| # | Company | Status |
|---|---|---|
| 1 | Admitted-Finance | Admitted-Finance |
| 2 | Admitted-Finance 44 NEW AMARANJIPURAM TONDIARPET CHENNAI 81 | CHENNAI | CHENNAI | TAMIL NADU | 600081 | Admitted-Finance |
Tender Value
Refer Docs
EMD Value
₹23,400
Closing Date
15 Aug 2023, 2:00 pmClosed
SE/ Operation
SE/ Operation, North Chennai Thermal Power Station -I, Chennai- 600 120.
NCTPS I Operation Circle CA CWPH Time bound works for Attending to leaks and puncture Breakdown works by welding in the wornout pipes and valves area and painting the corroded pipe lines and general house keeping of pump and butterfly valve area
2023_EB_353166_1
SE/OPN/NCTPS-I/25/2023-24
Open Tender
Power/Energy Projects/Products
Works
365 days
NCTPS I
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹23,400
Yes
5 Sept 2023
1 Aug 2023
16 Aug 2023
1 Aug 2023
15 Aug 2023
1 Aug 2023
Amount
S.S. welding of one full circle joint in 20 NB SS pipe, including cost of welding electrodes, consumables and T&P hire charges.
S.S. welding of one full circle joint in 25 NB SS pipe, including cost of welding electrodes, consumables and T&P hire charges.
S.S. welding of one full circle joint in 50 NB SS pipe, including cost of welding electrodes, consumables and T&P hire charges.
S.S. welding of one full circle joint in 80 NB SS pipe, including cost of welding electrodes, consumables and T&P hire charges.
S.S. welding of one full circle joint in 100 NB SS pipe, including cost of welding electrodes, consumables and T&P hire charges.
S.S. welding of one full circle joint in 150 NB SS pipe, including cost of welding electrodes, consumables and T&P hire charges.
S.S. welding of one full circle joint in 200 NB SS pipe, including cost of welding electrodes, consumables and T&P hire charges.
S.S. welding of one full circle joint in 250 NB SS pipe, including cost of welding electrodes, consumables and T&P hire charges.
Welding for one full circle MS pipe welding joint including joint including cost of welding electrodes, consumables and T&P hire charges25 NB.
Welding for one full circle MS pipe welding joint including joint including cost of welding electrodes, consumables and T&P hire charges 50 NB
Welding for one full circle MS pipe welding joint including joint including cost of welding electrodes, consumables and T&P hire charges 100 NB.
Welding for one full circle MS pipe welding joint including joint including cost of welding electrodes, consumables and T&P hire charges 125 NB.
Welding for one full circle MS pipe welding joint including joint including cost of welding electrodes, consumables and T&P hire charges 150 NB.
One running metre of MS patch welding on deteriorated components and accessories of CWPH including welding electrodes, gas, consumables and T&P
Cleaning, removing of rust in the corroded pipe lines in CWPH area with one coat of protective coating of self priming Epoxy primer (DFT100+10%microns) and two coats of Epoxy HB coal tar paint (DFT 125+10% microns per coat) (Total 350+10% microns) using different shades after thorough scrapping with emery sheet with manual labour and as per the direction and satisfaction of the Engineer in charge, the rate including the cost of scaffolding, T&P Labour, lead, lift, etc., complete
Dismantling of BFV electrically operated actuator and Complete servicing of actuator assembly replacing worn - out spares and reassembling the actuator assembly properly and Inspection of Open / Close operation, setting of torque & limit switches and commissioning for BFVs in Unit I, II & III during breakdown / overhauling period including cost of consumables and hire charges for T&Ps
Removal of debris & sludge from inner / outer lubricating water tank, by isolating suction valves and disconnecting drain pipes, thorough cleaning of tank inner surfaces, collecting & disposal of debris, cleaning of filters
Chipping & removal of the damaged concreates for lube water inner & outer tank tapping pipes
Providing and placing RCC 1:1 ½:3 using 20MM HSG metal including cost of all materials, lead, lift labour, LWF, vibrating charges and mixing charges excluding the cost of reinforcement etc. complete.
NERINA ENGINEERING WORKS
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .