| # | Company | Amount | Status |
|---|---|---|---|
| 1 | ₹45.9 Laccepted-finance | accepted-finance |
Tender Value
₹51.0 L
EMD Value
₹1.0 L
Closing Date
9 Feb 2026, 9:30 pmClosed
Bengaluru Water Supply And Sewerage Board
lokesh J
Tender for the work of providing and laying 300mm dia RCC Np3 Class Sewer Pipeline in KSFC layout and Surrounding Areas in Lingarajapuram coming under Lingarajapuram Service station of AEE-e-2-2 Subdivision-Part-B General category
BWSSB/2025-26/WS/WORK_INDENT3247
BWSSB/2025-26/WS/WORK_INDENT3247
Open
Water supply/sewage lines
Two Tender Document System(Two Cover)
BWSSB Executive Engineer East Two
₹1,280
₹1.0 L
9 Feb 2026
2 Feb 2026
10 Feb 2026
4 Feb 2026
Dismantling of Flexible pavements and disposal of dismantled materials and stacking serviceable and unserviceable materials separately.By Mechanical means
Dismantling of cement concrete pavement by mechanical means using pneumatic tools, breaking to pieces not exceeding 0.02 m3 in volume and stock piling at designated locations and disposal of dismantled materials and stacking serviceable and unserviceable materials separately(Vol-3,CSR 2023-24,Sl.No:2.19,pg no:12
Earth work excavation for pipeline trenches in all kinds of soils by mechanical means above 600 mm trench width as per drawing and technical specifications, including setting out, construction of shoring,strutting, barricading, caution lights, bracing, using sight rails & boning rods at every 100 mm whevere necessary as directed, removal of stumps and other deleterious matter, dressing of sides and levelling the bottom of trench to the extent required , utilising the available excavated earth locally for the work etc., and all other appurtenances complete in the following strata.All kinds of soils,Depth upto 1.50m,
Depth exceeding 1.5 m, but not exceeding 3 m
Earth work excavation for pipeline trenchesby mechanical means above 600 mm trench width as per drawing and technical specification,including setting out, construction of shoring, strutting, cost of blasting materials, barricading,caution lights, bracing, using sight rails & boning rods at every 100 mm whevere necessary as directed, removal of slumps and other deleterious matter, dressing of sides and levelling the bottom of trench to the extent required , utilising the available excavated earth locally for the work and all other appurtenances to complete in the following strata.(Volume-1,Common S.R 2023-24,part-2,Chapter-1,Pg.No:10,Sl.No:1.19)
Ordinary/soft rock (without requiring blasting) Depth upto 1.50 m
Depth exceeding 1.5 m, but not exceeding 3 m
Supplying S&S RCC SPUN / VIBRATED CAST PIPES (REINFORCED) pipes NP-3 Class conforming to IS:458-1988 with latest amentments using ordinary portland cement, for sanitary works and conveying to work site, rolling and lowering into trenches, laying true to line and level including loading and unloading at both destinations and jointing of pipes and specials, perfect linking of joints with jack to correct position including cost of jointing materials, i.e, rubber rings conforming to IS: 5382 for S&S RCC pipes, with all leads and lifts as directed and giving necessary hydraulic test as per ISS to the required pressure and commissioning etc. complete. (Contractor will make his own arrangements for procuring water for testing). Before the execution of the work, the contractor shall carry out the survey.
Providing and laying Ductile Iron pipes of class conforming to IS 8329:2000 with latest amendments, conveying to work site, rolling and lowering into trenches, laying true to line, level and perfect linking at joints, testing and commissioning, including loading and unloading at both destinations, cutting of pipes wherever necessary, jointing with DI specials (excluding cost of specials) and rubber gaskets, cleaning the socket and spigot end with soap solution, applying soft soap to the socket and spigot ends before insertion of rubber gaskets, jacking and fixing in perfect conditions etc. The cost to include soap solution, soft soap, waste etc. and giving necessary hydraulic test to the required pressure as per ISS with all lead and lifts and cost of all jointing materials. (The contractor will make his own arrangements for water for testing. Earth work excavation in trenches to be measured and paid for seperately) Note: In sewerage projects for internal cement mortal lining ( CML ) of DI pipes, if High Alumina Cement ( HAC ) as recommended in Annexure B clause 16.3 of IS8329:2000 is considered in place of Slag or Sulphate Resistance Cement ( SRC ), the cost of pipes may be increased by 5-6% from the prices listed. For DI K9 pipes:300mm dia pipe
Providing and constructing “WIRE CUT BRICK MACHINEHOLE CHAMBERS” using Portland/Pozzolana cement, conical in shape at top, with CC 1:3:6 foundation using 40mm and down size graded metal of approved quality and with an offset of 0.15M alround the chamber. Construct Brick masonry in CM 1:4, 340 mm thick, with wirecut bricks of approved quality, plaster inside and out side with CM 1:3, 12mm thick, except for the conical surface outside where the plaster thickness shall be 20mm. Slope inside to be 1:6 in the concrete towards central drain and finished smooth. Fixing of pipes in CC 1:2:4 with graded metal of 20mm and down size. Supplying and fixing SFRC Machinehole frame and cover (Heavy Duty) conforming to IS:12592 with latest amendment, in CC 1:2:4. Supplying and fixing footsteps made of 12mm dia. steel bars (Fe-500) with 3mm thick plastic encapsulation (IS-10910). The footsteps shall be fixed 30cms apart and on CC block embeded to masonry wall. The whole works include watering, curing, barricading, danger lighting, pouring tar over MH frame and cover, cost of tar, shoring, strutting, dewatering, engraving Machinehole number with flow direction on the inner conical surface etc. as per the drawing etc. as per technical specifications and for the following diameters and depth etc. for 1.2m diaCirc. B M.H
1.0 m to 2.0 depth
1.0 m depth
Supply and delivery at site special moulded variety PVC bend as per IS 7834/ 1987 and fabricated as per IG124/ 1984 with ISI mark with its latest amendments
Supply and delivery at site special moulded variety PVC reducer as per IS 7834/ 1987 and fabricated as per IG124/ 1984 with ISI mark with its latest amendments
Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver/grader in sub-base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.
Providing and applying primer coat with SS1 grade Bitumen Emulsion on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.90 kg per m2 using mechanical means.Prime Coat over WMM/WBM
Bituminous Macadam Grading - I for traffic <20 MSA,Providing and laying Bituminous Macadam with 120 tph capacity hot mix plant batch type using crushed aggregates of specified grading premixed with bituminous binder VG-30 @ 3.3% by weight of mix, transported to site, laid over a previously prepared surface with mechanical paver finisher to the required grade, level and alignment and rolled as per clauses 501.6 and 501.7 to achieve the desired compaction (Volume-3,Common S.R 2023-24,Pg.No:31,Sl.No:5.6,Ref.to MoRT&H Spec.504(i)A
Tack coat on Bituminous surface,Providing and applying tack coat with RS1 Bituminous Emulsion using emulsion pressure distributor at the rate of 0.20 kg/m2 on the prepared bituminous surface cleaned with mechanical broom
Bituminous Concrete Grading I for traffic<20 MAS,Providing and laying Bituminous Concrete with 120 TPH capacity hot mix plant batch type using crushed aggregates of specified grading, premixed with bituminous binder VG-30 @ 5.2 per cent of mix and filler, transporting the hot mix to work site, laying with mechanical paver finisher to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects
Construction of M30 Grade un-reinforced, dowel jointed, plain cement concrete pavement over a prepared sub base with OPC @ 270 kg/m3 and GGBS@ 90 kg/m3 , coarse and fine aggregate conforming to IS 383:2016, maximum size of coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design transported to site, laid with a paver finisher, spread, compacted and finished in a continuous operation including provision of contraction, expansion,construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures, curing compound, steel channels,finishing to lines and grades as per drawing
Removal of Unserviceable Soil with Disposal upto a suitable distance as directed by the Engineer incharge of work
Refilling available earth around trenches/pipelines, cables in layers not exceeding 20 cms in depth, compacting each deposited layer by ramming after watering with a lead upto 50 m , and lift upto 1.5 m. Including cost of all labour complete as per specifications
Dewatering the sewage / storm water by using reqired HP submersible pump for the diversion of storm / sewage during the execution of work. Considering for one Pump,5HP Pump
Conducting Topographical GIS survey for the proposed Water Supply/ UGD scheme to the city / town with latest total station survey equipments. The work shall include collection of field data from local body, conducting detailed survey showing the all important land marks,existing water supply lines, sewer lines, all roads, levels, nature of roads,L-section survey for transmission main/ feeders/sub-feeder/ rising main from Jack well to WTP and WTP to OHT's and distribution network inlcuding clearing the obstructions, with all survey staff required covering all the developed & newly developed layouts or L-section survey for Sub-Main/Mains/Trunk Sewer/Rising main from wetwell to STP inlcuding clearing the obstructions, with all survey staff required covering all the developed & newly developed layouts with submission of Soft copy of drawings along with source file and hard copy in 3 sets for the following:water supply/sewer work main pipes
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
3247drawing.pdf
Others - drawing • 0.97 MB
Spot Report_3247.docx
Others - spot report • 0.02 MB
3247_dtp_KSFC_PARTB_genral_kw3 Final.docx
Tender Document • 0.34 MB
scheB_3247.xlsx
Others - boq • 0.02 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .