| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹17.2 LAccepted-AOC MADURAI | TAMIL NADU | 625001 | ₹17.2 L Quoted ₹12.9 L | L1 | Accepted-AOC L1 Accept |
| 2 | L2₹12.9 LRejected-Finance ERODE | TAMIL NADU | 638451 | ₹12.9 L | L2 | Rejected-Finance L2 Reject |
| Sl No | Description | Qty | Unit | S.MURUGANANTHAM L1 | C. PADIKKASU L2 |
|---|---|---|---|---|---|
| 1.00Construction of weir at Vayalangudi Kanmai in Embal Panchayat | |||||
| 2.00 | Earth work excavation for foundation in all soils such as red earth, hard stiff clay soil, stiff black cotton soil, hard red earth, shales, murrams, gravel hard rock requiring blasting etc., complete | 57.42 | Cum | 263.5 ₹15,130.17 | 265 ₹15,216.30 |
| 3.00 | Dismantling with out damaging the near by structures if any, clearing away and carefully stacking materials useful for reuse for any thickness of wall in brick masonry in cement mortar wall under 3m High as directed by the Engineer in charge of the works as per technical Specification | 27.58 | Cum | 302.5 ₹8,342.95 | 305 ₹8,411.90 |
| 4.00 | Dismantling with out damaging the near by structures if any, clearing away Plain cement concrete as directed by the Engineer in charge of the works as per technical Specification | 13.58 | Cum | 520 ₹7,061.60 | 525 ₹7,129.50 |
| 5.00 | Earth work excavation for foundation in all soils such as red earth, hard stiff clay soil, stiff black cotton soil, hard red earth, shales, murrams, gravel hard rock requiring blasting etc., complete | 58.56 | Cum | 263.5 ₹15,430.56 | 265 ₹15,518.40 |
| 6.00 | Filling with M.sand and filling in to the basement including cost and conveyance to the siteand all labour charges for filling as per standard speecifications | 11.75 | Cum | 2,100 ₹24,675 | 2,150 ₹25,262.50 |
| 7.00 | Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete | 51.97 | Cum | 6,273 ₹3.3 L | 6,280 ₹3.3 L |
| 8.00 | Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete | 73.94 | Cum | 7,381.5 ₹5.5 L | 7,390 ₹5.5 L |
| 9.00 | Refilling with excavatd soil other than sand complying with the standard specification for filling all cost and conveyance etc., complete | 38.28 | Cum | 45 ₹1,722.60 | 48 ₹1,837.44 |
| 10.00 | Providing Steel Centering for RCC Slabs, beams of plain surfaces including strutting 3m height using MS Sheet, BG 10 gauge thick of size 90 x 60 cm BG 10 gauge stiffened with MS angles of size 25 x 25 x 3mm laid over silver oak joists os size 10cm 6.50 cm spaced at about 90cm and supported by causrina props of 10cm to 13cm dia spaced about 75cm centre to centre and removing the centering and strutting after specified period without damaging the concrete laid complying with standard specification and as directed by the Engineer
Below Sill Level | 110.95 | Sqm | 516 ₹57,250.20 | 525 ₹58,248.75 |
Tender Value
₹13 L
EMD Value
₹13,000
Closing Date
13 Mar 2026, 3:00 pmClosed
BDO, Arimalam
Pt. Union office, Arimalam
Construction of Weir at Vayalangudi Kanmai in Embal Panchayat
2026_RDTN_673015_1
Arm/QuarryFund/Work--2
Open Tender
Civil Works
Arimalam
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹13,000
7 Apr 2026
11 Mar 2026
13 Mar 2026
11 Mar 2026
13 Mar 2026
11 Mar 2026
Construction of weir at Vayalangudi Kanmai in Embal Panchayat
Earth work excavation for foundation in all soils such as red earth, hard stiff clay soil, stiff black cotton soil, hard red earth, shales, murrams, gravel hard rock requiring blasting etc., complete
Dismantling with out damaging the near by structures if any, clearing away and carefully stacking materials useful for reuse for any thickness of wall in brick masonry in cement mortar wall under 3m High as directed by the Engineer in charge of the works as per technical Specification
Dismantling with out damaging the near by structures if any, clearing away Plain cement concrete as directed by the Engineer in charge of the works as per technical Specification
Earth work excavation for foundation in all soils such as red earth, hard stiff clay soil, stiff black cotton soil, hard red earth, shales, murrams, gravel hard rock requiring blasting etc., complete
Filling with M.sand and filling in to the basement including cost and conveyance to the siteand all labour charges for filling as per standard speecifications
Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete
Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete
Refilling with excavatd soil other than sand complying with the standard specification for filling all cost and conveyance etc., complete
Providing Steel Centering for RCC Slabs, beams of plain surfaces including strutting 3m height using MS Sheet, BG 10 gauge thick of size 90 x 60 cm BG 10 gauge stiffened with MS angles of size 25 x 25 x 3mm laid over silver oak joists os size 10cm 6.50 cm spaced at about 90cm and supported by causrina props of 10cm to 13cm dia spaced about 75cm centre to centre and removing the centering and strutting after specified period without damaging the concrete laid complying with standard specification and as directed by the Engineer Below Sill Level
Providing Steel Centering for RCC Slabs, beams of plain surfaces including strutting 3m height using MS Sheet, BG 10 gauge thick of size 90 x 60 cm BG 10 gauge stiffened with MS angles of size 25 x 25 x 3mm laid over silver oak joists os size 10cm 6.50 cm spaced at about 90cm and supported by causrina props of 10cm to 13cm dia spaced about 75cm centre to centre and removing the centering and strutting after specified period without damaging the concrete laid complying with standard specification and as directed by the Engineer Above Sill Level
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 1 & 11 of Section 2 of Instruction to Bidders (ITB) of SBD)
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
techsummary_808830.pdf
BOQ Comparative Chart
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.14 MB
Arm_doc--2.pdf
Tender Documents • 0.18 MB
BOQ_808830.xls
BOQ • 0.45 MB
Download all tender documents and submit your bid