| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹8.0 LAccepted-AOC | L1 | Accepted-AOC Financial bid accepted at the rate | |
| 2 | L2₹8.0 L+₹4,584.62 (0.57%)Rejected-Finance | L2 | Rejected-Finance Rejected being higher rate |
Tender Value
₹8.0 L
EMD Value
₹15,980
Closing Date
25 Mar 2021, 5:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
EE BCD-2, Orai
EE BCD-2, Orai
Reconstruction of V.R.B. at Km. 8.148 of Samthar Dy
2021_UPIDC_557775_220
N-5/BCD-II/189/dt- 12.02.2021
Open Tender
Civil Works
Item Rate
90 days
Reconstruction of V.R.B. at Km. 8.148 of Samthar D
Please refer Tender documents.
2 documents required · 2 mandatory
₹600
₹15,980
Yes
9 Jun 2021
20 Mar 2021
26 Mar 2021
20 Mar 2021
25 Mar 2021
20 Mar 2021
90 days
Amount
Earth work of foundation in Mar Ranker and kanker mixed soil including lift upto 1.5 M. lead upto 30.0 M. i/c filling watering ramming of exvacated soil of the foundation trench and removal and disposal of surplus earth as directed by Engineer in Charge
Providing and Laying C.C. 1 : 3 : 6 with coarse sand F.M. not less than 2.2 ,stone Grit (20-40 mm) size in Foundation i/c all cost of labour and T&P etc.
Brick work with 1st class brick and coarse sand F.M. not less than 2.2 in 1 : 3 CM per M³ i/c all cost of labour and T&P etc.
Providing and Laying C.C. 1 : 1.5 : 3 with Stone Grit (10-20 mm) size i/c all cost of labour and T&P etc.
Centering & shuttering for R.C.C. work including all cost of material, labour and T&P etc.
Steel Reinforcement for R.C.C. work with cutting bending and binding and palcingin position with i/c all cost of labour materials and T.&P.
R.C.C. 1 : 1.5 : 3 with Stone Grit (10-20 mm) size i/c all cost of labour and T&P etc.
Struck pointing 1:2 Cement, Mortar including all cost of material, labour and T&P etc.
U/S D/S apron with boulder not less than 40 kg in size i/c all cost of labour and T&P etc.
Supply and Laying one layer of Tarfelt below bearing slab i/c all cost of labour Materials and T&P etc.
Providing and fixing joint filler board 20 mm thick at end of slab i/c all cost of labour and T&P etc.
Providing and Laying graded filter in perssure relief pipe, abutment and wing wall with aggregates 20-40 mm i/c all cost of materials labour and T&P etc.
Providing and Laying graded filter in perssure relief pipe, abutment and wing wall with aggregates 10-20 mm i/c all cost of materials labour and T&P etc.
Providing and Laying graded filter in perssure relief pipe, abutment and wing wall with coarse sand i/c all cost of materials labour and T&P etc.
Providing and Fixing 100 mm dia pvc pipe for weep holes at spacing 1.0 m c/c in abutment and wingwall i/c all cost of labour and T&P etc.
Providing and fixing wheel guard in size of 0.50 m x0.50 mx 0.750 m with reinforcement and M25 grade cement concrete i/c all cost of materials, labour and T&P etc
Providing and Fixing sign board with fabrication and painting 1.0 mm gauge sheets and ISA 40x40x5 size angle i/c all cost of labour and T&P etc.
Earth work in Mar Ranker and kanker soil including 30.0 mtr lead & 1.50 mtr lift with dressing and manual compaction etc.
ARYAN TRADERS
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .