Tender Value
₹98.8 Cr
EMD Value
₹2.0 Cr
Closing Date
17 Jun 2026, 11:00 amClosed
Yes (up to 3 members)
No
Two Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
90 days
Expenditure
Capital (Works)
ENGG WORK
15 conditions · 4 needing a document upload
Financial Eligibility Criteria: The tenderer must have minimum average annual contractual turnover of V/N or 'V' whichever is less; where V= Advertised value of the tender in crores of Rupees. N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of 'total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. The tenderers shall submit requisite information as per Annexure-VI B, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet Note: the financial turnover of 2024-25 of the bidder has not been audited then certificate of C.A. is required that the balance sheet of financial year has not been audited. If the bidder have not submitted the certificate then the financial turnover of the 2024-25 will be taken as Nil and average of three financial year will be considered for conractual reciept 2022-23 & 2023-24 as per factual based on Audited balance Sheet and for 2024-25 as Nil.
Financial Eligibility Criteria:For tenders having advertised value more than Rs 10 crore wherein eligibility criteria includes bid capacity also, the tenderer will be qualified only if its available bid capacity is equal to or more than the total bid value of the present tender. The available bid capacity shall be calculated as under: Available Bid Capacity = [A x N x 2] - 0.33xNxB Where, A= Maximum value of construction works executed and payment received in any one of the previous three financial years or the current financial year (up to date of inviting tender), taking into account the completed as well as works in progress. N=Number of years prescribed for completion of work for which bids has been invited. B = Existing commitments and balance amount of ongoing works with tenderer as per the prescribed proforma of Railway for statement of all works in progress and also the works which are awarded to tenderer but yet not started up to the date of inviting of tender.
Technical Eligibility Criteria: (a) The tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: (i) Three similar works each costing not less than the amount equal to 30% of advertised value of the tender, or (ii) Two similar works each costing not less than the amount equal to 40% of advertised value of the tender, or (iii) One similar work costing not less than the amount equal to 60% of advertised value of the tender.
The "Similar Work" is defined as "Any bridge work involving erection/launching or Regirdering of Plate girder/Open web girder/Composite bridge/Bowstring Arch bridge"
54 conditions · 7 needing a document upload
Tenderers are advised to visit the site of work to ascertain all aspects of thesite conditions viz accessibility, availability of approach road, nature of the soil, availability of material, availability of labour etc. that may be encountered incourse of execution of work
Before quoting rates tenderers are to read and understand all the clause/condition/free provisions incorporated in tender document and quote their rates accordingly
In case, the financial turnover of 2024-25 of the bidder has not been audited then certificate of C.A. is required that the balance sheet of financial year has not been audited. If the bidder have not submitted the certificate then the financial turnover of the 2024-25 will be taken as Nil and average of three financial year will be considered for conractual reciept 2022-23 & 2023-24 as per factual based on Audited balance Sheet and for 2024-25 as Nil.
The bid security submitted by tenderer in the form of Bank Guarantee shall be submitted as President of India, Acting through Dy.CE/GSU/GWL, North Central Railway and Beneficiary FA&CAO/C/ North Central Railway, Prayagraj
Please submit your bank details i.e.Name of the Bank along with Bank Branch Code, Account Number, IFSC Code, and PAN Number.
Please furnish list of plant and Machinery available on hand own and proposed to be inducted own and hired to be given separately for the subject work.
Please furnish list of Works on hand indicating Description of Work, Contract Value, Approximate value of balance work yet to be done and Date of award
Please furnish list of Works completed in last seven financial years giving Description of Work, Organization for whom executed, approximate value of contract at time of award, Date of award and Date of Completion. Date of actual Start, Actual Completion and Final value of Contract shall also be given.
Please furnish list of personal, organization available on hand and proposed to be engaged for the subject work.
An undertaking by all partners of the partnership firm that they are not blacklisted or debarred by Railways or any other Ministry / Department of the Govt. of India from participation in tenders / contracts as on the date of opening of bids, either in their individual capacity or in any firm in which they were / are partners. Concealment / wrong information in regard to above shall make the contract liable for determination under Clause 62 of the General Conditions of Contract.
The contractor shall have the option to take payment from Railway through a letter of credit(LC) arrangement. This option has to be exercised IREPS by the tenderer at the time of bidding itself and the tenderer shall affirm having read over and agreed to the terms and conditions of the LC option. In casetendereropts for payment through LC the procedure to deal release of payment through LC will be as per Railway Board's letter No. 2018/CE-I/CT/9 dated04.06.2018. The option so exercised , shall be an integral part of the bidder'soffer. Option of taking payment through LC arrangement, once exercised by the tenderer at the time of bidding, shall be final and no change shall be permitted, thereafter, during execution of contract.
As per Advanced Correction Slip no. 2 to IRGCC and up to date, April 2022, in case of other than Company/Proprietary firm, Annexur-V(A) shall also be submitted by each member of a Partnership Firm/ Joint Venture(JV)/ Hindu Undivided Family(HUF)/ Limited Liability Partnership(LLP) etc. as the case may be. Non submission of these Certificate(s) by the bidder shall result in summarily rejection of his/ their bid.
Is your firm is registered with MSME, Govt. of India for this category of work. If yes have you attached copy of relevant document?
Bid Security to be submitted in terms of para 5 of Tenders for works. If Bid security is not submitted and examption claimed than relevent doc. in support of examption should be submitted. The Bid shall be summarily rejected if it is not accompanied by the prescribed amount of Bid security
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
"Jhansi-Manikpur Section-Construction of ROB in lieu of Level Crossing No. 369 at KM 1131/1-2".
DYCEGSUGWL_1126~NCR
DYCEGSUGWL_1126
Open
Works - General
18 Months
Jhansi, Uttar Pradesh
₹0
₹2.0 Cr
17 Jun 2026
27 May 2026
3 Jun 2026
140 items across 3 schedules · ₹98,84,50,653.28 total
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| Earthwork in filling in embankment, guide bunds, around buried type abutments, bridge gaps, trolley refuges, platforms etc. with contractor's own earth conforming to Soil Quality Class SQ1/SQ2/SQ3, after preparation of foundations as applicable, benching in existing banks wherever required, spreading in layers with motor grader, bringing the moisture content to OMC, mechanical compaction to specified density and dressing of bank to final profile as per RDSO Specifications: RDSO/2020/GE: IRS-0004 with latest correction slips. Note: 1) Foundation preparation, Benching including additional earthwork on account of this, wherever required, shall be paid extra under relevant schedule item for benching. 2) Payment for Earthwork under this item shall be made based on the cross section measurements calculated (i) with original ground profile of existing bank based on initial ground levels before doing benching and (ii) final profile of the bank worked out with final levels as per prevailing guidelines. | — | — | — | — | |
| 1 | Using Soil Class SQ1 | cum 500.00 | — | 281.85 | 1,40,925 |
| Felling trees of girth (measured at a height of 1.0 m above ground level) including leading and stacking of material within 100m. Note : 1. When stumps are grubbed up in addition, the rates shall be doubled for trees cut and grubbed 2. Payment for grubbing shall only be made where specially ordered. 3. Grubbing shall be ordered only where it is essential to remove the stumps, including the roots, as per specification. 4. Grubbing shall include removal of roots of trees and saplings to a depth of 60cm below ground level or 30 cm below formation level or 15 cm below sub grade level, whichever is lower. | — | — | — | — | |
| 2 | Girth over 30 cm and up to 60 cm | Each 6.00 | — | 325.79 | 1,954.74 |
| 3 | Girth over 60 cm and up to 1.5m | Each 15.00 | — | 900.16 | 13,502.4 |
| 4 | Girth over 1.5m up to 3 m | Each 6.00 | — | 1,793.64 | 10,761.84 |
| Providing portable fencing along running track where work is to be done in close vicinity of track, maintaining during execution of work and removing after completion of the work as per direction of the Engineer. Fencing shall consist of self supporting steel angles of size 50mm x 50mm x 6mm, 1.5m long provided with hooks etc. and embedded in CC 1:2:4 block of size 0.23m x 0.23m x 0.23m placed at c/c distance of 2m along track. 12mm dia rods in three horizontal layers shall be tack welded with angle posts. Note : Released material will be property of the contractor after completion of work. Cost of cement required for CC blocks shall be paid separately. | — | — | — | — | |
| 5 | With provision of one 50mm wide retro-reflective tape in horizontal direction, duly secured/tight with vertical posts. | Metre 800.00 | — | 237.69 | 1,90,152 |
| Exploratory drilling of boreholes down to required depth, drilling of 150mm dia. boreholes in all type of soils except hard rock & large boulders (boulder core more than 30cm) including refilling, reinstating surface and disposing off surplus material including use of mechanical rigs with power operated winches as well as percussion/chiselling tool for advancing through occasional seams of hard strata to be employed, where necessary in Dry area. | — | — | — | — | |
| 6 | 0m to 10m | Metre 40.00 | — | 1,224.75 | 48,990 |
| 7 | 10m to 20m | Metre 40.00 | — | 1,286.29 | 51,451.6 |
| 8 | 20m to 30m | Metre 40.00 | — | 1,353.99 | 54,159.6 |
| 9 | Conducting chemical analysis of soil samples to determine aggressiveness in relation to attack on concrete / reinforcement including determination of pH value | Each 4.00 | — | 1,671.08 | 6,684.32 |
| Earthwork in excavation by mechanical means (Hydraulic Excavator)/Manual Means for foundations and floors of the bridges, retaining walls etc. including setting out, dressing of sides, ramming of bottom, getting out the excavated material, back filling in layers with approved material and consolidation of the layers by ramming and watering etc. including all lift, disposal of surplus soil up to a lead of 300m, all types of shoring and strutting with all labour and material complete as per drawing and technical specification as directed by Engineer in charge. Note: This item will be used for excavation work in connection with other miscellaneous works also like side drains, foundation for OHE masts and other miscellaneous structures in connection with Gauge Conversion, Doubling, New lines. | — | — | — | — | |
| 10 | All kinds of soils | cum 10000.00 | — | 196.66 | 19,66,600 |
| 11 | Soft rock (not requiring blasting) | cum 1000.00 | — | 405.35 | 4,05,350 |
| 12 | Hard rock (blasting prohibited ) | cum 500.00 | — | 1,114.41 | 5,57,205 |
| Providing and laying in position Plain cement concrete of specified Nominal Mix f o r miscellaneous works like side drains, foundation for OHE masts and other miscellaneous structures excluding the cost of Cement, centering and shuttering - All work up to plinth level : | — | — | — | — | |
| 13 | 1:1½:3 (1 Cement: 1½ coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size) | cum 1000.00 | — | 3,434.82 | 34,34,820 |
| 14 | 1:3:6 (1 Cement : 3 coarse sand (zone-III) : 6 graded stone aggregate 20 mm nominal size) | cum 100.00 | — | 3,667.29 | 3,66,729 |
| 15 | Providing and laying in position machine batched, machine mixed and machine vibrated Cement Concrete of specified grade as per approved Design Mix (mixed in Mobile Concrete Batching/Mixing Plant at site or RMC from approved p l a n t s ) using 20mm graded crushed stone aggregate and coarse sand of approved quality in RCC raft foundation & Pile cap including finishing, using Plasticiser in approved proportions (as per IS:9103), to modify workability without impairing strength and durability complete as per specifications and direction of the Engineer in charge. N o t e : 1. Payment for cement, reinforcement and shuttering shall be made extra under relevant item. 2. Plasticiser shall invariably be used in approved proportion to increase workability with minimum possible quantity of cement for all grade of Design Mix Concrete unless it is specifically approved citing reasons for not using plasticiser at the stage of Mix Design and in that case deduction shall be made as per relevant item. | cum 6500.00 | — | 3,645.58 | 2,36,96,270 |
| Providing and laying in position machine batched, machine mixed and machine vibrated Cement Concrete of specified grade as per approved Design Mix (mixed in Mobile Concrete Batching/Mixing Plant at site or RMC from approved plants) using 20mm graded crushed stone aggregate and coarse sand of approved quality for the following Reinforced cement concrete structural elements up to height of 9.0 m from foundation top level, including finishing, using Plasticiser in approved proportions (as per IS:9103), to modify workability without impairing strength and durability complete as per specifications and direction of the Engineer in charge. Note: 1. Payment for cement, reinforcement and shuttering shall be made extra under relevant item. 2. Plasticiser shall invariably be used in approved proportion to increase workability with minimum possible quantity of cement for all grade of Design Mix Concrete unless it is specifically approved citing reasons for not using plasticiser at the stage of Mix Design and in that case deduction shall be made as per relevant item. | — | — | — | — | |
| 16 | Abutment & Pier | cum 1600.00 | — | 3,725.25 | 59,60,400 |
| 17 | Wing wall and Return wall | cum 300.00 | — | 3,725.25 | 11,17,575 |
| 18 | Abutment cap, Pier Cap, Inspection Platform & Pedestal over Pier cap, Fender wall, Diaphragm wall etc. | cum 500.00 | — | 3,765.08 | 18,82,540 |
| 19 | Approach slab at formation level, Dirt wall/ ballast wall at formation level | cum 3100.00 | — | 3,685.41 | 1,14,24,771 |
| 20 | Providing and laying Plain Cement Concrete 1:3:6 with graded stone aggregate of 40mm nominal size, in foundation and floors, retaining walls of bridges including mechanical mixing, vibrating, pumping and bailing out water where ever required with all materials and labour complete but excluding the cost of cement and shuttering as per drawings and technical specifications as directed by Engineer. | cum 200.00 | — | 3,722.48 | 7,44,496 |
| 21 | Providing and fixing Weep Holes in Abutments, Wing walls and Return walls etc., of new bridges with 110mm dia UPVC pipe Type A ISI marked with all contractor's men, material, transportation, all taxes as per specifications and as directed by Engineer-in-Charge. | Metre 2250.00 | — | 246.87 | 5,55,457.5 |
| Boring, providing and installation of bored cast in-situ Reinforced Cement Concrete piles using Hydraulic piling Rig of specified diameter and length below pile cap of specified grade with Design Mix Cement Concrete, using 20mm graded crushed stone aggregate and coarse sand of approved quality, to carry a safe working load not less than specified, concreting by machine batching, machine mixing, scaffolding, using Admixture in approved proportion (as per IS:9103), placing with tremie pipe, chipping off of pile top to remove laitance concrete above cut off level etc., pumping and bailing out water complete in all respect as per approved drawing, specification and direction of the Engineer in charge. N o t e : 1. Payment for only cement, reinforcement shall be made extra. 2. Length of the pile for payment shall be measured up to the bottom of RCC pile Cap. 3. Plasticiser shall invariably be used in approved proportion to increase workability with minimum possible quantity of cement for all grade of Design Mix Concrete unless it is specifically approved citing reasons for not using plasticiser at the stage of Mix Design and in that case deduction shall be made as per relevant item. | — | — | — | — | |
| 22 | 1200mm diameter | Metre 9000.00 | — | 10,024.16 | 9,02,17,440 |
| Conducting load test of a single pile up to specified capacity in accordance with IS:2911 (Part-IV) including installation of loading platform and preparation of pile head or construction of test cap and dismantling of test cap after test etc. with all labour, material, tool & plants, equipment, machinery, etc. complete as per drawing and specification, as directed by the Engineer. | — | — | — | — | |
| 23 | Initial load test above 100 ton and up to 250 T capacity pile | Each 2.00 | — | 91,467.04 | 1,82,934.08 |
| 24 | Extra for every increase of 50 ton in pile capacity or part thereof over 250 ton | Each 8.00 | — | 4,899.71 | 39,197.68 |
| 25 | Routine Load Test above 100 ton capacity up to 250 ton capacity pile | Each 18.00 | — | 45,733.52 | 8,23,203.36 |
| Lateral load testing of single pile in accordance with "IS Code of practice IS:2911 (Part-IV) for determining safe allowable lateral load of pile" with all labour, material, tool & plants, equipment, machinery, etc complete as per drawing and specification as directed by the Engineer. | — | — | — | — | |
| 26 | Piles with lateral load capacity of above 50 ton and up to 100 ton | Each 2.00 | — | 31,809.47 | 63,618.94 |
| Centering and shuttering including strutting, propping etc. and removal of form for : | — | — | — | — | |
| 27 | All types of bridge sub-structures, e.g. pier, abutment, wing wall, retaining wall, RCC box type foundations, Abutment cap, Pier Cap, Inspection Platform & Pedestal over Pier cap, Fender wall, Diaphragm wall etc. up to 5m above ground level | Sqm 25100.00 | — | 661.48 | 1,66,03,148 |
| 28 | All types of bridge super- structures, e.g. slabs, I-girders, T- girders, Box girders etc. up to 5m above ground level. | Sqm 21100.00 | — | 860.71 | 1,81,60,981 |
| 29 | Extra for additional height over item no. 025031 & 025032 wherever required with adequate bracing, propping etc. over initial height of 5 metres for every additional height of 1 metre or part thereof. | Sqm 10000.00 | — | 106.15 | 10,61,500 |
| Supply and using Cement at Worksite | — | — | — | — | |
| 30 | Ordinary Portland Cement 43 grade approved brands/makes | MT 14000.00 | — | 8,153.06 | 11,41,42,840 |
| Supply of steel reinforcement of approved brands/makes for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete. | — | — | — | — | |
| 31 | Thermo-Mechanically Treated bars of grade Fe-500D or more of approved brands/makes. | Kg 4700000.00 | — | 80.14 | 37,66,58,000 |
| 32 | Providing and launching in position machine batched, machine mixed and machine vibrated Cement Concrete of specified grade as per approved Design Mix (mixed in Mobile Concrete Batching/Mixing Plant at site or RMC from approved plants) using 20mm graded crushed stone aggregate and coarse sand of approved quality for the Precast Prestressed (Post- tensioned) Concrete Girder/Box Girders/Slabs in contactor's casting yard in the vicinity of worksite, including finishing, using Plasticiser in approved proportions (as per IS:9103), to modify workability without impairing strength and durability, complete as per drawings, specifications and direction of the Engineer. Note: 1. Payment for Shuttering, Cement, Reinforcement, HTS cables, Sheathing, Anchorage Cones, stressing of cables, grouting of the ducts and launching of girder/slab in position shall be made extra under relevant items. However, deduction shall be made in case of slab as per relevant item. 2. For pre-cast item, loading in transport vehicle in casting yard is included and shall not be paid extra. 3. Plasticiser shall invariably be used in approved proportion to increase workability with minimum possible quantity of cement for all grade of Design Mix Concrete unless it is specifically approved citing reasons at the stage of Mix Design and in that case deduction shall be made as per relevant item. | cum 4000.00 | — | 3,645.58 | 1,45,82,320 |
| 33 | Providing, fabricating & fixing in position to exact design profiles, H.T.S. cables of all classification made from Low Relaxation strands conforming to IS:14268- latest version in Prestressed (Post- tensioned) Concrete girders/slabs etc. including supplying, cutting, making into cables with necessary spacers, colour coding, protecting with water soluble oil at all time, anchoring of cables, supplying and placing spiral corrugated type galvanized metal steel ducts sheathing made up of Cold Rolled Cold Annealed (CRCA) mild steel conforming to IS:513 of required diameter/ thickness, vent pipe, placing, bending, routing, fixing, stressing & grouting of cable ducts with cement grout, Anchorage sets in required number with provision for future prestressing if any including all lead and lift with contractor's own materials, labour, equipments etc. complete as per drawings & specifications. Rate also includes covering anchorage pads with epoxy mortar of approved quality to avoid corrosion. Cement for grouting to be paid separately. Payment shall be made in terms of weight of HTS cables as per drawing. | MT 105.00 | — | 1,90,323.94 | 1,99,84,013.7 |
| 34 | Design, manufacturing, supplying and fixing in position elastomeric b e a r i n g true to line and level conforming to IS:3400, IS:226, BS- 5400 under prestressed concrete girders/ Steel Girders, for Pre-cast as well as cast-in-situ girders as per approved drawing. The rate shall include cost of load test of one no. bearing from Railway approved firms and all fixing materials, equipments, machineries, labour, taxes, loading, unloading, leading, lifting etc. complete. Rates include getting the drawing approved from Railway and cost of inspection during manufacturing from railway approved organization.Note : 1. The rate is for finished item complete and paid only after fixing in position below the girder. 2. The volume shall be as given in the drawing and no deduction shall be made for inserted steel plates etc. | Cubic 18000000.00 Centimetre | — | 1.47 | 2,64,60,000 |
| Providing and fixing in position of standard preformed sealed and slab type or strip seal elastomeric type expansion joints for Railway bridge or Road Over Bridges as per approved drawings and latest MORTH/IRC specifications complete in all respect as directed by Engineer in-charge. | — | — | — | — | |
| 35 | For 80mm expansion | Metre 650.00 | — | 9,614.54 | 62,49,451 |
| Providing and fixing in position GI Drainage Spouts of required length with Grating in RCC slab and filling bitumen along kerb as shown in drawing with contractor's pipes, bitumen, tools, equipment, lead, lifts etc. complete as per specifications and as directed by Engineer in-charge. | — | — | — | — | |
| 36 | 100mm dia. Drainage Spouts | Metre 400.00 | — | 1,261.63 | 5,04,652 |
| 37 | Supplying and laying 160mm dia. PVC Pipes Class-I, capable for a pressure of 2.5 kg/sqm in footpath of ROB for laying cable with all contractor's materials labour, tools, plant, machinery, vehicles, consumables, lead, lift etc. complete as per specifications and as directed by Engineer in-charge. | Metre 2500.00 | — | 584.15 | 14,60,375 |
| Supplying, fabrication, assembling of all types of steel girders of specified spans with structural steel conforming to Quality "B0" Grade Designation E250 conforming to IS:2062, erection / slewing / end launching of steel girders with cranes or any other approved launching methods as per site conditions (not requiring traffic block) on sub-structure including provision of trolley r e f u g e s etc., complete as per a p p r o v e d Q A P and drawings conforming to IRS-B1-2001 and other relevant codes and specifications. Note: 1. Detailed fabrication and erection drawings & launching methodology will be prepared by the contractor and got approved from Railway. 2. The rate is all inclusive including launching in position, complete in all respect except cost of (i) Painting / Metalising; (ii) Bearings & (iii) HSFG bolts which shall be paid extra under relevant item. 3. The payment shall be made on the theoretical weight of main components and gusset plates o n l y. 4. Payment Schedule: (i) Receipt of material at site: 40% (ii) Fabrication of girders: 20% (iii) Erection/Launching: 20% (iv) Completion in all respects: 20% | — | — | — | — | |
| 38 | Plate Girder/Semi Through Girder/Composite Girder (Steel Work) | MT 1400.00 | — | 1,00,144.26 | 14,02,01,964 |
| 39 | Extra for using steel conforming to Grade Designation E350 instead of Grade Designation E250 of Quality "B0" as per IS: 2062 | MT 1400.00 | — | 3,077.26 | 43,08,164 |
| 40 | Supplying and fixing HSFG bolts of any dia and any length with suitable nuts including DTI washers conforming to IRS-B1-2001 for bridges and steel structures with contractors labour, tools and plants and lead and lift etc., complete. | Kg 10000.00 | — | 169.56 | 16,95,600 |
| Metallizing of steel work of girders with sprayed aluminium after surface preparation by Sand/grit blasting, followed by one coat of etch primer (IS:5666) & one coat of Zinc Chrome primer (IS:104) and two coats of aluminium paint (IS:2339) with all labour, T&P and material as a complete job duly conforming to all relevant specifications and process given under Clause 39 of IRS-B1-2001. Note: Nominal Thickness of sprayed Aluminium coating shall be 150 microns. DFT of Zinc chrome primer shall be 25-30 microns and DFT of each coat of Aluminium paint shall be 12-14 microns. | — | — | — | — | |
| 41 | On new girder during fabrication | Sqm 8000.00 | — | 665.66 | 53,25,280 |
| 42 | Providing and fixing railing used in rows for footpath or anti-crash barrier railing with B class G.I. pipe 65/50 mm nominal dia including cost of M.S. angle and channels in vertical posts, welding / bolting, priming painting with one coat ready mix Zinc Chromate conforming to IS:104 with DFT of 25-30Microns, followed by one coat of Zinc Chrome red oxide conforming to IS:2074 with DFT of 25 Microns with all material, labour, T&P as a complete job. Note: Cost of painting shall be paid extra under relevant item. | Kg 5000.00 | — | 90.12 | 4,50,600 |
| Design, supply, fitting and fixing in position true to line and level POT- PTFE bearing of 250 MT Capacity, consisting of a metal piston supported by a disc or un reinforced elastomer confined within a metal cylinder, sealing rings, dust seals, PTFE surface sliding against stainless steel mating surface, complete assembly to be of cast steel / fabricated structural steel, metal and elastomer elements complete as per IS:2062, IS:1030, AISI:304, AISI:316, IS:6911, BS:3784, IS:3400, IS:226, BS-5400, Bridge Code and as per approved drawing a n d Technical Specifications. The design of the bearings shall be submitted by the manufacturers / contractor and got approved from Railway before fixing. Test report after inspection of the bearings shall be submitted and got approved before the materials are lifted from the manufacturer premises. | — | — | — | — | |
| 43 | POT-cum -PTFE Bearing (Free end) | Each 24.00 | — | 79,121.36 | 18,98,912.64 |
| 44 | POT Bearing-Fixed Type | Each 12.00 | — | 1,01,205.39 | 12,14,464.68 |
| 45 | POT-cum -PTFE Guided (L)Bearing | Each 12.00 | — | 1,24,368.89 | 14,92,426.68 |
| 46 | POT-cum -PTFE Guided (T)Bearing | Each 24.00 | — | 1,17,682.4 | 28,24,377.6 |
| 47 | Supplying fabricating and erecting welded and/or bolted and/or riveted steel work in built up sections, trusses and framed work, staging, racks, Height Gauge etc. for Steel Structures other than bridge girders, using RSJ, tees, angles and channels/flats, plates, gussets, round or square bars, cleats, bolts etc., with contractors own steel including cutting, bending, straightening, drilling, riveting, hoisting, fixing, erecting, welding, bolting etc., with Providing stiffeners wherever required as per approved drawing including applying a priming coat of a approved steel primer with all contractor's materials, labour, tools & plants, lead & lift including crossing of tracks if required etc., complete as per specification and as directed by Engineer-in-charge. Note: The payment shall be made on the theoretical weight of main components and gusset plates only. | MT 110.00 | — | 87,491.62 | 96,24,078.2 |
| 48 | Supply and laying of quarry dust including consolidation, supply of all materials, labour, lead, lift, tools, plants, crossing of tracks as per drawing and technical specification as directed by the Engineer in charge in case loose slush is encountered at site of foundation before casting the foundation or laying the filtering media. | cum 50.00 | — | 1,274 | 63,700 |
| 49 | Dewatering of natural or accumulated water from any location. Payment to be done for Horse power of pump multiplied by pumping hours. | HP Hour 400.00 | — | 45.37 | 18,148 |
| Designing and developing Detailed structural and working Drawings for following items for ROB/RUB/Bridge based on Railway's approved GADs, duly collecting necessary data from Railways and R&B authorities, duly designing members and submission of check plot duly getting proof-checked by Railway approved institutes, submitting for Railway's verification and approval, making corrections duly incorporating suggestions in drawings/designs, further submission of original in transparent film paper and soft copy (CD) for Railways approval etc. with contractor's technical expertise and instruments, labour, consumables, repeatedly attending till final approval etc., complete as directed by Engineer in-charge. | — | — | — | — | |
| 50 | Open / Pile / Well Foundation for piers/abutments | Set 14.00 | — | 27,879.28 | 3,90,309.92 |
| 51 | RCC Bed Block | Set 6.00 | — | 8,631.37 | 51,788.22 |
| 52 | Foundation and sub-structure for RCC retaining wall, abutment and approach slab | Set 6.00 | — | 27,210.31 | 1,63,261.86 |
| Drilling of hole of different diameter and chamfering, in rail of any section and any UTS manually only in emergencies with contractor's labours, tools & plants, consumables etc. | — | — | — | — | |
| 53 | Hole of dia. 26.5mm and above | Each 40.00 | — | 248.1 | 9,924 |
| 54 | Hole of dia. below 26.5mm | Each 40.00 | — | 151.52 | 6,060.8 |
| 55 | Trimming of tree branches coming within 6m of centre line of track & those obstructing views of Curves/LCs / Signal / Indicator at locations in section & station yard, as specified by Engineer in-charge including disposal of branches, bushes outside cess/yard. Note: Girth of more than 20 cm will only be considered as tree branch. | Each 10.00 | — | 158.89 | 1,588.9 |
| Manufacturing, fabricating and supplying retro-reflective Engineering Indicator boards, made of 2mm thick aluminium sheet or 3mm thick aluminium composite sheet, face to be fully covered with high intensity encapsulated type heat activated retro-reflective sheeting conforming to type-IV of ASTM- D4956-01 in yellow & black or other colour combination including subject matter, message, symbols, borders etc. as approved by Engineer In-charge or as per IRPWM guidelines, pasted on substrate by an adhesive backing which shall be activated by applying heat and pressure conforming to class-2 of ASTM-D- 4956-01 and fixing the same with suitable sized aluminium alloy rivets @ 20 cm c/c to back-support frame of M.S. angle iron of size 25mm x25mm x 3mmprovided all along the edges of board with theft resistant measures back side of board shall be with non-peelable weatherproof paint, consisting of one coat of zinc chromate primer and two coats of epoxy paint. Vertical post shall have black & white anti-corrosive paint or powder coating complete, as directed. | — | — | — | — | |
| 56 | Caution Indicator Board of size 1400mmx400mm with back support frame fixed to vertical post of MS angle of size 50mmx50mmx6mm of 3650 mm long | Each 4.00 | — | 6,066.05 | 24,264.2 |
| 57 | Speed Indicator Board of equilateral triangular shape having each side of 1000mm with back support frame fixed to vertical post of MS angle of size 50mmx50mmx6mm of 3650 mm long | Each 8.00 | — | 5,128.99 | 41,031.92 |
| 58 | Stop Indicator Board of size 1400mmx400mm with back support frame fixed to vertical post of MS angle of size 50mmx50mmx6mm of 3650 mm long | Each 4.00 | — | 6,066.05 | 24,264.2 |
| Hiring of machinery for minor miscellaneous works for short duration including operator/driver, fuel, lubricants and consumable. The contractor shall arrange all statutory permits as required by rules and regulations prevailing in the area of work. Payment shall be made for actual working hours at site. | — | — | — | — | |
| 59 | JCB Backhoe Loaders 3DX Plus or similar with minimum 1.10 cum bucket capacity | Hour 100.00 | — | 794.59 | 79,459 |
| 60 | Hydra or similar tyre mounted Pick- n-Carry crane of 12T capacity for misc. works of handling of material | Hour 20.00 | — | 942.83 | 18,856.6 |
| 61 | Arranging labour as and when required by the Engineer in charge, for various works under SSE/P.Way, with contractor's T&P, equipments, hand signal flags, etc. as per specifications, special conditions and detailed scope of work as furnished in the tender and as directed by the Engineer in charge. Note: Item shall be operated with prior approval of concerned Sr. DEN / DEN in charge. | Day 100.00 | — | 651.58 | 65,158 |
| Schedule total | ₹90,98,18,153.18 | ||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
AnnexureVA.pdf
ATTACHMENT
MaterialSpecification..pdf
ATTACHMENT
PCEcircular.pdf
ATTACHMENT
GCC2022ACS10.pdf
ATTACHMENT
GGC2022correctionslip11.pdf
ATTACHMENT
LC-369APPROVEDGAD.pdf
ATTACHMENT
TD1126.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .