Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.9 CrAdmitted-Finance BALIBAZAR TALAP DOOMDOOMA | TINSUKIA | ASSAM | 786151 | ₹1.9 Cr | L1 | Admitted-Finance |
| 2 | Rejected-Technical P J B ROAD PRASANTI APPARTMENT 103 P O CHEMIKUTHI PS CHANDMARI DIST KAMRUP M ASSAM | KAMRUP M | ASSAM | - | - | Rejected-Technical technically disqualified |
| Sl No | Description | Qty | Unit | MS N.K CONSTRUCTION L1 |
|---|---|---|---|---|
| 1.00 | Earth work in excavation by mechanical means (Hydraulic excavator)/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m
and lift upto 1.5 m, as directed by Engineer-in- charge.
All kinds of soil | 555.98 | cum | 205 ₹1,13,975.9 Lowest |
| 2.00 | Excavating, supplying and filling of local earth (including royalty) by mechanical
transport upto a lead of 5km also including ramming and watering of the earth in layers not exceeding 20 cm in trenches, plinth, sides of foundation etc. complete. | 552.6 | cum | 368 ₹2,03,356.8 Lowest |
| 3.00 | Dry brick pitching half brick thick in drains including supply of bricks and
preparing the surface complete :
With common burnt clay F.P.S. (non modular) bricks of class designation 7.5 | 406.77 | sqm | 607 ₹2,46,906.96 Lowest |
| 4.00 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :
1:3:6 (1 Cement: 3 coarse sand (zone-III) derived from natural sources : 6 graded stone aggregate 40mm nominal size derived from natural sources) | 21.02 | cum | 6,670 ₹1,40,203.4 Lowest |
| 5.00 | Centering and shuttering including strutting, propping etc. and removal of form for Foundations, footings, bases of columns, etc. for mass concrete | 66.3 | sqm | 307 ₹20,354.1 Lowest |
| 6.00 | Centering and shuttering including strutting, propping etc. and removal of form for Lintels, beams, plinth beams, girders, bressumers and cantilevers | 223.38 | sqm | 608 ₹1,35,815.04 Lowest |
| 7.00 | Centering and shuttering including strutting, propping etc. and removal of form for Columns, Pillars, Piers, Abutments, Posts and Struts | 336.95 | sqm | 804 ₹2,70,907.8 Lowest |
| 8.00 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level :
1:1.5:3 (1 cement: 1.5 coarse sand (zone-III) derived from natural sources : 3
graded stone aggregate 20 mm nominal size de rived from natural sources) | 142.8 | cum | 8,364 ₹11,94,370.84 Lowest |
| 9.00 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in:
Cement mortar 1:4 (1 cement: 4 coarse sand)
(a) In proportion 1:3. | 77.75 | cum | 6,882 ₹5,35,075.5 Lowest |
| 10.00 | Providing and fixing 18mm thick gang saw cut, mirror polished, premoulded and prepolished, machine cut for kitchen platforms, vanity counters, window sills, facias and similar locations of required size, approved shade, colour and texture laid over 20mm thick base cement mortar 1:4 (1 cement: 4 coarse sand), joints treated with white cement, mixed with matching pigment, epoxy touch ups, including rubbing, curing, moulding and polishing to edges to give high gloss finish etc. complete at all levels.
Granite stone slab colour black, Cherry/Ruby red
Area of slab over 0.50 sqm | 373.37 | sqm | 4,425 ₹16,52,162.25 Lowest |
Tender Value
₹1.8 Cr
EMD Value
₹3.7 L
Closing Date
30 Jul 2026, 2:00 pmClosed
SE, PWD, DIBRUGARH BLDG CIRCLE, DIBRUGARH
SE OFFICE, PWD, DIBRUGARH BLDG CIRCLE, DIBRUGARH
Construction of Bir Raghab Moran and others 8 Nos Statues and Memorial Park at Gelapukhuri, Tinsukia Phase II RSL 22
2026_PWBNH_53202_1
SE(B)/DBC/BRM-TSK/25-26/420
Open Tender
Civil Works - Building
Item Rate
365 days
TINSUKIA
Please refer Tender documents.
5 documents required · 5 mandatory
₹3,700
Yes
₹3.7 L
Yes
SE OFFICE, PWD, DIBRUGARH BLDG CIRCLE, DIBRUGARH
17 Sept 2026
23 Jul 2026
30 Jul 2026
23 Jul 2026
30 Jul 2026
23 Jul 2026
27 Jul 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator)/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m
and lift upto 1.5 m, as directed by Engineer-in- charge.
All kinds of soil | - | cum | 1.25 | - |
| 2 | Excavating, supplying and filling of local earth (including royalty) by mechanical
transport upto a lead of 5km also including ramming and watering of the earth in layers not exceeding 20 cm in trenches, plinth, sides of foundation etc. complete. | - | cum | - | - |
| 3 | Dry brick pitching half brick thick in drains including supply of bricks and
preparing the surface complete :
With common burnt clay F.P.S. (non modular) bricks of class designation 7.5 | 0.4 | sqm | 100 | ₹40 |
| 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :
1:3:6 (1 Cement: 3 coarse sand (zone-III) derived from natural sources : 6 graded stone aggregate 40mm nominal size derived from natural sources) | 1 | cum | 53 | ₹52.95 |
| 5 | Centering and shuttering including strutting, propping etc. and removal of form for Foundations, footings, bases of columns, etc. for mass concrete | 1 | sqm | 10 | ₹9.99 |
| 6 | Centering and shuttering including strutting, propping etc. and removal of form for Lintels, beams, plinth beams, girders, bressumers and cantilevers | 1 | sqm | 11 | ₹10.99 |
| 7 | Centering and shuttering including strutting, propping etc. and removal of form for Columns, Pillars, Piers, Abutments, Posts and Struts | 1 | sqm | 100 | ₹99.9 |
| 8 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level :
1:1.5:3 (1 cement: 1.5 coarse sand (zone-III) derived from natural sources : 3
graded stone aggregate 20 mm nominal size de rived from natural sources) | 0.6 | cum | 53 | ₹31.8 |
| 9 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in:
Cement mortar 1:4 (1 cement: 4 coarse sand)
(a) In proportion 1:3. | - | cum | 100 | - |
| 10 | Providing and fixing 18mm thick gang saw cut, mirror polished, premoulded and prepolished, machine cut for kitchen platforms, vanity counters, window sills, facias and similar locations of required size, approved shade, colour and texture laid over 20mm thick base cement mortar 1:4 (1 cement: 4 coarse sand), joints treated with white cement, mixed with matching pigment, epoxy touch ups, including rubbing, curing, moulding and polishing to edges to give high gloss finish etc. complete at all levels.
Granite stone slab colour black, Cherry/Ruby red
Area of slab over 0.50 sqm | - | sqm | 53 | - |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.33 MB
BidDocBRM.pdf
Tender Documents • 3.10 MB
BOQ_83801.xls
BOQ • 0.33 MB
formbid.pdf
Additional Documents • 0.20 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .