| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹80.7 LAccepted-AOC DISTT SIKAR | SIKAR | RAJASTHAN | ₹80.7 L | L1 | Accepted-AOC L1 |
| 2 | L2₹83.2 LRejected-AOC | ₹83.2 L | L2 | Rejected-AOC L2 |
| Sl No | Description | Qty | Unit | SRI SAIRAM CONSTRUCTIONS L2 | M/s. RK AND CO L1 |
|---|---|---|---|---|---|
| 1.00Name of Work :Construction of Community Hall at Muthuvanthidal Village and Panchayat | |||||
| 2.00Ground Floor | |||||
| 3.00 | Earth work excavation for foundation in all soils and sub soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation. | 86.14 | cum | 271 ₹23,343.94 | 263 ₹22,654.82 |
| 4.00 | Filling in Basement with excavated Earth in layers of not more than 15cm. Thick well rammed, watered and consolidated complying with standard specifications etc., complete. | 2,465.02 | cum | 48 ₹1.2 L | 46 ₹1.1 L |
| 5.00 | Cement concrete 1 : 4: 8 mix using 40 mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed. | 27.94 | cum | 6,042 ₹1.7 L | 5,866 ₹1.6 L |
| 6.00Brick work in CM 1 : 5 mix using country bricks ground mould of size 23 x 11 x 7 cm for the following including curing etc., complete complying with standard specifications. | |||||
| 7.00 | Basement | 29.44 | Sqm | 6,370 ₹1.9 L | 6,184 ₹1.8 L |
| 8.00 | Ground Floor | 49.97 | Sqm | 6,466 ₹3.2 L | 6,277 ₹3.1 L |
| 9.00 | Supplying and fabricating and placing in position MS steel or ribbed for steel for all reinforced cement concrete works as per the design given including cost of steel and binding wire in all floors etc., complete complying with standard specification. | 12,187.92 | Kg | 95 ₹11.6 L | 92 ₹11.2 L |
| 10.00Supplying and Erecting centering for sides and soffits including necessary supports and strutting upto 3.29m height for plane surface in all floors with all cross bracing using mild steel sheets of size 90x60cm and 10 gauge stiffened, welded with steel angle of size 25x25x3 mm for boarding laid over silver oak joists (Country wood) of size 10x6.5cm spaced @ about 90cm c/c and supported by casurina props of 10-13cm dia spaced @ 75cm c/c etc., complete complying with standard specifications and as directed by the departmental officers. Rate for 10Sqm for the following items (RCC floor slab, roof slab, Rectangular/Square, tee/All beams, lintels, staircase waist slabs, landing slabs, landing beam, portico beam etc. | |||||
Tender Value
₹84 L
EMD Value
₹84,000
Closing Date
24 Feb 2026, 3:00 pmClosed
Project Director
DRDA,Sivagangai
Construction of Community Hall at Muthuvanthidal Village and Panchayat in Thiruppuvanam Block
2026_RDTN_661102_1
TPM_SCPAR_2025-2026
Open Tender
Civil Works - Buildings
360 days
Sivagangai
Please refer Tender documents.
5 documents required · 5 mandatory
₹0
₹84,000
9 Mar 2026
19 Feb 2026
24 Feb 2026
19 Feb 2026
24 Feb 2026
19 Feb 2026
Ground Floor
Earth work excavation for foundation in all soils and sub soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Filling in Basement with excavated Earth in layers of not more than 15cm. Thick well rammed, watered and consolidated complying with standard specifications etc., complete.
Cement concrete 1 : 4: 8 mix using 40 mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed.
Brick work in CM 1 : 5 mix using country bricks ground mould of size 23 x 11 x 7 cm for the following including curing etc., complete complying with standard specifications.
Basement
Ground Floor
Supplying and fabricating and placing in position MS steel or ribbed for steel for all reinforced cement concrete works as per the design given including cost of steel and binding wire in all floors etc., complete complying with standard specification.
Supplying and Erecting centering for sides and soffits including necessary supports and strutting upto 3.29m height for plane surface in all floors with all cross bracing using mild steel sheets of size 90x60cm and 10 gauge stiffened, welded with steel angle of size 25x25x3 mm for boarding laid over silver oak joists (Country wood) of size 10x6.5cm spaced @ about 90cm c/c and supported by casurina props of 10-13cm dia spaced @ 75cm c/c etc., complete complying with standard specifications and as directed by the departmental officers. Rate for 10Sqm for the following items (RCC floor slab, roof slab, Rectangular/Square, tee/All beams, lintels, staircase waist slabs, landing slabs, landing beam, portico beam etc.
Upto Basement
Column
Above GL
RCC Cement concrete 1 : 1 ½ : 3 using 20 mm ISS HBG metal for all RCC item of works excluding cost of Reinforcement and fabrication charges, centering and shutting but including curing and providing fixtures like fan clamps in the RCC floor or roof slabs wherever necessary and bearing surfaces of walls sides and bottom of the slabs, beams etc., shall be finished smooth with cement mortar 1 : 3, 12mm thick extra as directed by the departmental officers etc.,
Basement
Ground Floor
Plain cement concrete with CC 1 : 2 : 4 using 20 mm iss metal including cost and conveyance of all materials to site and labour charges etc., complete
Plastering with CM 1 : 5, 12mm thick over the cement concrete for floor finish including curing etc., complete complying with standard specifications and as directed by the departmental officers.
Supplying and applying of two coats of putty of 3mm thick over the exposed RCC surface of ceiling including finishing the joints smoothy with grinding machine and the surface shall be thoroughly cleaned out of dust and scrubbing. The Surface shall then be allowed to dry for atleast 48 hours. It shall then be sand papered (waterproof abrasive sheet) to give a smooth and even surface. Any unevenness shall be made good by applying 1st coat of putty mixed with water on the entire surface including filling up the undulations and applying 2nd coat of putty after 6 hours of 1st coat of putty and then sand papering (waterproof abrasive sheet) the same after it is dry and finishing the surface smoothly, etc., complete.
Paving the floor with Polished Rajasthan Kota Stone Slabs of 20mm thick with Machine Cut Edges of size below 2'0" x 2'0" in Cement mortar 1:3 etc., complete complying with standard specifications and as directed by the departmental officers.
Dadooing of walls with glazed tiles of size laid in CM 1:2, 10mm thick & pointing with white cement using 0.4kg/cm2 -10Sqm.
Paving the floor with pre-polished concrete anti-skid step tiles (Required shape and design) of 20mm thick of approved quality and colour laid in Cement Mortar 1:3 (One Cement and Three crushed stone M.Sand) 20mm thick and pointed with white cement mixed with colouring pigment at the rate of 0.40 Kg. / sq.m., curing, etc., complete complying with standard specification and as directed by the departmental officers. (The make and brand of the tiles should be got approved by Executive Engineer before use on works)
Distembering two coats oil bound distember over priming coat inculding cost and conveyance of all materials to site and all loboure charges etc complete ( Inner wall )
Exterior Emulsion painting two coats with best approved quality and colour paint over one coat of Base coat including cost and convyance of all materials to work site and labour charges etc., complete.
Painting two coats using best synthetic enamel paint over new iron works including cost and conveyance and all labour charges etc. complete
Supply & Delivery of UPVC of following size including cost and conveyance of all materials to site and all labour charges etc complete
Upvc Door
Upvc Window
Upvc Ventilator
Towards cost for fixing of UPVC Doors & Windows including cost and conveyance of all materials to site and all labour charges etc complete
Upvc Door
Upvc Window
Upvc Ventilator
Provision for SS Hand rail Arrangements in Ramp & Staircase etc complete
110mm PVC pipe
110mm PVC Pipe down fall pipe
110mm PVC Elbow
110mm PVC Tee
Provision for Electrification arrangements
Service connection bearer wire SD-64
Meter Board SD 125
Light point SD20
Supplying & Fixing of Tube Light SD87
CFL at toilet SD80
Fan Point SD20
Supplying & Fixing of Fan SD106
Plug Point (3x3) SD40
Provision for EB Deposit
Provision for Ground level earthing SD 126
First Floor
Brick work in CM 1 : 5 mix using country bricks ground mould of size 23 x 11 x 7 cm for the following including curing etc., complete complying with standard specifications.
Frist Floor
Supplying and fabricating and placing in position MS steel or ribbed for steel for all reinforced cement concrete works as per the design given including cost of steel and binding wire in all floors etc., complete complying with standard specification.
Supplying and Erecting centering for sides and soffits including necessary supports and strutting upto 3.29m height for plane surface in all floors with all cross bracing using mild steel sheets of size 90x60cm and 10 gauge stiffened, welded with steel angle of size 25x25x3 mm for boarding laid over silver oak joists (Country wood) of size 10x6.5cm spaced @ about 90cm c/c and supported by casurina props of 10-13cm dia spaced @ 75cm c/c etc., complete complying with standard specifications and as directed by the departmental officers. Rate for 10Sqm for the following items (RCC floor slab, roof slab, Rectangular/Square, tee/All beams, lintels, staircase waist slabs, landing slabs, landing beam, portico beam etc.
Column
Above GL
RCC Cement concrete 1 : 1 ½ : 3 using 20 mm ISS HBG metal for all RCC item of works excluding cost of Reinforcement and fabrication charges, centering and shutting but including curing and providing fixtures like fan clamps in the RCC floor or roof slabs wherever necessary and bearing surfaces of walls sides and bottom of the slabs, beams etc., shall be finished smooth with cement mortar 1 : 3, 12mm thick extra as directed by the departmental officers etc.,
Frist Floor
Plain cement concrete with CC 1 : 2 : 4 using 20 mm iss metal including cost and conveyance of all materials to site and labour charges etc., complete
Weathering course with best quality broken brick jelly of size 20mm uniform gauge in pure slaked lime (no sand to be listed) over the RCC roof slab in the proposition being brick jelly to lime 32:12 ½ by volume and laid over into a single layer and consolidated to required finished thickness beating the mixture with wooden.
Finishing the top of roof with one course of machine pressed tiles of size 230mm x 230mm x 20mm of approved quality set in Cement Mortar 1:3 (One Cement and Three Crushed stone M.Sand) 12mm thick mixed with water proofing compound conforming to ISS at 2% by weight of cement used and the joints pointed neatly to full depth of tiles with the same cement mortar mixed with red oxide and water proofing compound including curing etc., complete complying with standard specification and as directed by the departmental officers
Plastering with CM 1 : 5, 12mm thick over the cement concrete for floor finish including curing etc., complete complying with standard specifications and as directed by the departmental officers.
Supplying and applying of two coats of putty of 3mm thick over the exposed RCC surface of ceiling including finishing the joints smoothy with grinding machine and the surface shall be thoroughly cleaned out of dust and scrubbing. The Surface shall then be allowed to dry for atleast 48 hours. It shall then be sand papered (waterproof abrasive sheet) to give a smooth and even surface. Any unevenness shall be made good by applying 1st coat of putty mixed with water on the entire surface including filling up the undulations and applying 2nd coat of putty after 6 hours of 1st coat of putty and then sand papering (waterproof abrasive sheet) the same after it is dry and finishing the surface smoothly, etc., complete.
Distembering two coats oil bound distember over priming coat inculding cost and conveyance of all materials to site and all loboure charges etc complete ( Inner wall )
Exterior Emulsion painting two coats with best approved quality and colour paint over one coat of Base coat including cost and convyance of all materials to work site and labour charges etc., complete.
Painting two coats using best synthetic enamel paint over new iron works including cost and conveyance and all labour charges etc. complete
Supply & Delivery of UPVC of following size including cost and conveyance of all materials to site and all labour charges etc complete
Upvc Door
Upvc Window
Upvc Ventilator
Towards cost for fixing of UPVC Doors & Windows including cost and conveyance of all materials to site and all labour charges etc complete
Upvc Door
Upvc Window
Upvc Ventilator
Supply & Delivery of Grill Gate including cost and conveyance of all materials to site and all labour charges etc complete
Providing Sanitary Arrangements including all cost etc Complete
110mm PVC pipe
110mm PVC Pipe
110mm PVC Elbow
110mm PVC Tee
Provision for Electrification arrangements
Service connection bearer wire SD-64
Meter Board SD 125
Light point SD20
Supplying & Fixing of Tube Light SD87
CFL at toilet SD80
Fan Point SD20
Supplying & Fixing of Fan SD106
Plug Point (3x3) SD40
Provision for Ground level earthing SD 126
Supply of European Water Closet
HDPE Sintex tank 1000 litre - 1 No.
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.35 MB
CommunityHall_Tpm_TENDRER_Doc.pdf
Tender Documents • 0.79 MB
BOQ_793440.xls
BOQ • 0.40 MB
Download all tender documents and submit your bid