through all modes of transportation with in all leads and lifts, as per PWD specifications and as per direction of the Engineer-in-charge.
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:4:8 (One Cement : four coarse sand : eight graded stone) aggregate 40 mm (fory millimeter) nominal size, including carriage of materials through all modes of transportation with in all leads and lifts, as per PWD specifications and as per direction of the Engineer-in-charge.
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:4:8 (One Cement : four coarse sand : eight graded stone) aggregate 40 mm (fory millimeter) nominal size, including carriage of materials through all modes of transportation with in all leads and lifts, as per PWD specifications and as per direction of the Engineer-in-charge.
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level 1:2:4 (one cement : two coarse sand : four graded stone) aggregate 20 mm (twenty millimeter nominal size), including carriage of materials through all modes of transportation with in all leads and lifts, as per PWD specifications and as per direction of the Engineer-in-charge.
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level 1:2:4 (one cement : two coarse sand : four graded stone) aggregate 20 mm (twenty millimeter nominal size), including carriage of materials through all modes of transportation with in all leads and lifts, as per PWD specifications and as per direction of the Engineer-in-charge.
Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (One cement : one point five coarse sand) : three graded stone aggregate 20 mm (twenty milimeter nominal size), including carriage of materials through all modes of transportation with in all leads and lifts, as per PWD specifications and as per direction of the Engineer-in-charge.
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. Thermo-Mechanically Treated bars of grade Fe-500D or more, including carriage of materials through all modes of transportation with in all leads and lifts, as per PWD specifications and as per direction of the Engineer-in-charge.
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. Thermo-Mechanically Treated bars of grade Fe-500D or more, including carriage of materials through all modes of transportation with in all leads and lifts, as per PWD specifications and as per direction of the Engineer-in-charge.
Providing and laying brick masonry using common burent clay building bricks in Rat trap bond masonary (on 3" Edge) in cement mortar 1:4 (one cement : four sand) second class bricks., including carriage of materials through all modes of transportation with in all leads and lifts, as per PWD specifications and as per direction of the Engineer-in-charge.
Half brick masonry with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 (seven point five) in superstructure above plinth level up to floor V level. Cement mortar 1:4 (one cement : four coarse sand), including carriage of materials through all modes of transportation with in all leads and lifts, as per PWD specifications and as per direction of the Engineer-in-charge.
Half brick masonry with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 (seven point five) in superstructure above plinth level up to floor V level. Cement mortar 1:4 (one cement : four coarse sand), including carriage of materials through all modes of transportation with in all leads and lifts, as per PWD specifications and as per direction of the Engineer-in-charge.
Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (one cement : six coarse sand : twelve graded stone aggregate 20 mm (twenty millimeter) nominal size upto plinth level with : Cement mortar 1:6 (one cement : six coarse sand), including carriage of materials through all modes of transportation with in all leads and lifts, as per PWD specifications and as per direction of the Engineer-in-charge.
Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (one cement : six coarse sand : twelve graded stone aggregate 20 mm (twenty millimeter) nominal size upto plinth level with : Cement mortar 1:6 (one cement : six coarse sand), including carriage of materials through all modes of transportation with in all leads and lifts, as per PWD specifications and as per direction of the Engineer-in-charge.
Boulder filling tightly hand packed under floors, , including carriage of materials through all modes of transportation with in all leads and lifts, as per PWD specifications and as per direction of the Engineer-in-charge.
Precast concrete block masonry (including quion blocks, Jamb blocks, closer etc.) with solid concrete blocks of approved sizemade of cement concrete 1:3:6 (one cement : three coarse sand : six graded stone aggregate 40 mm (forty milimeter millimeter) nominal size and down gauge) foundation and plinth upto all floor level with : Cement mortar 1:6 (one cement : six coarse sand), including carriage of materials through all modes of transportation with in all leads and lifts, as per PWD specifications and as per direction of the Engineer-in-charge.
15mm (fifteen milimeter) cenment plaster on rough side of single or half brick wall of mix: 1:4 (one cement : four coarse sand) complete upto floor all level, including entire carriage of materials in all leads and lifts and as per drawing and technical specifications as per the direction of Engineer-in-charge including all incidentals. The rates are inclusive of octroi, royality, malkana, toll tax, sale tax, GST or other taxes imposed by the Government.
UMA SHANKAR CONTRCATOR
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .