| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.8 LAdmitted-Finance | ₹1.8 L | L1 | Admitted-Finance |
| 2 | L2₹1.9 LAdmitted-Finance | ₹1.9 L | L2 | Admitted-Finance |
| Sl No | Description | Qty | Unit | GEC ELECTRICALS L2 | m/s paul engineering constructions L1 |
|---|---|---|---|---|---|
| 1.01 | Supply installation testing and commissioning of 50 mm2 ACSR Conductor | 0.02 | Km | 1,400 ₹1,400 | 1,200 ₹1,200 |
| 1.02 | Supply installation testing and commissioning of 11 KV pin insulators with pins | 3 | No | 600 ₹600 | 600 ₹600 |
| 1.03 | Supply installation testing and commissioning of 11kV G.O. AB Switch 3-Phase, 3-Pole 200A Vertical Type. | 1 | Set | 10,000 ₹10,000 | 15,000 ₹15,000 |
| 1.04 | Painting with Al Paint | 1 | Ltr | 500 ₹500 | 450 ₹450 |
| 1.05 | Painting withRed Oxide Primer | 1 | Ltr | 300 ₹300 | 600 ₹600 |
| 1.06 | Earthing of Substation --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239.GI Strip for neutral earthing of size 25 mm x 3 mm for connection of transformer body,G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber made of brick masonary with RCC slab cover. | 3 | No | 24,000 ₹24,000 | 24,000 ₹24,000 |
| 1.07 | Providing and fixing of Al Thimbles of Sizes | 24 | No | 2,400 ₹2,400 | 1,680 ₹1,680 |
| 1.08 | Dismantling and re-installation of 400mm² 3½ Core Cable,1.1kV Grade, Armoured, XLPE Insulated Stranded Conductor FRLS | 40 | Mtr | 4,000 ₹4,000 | 2,800 ₹2,800 |
| 1.09 | Providing and fixing of G.I. Channel iron (75x40x40)mm 6ft long 2No's | 26 | Kg | 5,200 ₹5,200 | 5,720 ₹5,720 |
| 1.10 | Providing and fixing Pole collar | 6 | No | 1,200 ₹1,200 | 1,320 ₹1,320 |
Updated dates
Tender Value
₹1.9 L
EMD Value
₹3,800
Closing Date
15 Dec 2025, 11:30 amClosed
Executive Engineer EDI
Office of Executive Engineer EDI Basantbagh Srinagar
Shifting of 315KVA Distribution Transformer from control room to RCC Platform at Doordarshan Kendra Srinagar at Nawa I Subh
2025_PDD_295796_1
E-NIT No 049/EDI
Open Tender
Electrical Works
10 days
Office of Executive Engineer EDI
Please refer Tender documents.
5 documents required · 5 mandatory
₹200
Yes
Executive Engineer EDI
₹3,800
Yes
19 Dec 2025
20 Nov 2025
15 Dec 2025
20 Nov 2025
15 Dec 2025
20 Nov 2025
20 Nov 2025 - 22 Nov 2025
Supply installation testing and commissioning of 50 mm2 ACSR Conductor
Supply installation testing and commissioning of 11 KV pin insulators with pins
Supply installation testing and commissioning of 11kV G.O. AB Switch 3-Phase, 3-Pole 200A Vertical Type.
Painting with Al Paint
Painting withRed Oxide Primer
Earthing of Substation --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239.GI Strip for neutral earthing of size 25 mm x 3 mm for connection of transformer body,G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber made of brick masonary with RCC slab cover.
Providing and fixing of Al Thimbles of Sizes
Dismantling and re-installation of 400mm² 3½ Core Cable,1.1kV Grade, Armoured, XLPE Insulated Stranded Conductor FRLS
Providing and fixing of G.I. Channel iron (75x40x40)mm 6ft long 2No's
Providing and fixing Pole collar
Providing and fixing V shape cross Arm Comp with F-top
Providing and fixing Galvanized Nuts & Bolts of sizes
Supply installation testing and commissioning of MCCB 400 A complete with enclosure with stand
Supply installation testing and commissioning of 50 mm² AB (HT) Cable (3x50 + 1x70 insulated )mm² XLPE (11 kV, 3C + Earth)
Supply installation testing and commissioning of 3Ph3 Wire HT CT/PT operated Fully static Smart Tri-Vector Energymeters DLMS Compliant Category 'C' with RS 232 port for modem compatibility. 11kV/110V, Ph-Ph (3P,3W) meters for measurement of different electrical parameters including Active Energy (kWh/ MWh), Reactive Energy (kVArh/MVArh), Apparent Energy (kVAh/ MVAh) etc.
Dismantling/ re-installation of 315 KVA distribution transformer from old structure to new RCC Platform
Shifting of HT meter including box and cable with earthing
Supply installation testing and commissioning of end kit heat shrinkable for 11 KV
GEC ELECTRICALS (BID ID -2663526)
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.14 MB
BOQ_957717.xls
BOQ • 0.27 MB
SBD049.pdf
Other Document • 0.73 MB
TECH049.pdf
Other Document • 18.11 MB
Download all tender documents and submit your bid