Loading…
India Infra Updates on WhatsApp
Join the Tenderkart WhatsApp channel for India Tender Updates
Loading…
Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.0 LAccepted-Finance | L1 | Accepted-Finance accepted | |
| 2 | L2₹2.0 L+₹1,964 (0.99%)Accepted-Finance | L2 | Accepted-Finance accepted | |
| 3 | L3₹2.3 L+₹33,464 (16.9%)Accepted-Finance | L3 | Accepted-Finance accepted | |
| 4 | L4₹2.5 L+₹51,204 (25.9%)Accepted-Finance 01 KATYANI CONSTRUCTION COMPANY H NO 1 SHOP NO 1 RATAN LAL NAGAR KANPUR NAGAR UTTAR PRADESH 208022 | KANPUR NAGAR | UTTAR PRADESH | 208022 | L4 | Accepted-Finance accepted | |
| 5 | L5₹2.5 L+₹51,464 (26.0%)Accepted-Finance 145 1 0 NEAR OLD LIC SHIV NAGAR VILLAGE TOWN MODIPURAM CITY MEERUT MEERUT UTTAR PRADESH 250110 INDIA | MEERUT | UTTAR PRADESH | 250110 | L5 | Accepted-Finance accepted |
Tender Value
₹3.2 L
EMD Value
₹3,500
Closing Date
6 Apr 2023, 11:00 amClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
SE ETC-I, Kanpur
SE ETC-I, Kanpur
WORK
2023_UPTCL_774873_2
ET-78/ETC-I(K)/2022-23
Open Tender
Electrical Works
Fixed-rate
120 days
Kanpur
Please refer Tender documents.
3 documents required · 3 mandatory
₹590
.PNB Account No 0727002100004177
₹3,500
19 Apr 2023
28 Mar 2023
6 Apr 2023
28 Mar 2023
6 Apr 2023
28 Mar 2023
Amount
Shifting of main tank of 63MVA T/F from unloading point to T/F plinth (upto 70mtr).
Additional Shifting of 5 meter or part thereof (63 MVA Transformer Main Tank).
Complete Erection of 63 MVA T/F by erection of radiators, conservator tank, HV/LV/N bushing and its turrets, connecting all pipe lines erection of fans, control cables, motor drive mechanism of RTCC panel, cooling fans etc. and all other associated work for satisfactorily completion of work
Filing of Transformer oil from Oil drums to main tank of 63 MVA T/F.
Centrifuging of complete Transformer oil in main tank of the Transformer taking the IR/BDV value of Transformer oil at an interval of 4 Hrs. as per norms till the desired value of BDV/PPM are obtained (Centrifuging machine along with operator shall be arranged by the contractor at his own cost).
Erection of RTCC panel of 63 MVA T/F in control room. The job includes its fitting, cutting of pocket etc.
Termination of cable connections in cooling fans/RTCC/Marshalling box including re-dressing/ferruling etc as per drawing.
Earthing of 63 MVA, 132/33 KV Transformer body, MB, OLTC/RTCC with MS flat to be provided by the deptt. and connecting the same with main earth mat at 2 places as required.
Making delta earthing with 03mtr. long electrodes which is to be provided be deptt. and connecting with neutral of 63 MVA T/F and green bus painting of MS Flat size 75mmX10mm(each for HV & LV Neutral).
SHILPA ENTERPRISES
M/S DHIRENDRA SINGH
Katyani Construction Co.
Hi-tech power transmission
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .