Tender Value
₹1.5 L
EMD Value
₹3,020
Closing Date
27 Oct 2026, 2:00 pm
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Executive Engineer
Irrigation Division Kulgam
Restoration of left right side embankment by way of construction of lining wall and breast wall near RD 350 mts of Main Banimullah Canal
2026_IFC_328354_8
eNIT No. 15 of 2026-27
Open Tender
Civil Works - Canal
Percentage
10 days
Kulgam
Please refer Tender documents.
2 documents required · 2 mandatory
₹300
MH 0702
₹3,020
15 Oct 2026
15 Oct 2026
27 Oct 2026
15 Oct 2026
27 Oct 2026
15 Oct 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in bulk excavation by manual means over areas (exceeding 30 cm indepth, 1.5 m in width as well as 10 m2 on plan) including disposal of excavated earthlead upto 50 meters and lift upto 1.5 m, as directed by Engineer-in-Charge.All kinds of soil : | 11.63 | cum | 592.9 | ₹6,895.43 |
| 2 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with::3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) | 18.36 | cum | 5,733.6 | ₹1,05,268.9 |
| 3 | Centering and shuttering including strutting, propping etc. and removal of form work for: Foundations, footings, bases for columns | 12 | sqm | 286.35 | ₹3,436.2 |
| 4 | Centering and shuttering including strutting, propping etc. and removal of form work for:Retaining walls, return walls, walls (any thickness) including attached pilasters buttresses, plinth and string course fillets, kerbs andsteps etc. | 21.6 | sqm | 628.95 | ₹13,585.32 |
| 5Carriage of material by Mechanical transport and Headload from source to actual site of work including loading,unloading ,stacking complete job. | |||||
| 5.1 | Sand for an average lead of 17 km by MT and 300 mts by HL | 8.26 | cum | 789.79 | ₹6,523.67 |
| 5.2 | 20 mm Agg. for an average lead of 15 km by MT and 300 mts by HL | 16.52 | cum | 763.61 | ₹12,614.84 |
| 5.3 | Cement for an average lead of 9 km by MT and 300 mts by HL | 4.04 | MT | 435.58 | ₹1,759.74 |
| 6 | Providing,printing and arranging color photographs of the work at various stages of execution, along with printing of nessary supporting documents records and other relevant documents required for prepration varification and processing of bills, complete in all respects as directe by Engineer in charge . | 10 | L.S | 60 | ₹600 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.96 MB
BOQ_1111578.xls
BOQ • 0.27 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .