| 1 | ₹59.5 LAWARDED | AWARDED |
Tender Value
₹63.4 L
EMD Value
₹1.5 L
Closing Date
6 Aug 2025, 11:00 pmClosed
Directorate of Municipal Administration
Construction of compound and development work for old solid waste dumping yard site behind Brahmin Samaj on Huliyar Road, Arsikere CMC limit
DMA/2025-26/OW/WORK_INDENT45869
DMA/2025-26/OW/WORK_INDENT45869
Open
Other Works
Two Tender Document System(Two Cover)
DMA City Municipal Council Arasikere
₹1,590
₹1.5 L
22 Jul 2025
22 Jul 2025
8 Aug 2025
5 Aug 2025
Construction of compound and development work for old solid waste dumping yard site behind Brahmin Samaj on Huliyar Road, Arsikere CMC limit
Earth work excavation by manual means for drains, canals, waste weir, draft, approach channels, key trenches, foundation of Buildings & bridges and such simillar works in all kinds of soils, as per dr...
Providing Coursed rubble masonry (first sort) with hard stone in foundation and plinth with Cement mortar 1:6 (1 cement : 6 coarse sand
Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes...
Providing Size Stone masonry with hard stone in foundation & plinth with Cement mortar 1:6 (1 cement : 6 coarse sand)
Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/tra...
As per recommendations of Technical working group, rates for formwork shall be added on percentage basis to the finished concrete item rate. For drain form works consider 20%
Providing and constructing load bearing wall with Solid Concrete blocks of size 400x150x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2...
Providing Flush / Ruled/ Struck or weathered pointing Pointing on brickwork or brick flooring with cement mortar 1:3 (1 cement : 3 fine sand)after raking joints to depth nicely lining, including cost ...
Steel Fabrication Supplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/we...
Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint ...
Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable ...
Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment,scarified to a depth of 150 mm, mixed with water at OMC and then compacted...
Construction of Embankment by excavating the available approved Gravel/Murrum deposited at a place or borrow pits during or prior excavation with all lifts and lead, transportation to site, spreading,...
Wet Mix Macadam (Plant Mix Method) Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical ...
Providing and constructing un-reinforced plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M20 (Grade), c...
uction of Subgrade and Earthen Shoulders Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads,transporting to site, spreading, gradin...
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .