Tender Value
₹2.6 Cr
EMD Value
₹5.2 L
Closing Date
21 Jul 2026, 6:00 pm
SE PWD CIRCLE SIKAR
SE PWD CIRCLE SIKAR
Construction of road on Bagoli Thikariya MDR-276 in Gram Jajod (1.10km) Ch50/475 to Ch51/575
2026_CEPWD_569396_5
NIT 01/2026-27 SE PWD Circle Sikar
Open Tender
Civil Works
240 days
SIKAR
Please refer Tender Documents.
2 documents required · 2 mandatory
₹2,000
Through online eGRAS Challan Sikar 14116
₹5.2 L
Yes
7 Jul 2026
7 Jul 2026
22 Jul 2026
7 Jul 2026
21 Jul 2026
7 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | PART 'A' - ROAD WORK | - | - | - | - |
| - | Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per MoRTH Specification Clause 201. By Mechanical Means. In area of non-thorny jungle | 0.39 | Hect | 10,374 | ₹4,045.86 |
| - | Dismantling of Cement Concrete Pavements as per MoRTH Specification Clause 202.
Dismantling of cement concrete pavements by mechanical means using pneumatic tools breaking to pieces not exceeding 0.02 cum in volume and stock piling at designated locations and disposal of dismantled materials upto a lead of 1000 m, stacking serviceable and unserviceable materials separately. | 261 | Cum | 515 | ₹1,34,415 |
| - | Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per MoRTH Specification Clause 202. By mechanical means Cement Concrete | 1,120 | Cum | 252 | ₹2,82,240 |
| - | Excavation in Ordinary Rock using Hydraulic Excavator and Tippers with disposal upto 1000 m Excavation for road way in ordinary rock with hydraulic excavator of 0.9
cum bucket capacity including cutting and loading in tippers, transporting to embankment sitewitha liftupto1.5mand leadupto 1000 m, trimming bottom and side slopes in accordance with requirements of lines, grades and cross-sections as per MoRTH Specification Clause 301.3.5 | 675 | Cum | 36 | ₹24,300 |
| - | Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300-1 and 300-2 with a lead upto 50 m as per MoRTH Specification Clause 305.3 | 540 | Cum | 44 | ₹23,760 |
| - | Granular Sub-Base with Close Graded Material (Table:- 400-1)
Plant Mix Method
Providing laying spreading and compacting specified graded sand, gravel (crushedstone)as per Table 400-1,400-2 or any other course material as per design mix, as per CBR in sub base course including premixing thematerial atOMC inwetmixplant, carriage of mixed material spreading in uniform layers with motor grader F.Eloaderona prepared base and compacting with vibratory roller toachievedesired density (as per I.S.2720) including all material, labor, machinery, lighting guarding, barricading and maintenance of diversion complete . [MoRTHspecification :Clause401]. By mechanical means with a lead of 1 Km. For All Rajasthan except Bikaner, Churu, Hanumangarh and SriGanganagar For Grading-I Material | 1,424.5 | Cum | 773 | ₹11,01,138.5 |
| - | Construction of dry lean cement concrete Sub- base over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement content not to be less than 150 kg/ cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching plant, transported to site, laid with a paver with electronic sensor, compacting with 8-10 tonnes vibratory roller, finishing and curing. For All Rajasthan except Bikaner, Churu, Hanumangarh and SriGanganagar | 1,155 | Cum | 2,418 | ₹27,92,790 |
| - | Cement Concrete Pavement with Slip Form Paver
Construction of un-reinforced , plain cement concrete pavement M-40 (Grade), thickness as per design, over a prepared sub base, with 43/53 grade cement as per Clause 602, coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 31.5 mm, mixed in a in fully automatic computerised compatible with Printer and Pen Drive Batching Plant and transported to site in transit mixer for having continous agitated mixer, manufactured as per approved mix design including pumping of R.M.C. from transit mixer to site of laying , with all lead and lift including cost of admixtures in recommended portion as per IS 9103 to accelerate/ retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer in charge laid with a Slip Form Paver (laying and fixing of 150 micron thick polythene film) and finished in continuous operation including provision of contraction and expansion, construction joints, applying debonding strips, primer, sealant near approaches to bridge/culvert and construction joints, admixtures as approved, curing of concrete slabs for 14-days using water finishing to lines and grade as per drawing and MoRTH Specification Clause 602 should have minimum flexural strengthen of 4.5 MPa, with all required equipments. (Dowel Bars and Tie Bars will be paid seprately). | 1,925 | Cum | 6,053 | ₹1,16,52,025 |
| - | Providing and Fixing of Dowel Bars of Mild Steel confirming to IS : 432 of specified length and diameters as per MoRTH Specification IRC 15 & 58 including cutting, placing in position across transverse joint with proper spacing, providing with PVC sleeve complete as per drawing, technical specification and as per direction of the Engineer-in-charge. | 2,000 | Kg | 66 | ₹1,32,000 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 4.10 MB
Tendernotice_2.pdf
PDF • 11.68 MB
BOQ_1013255.xls
BOQ • 0.29 MB
05Component.pdf
Other Document • 0.56 MB
05Rate_Analysis_MDR_276_Jajod_Reengus.pdf