| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹6.7 CrAccepted-AOC 125 126 14 AZAD NAGAR OFFICERS COLONY HISAR | ₹6.7 Cr Quoted ₹7.4 Cr | L1 | Accepted-AOC Due to L1 bidder |
| 2 | L2₹8.1 Cr+₹67.2 L (9.07%)Rejected-AOC | ₹8.1 Cr+₹67.2 L (9.07%) | L2 | Rejected-AOC Due to L2 bidder |
| 3 | L3₹8.4 Cr+₹1.0 Cr (13.6%)Rejected-AOC | ₹8.4 Cr+₹1.0 Cr (13.6%) | L3 | Rejected-AOC Due to L3 bidder |
| 4 | L4₹8.7 Cr+₹1.3 Cr (17.9%)Rejected-AOC | ₹8.7 Cr+₹1.3 Cr (17.9%) | L4 | Rejected-AOC Due to L4 bidder |
| Sl No | Description | Qty | Unit | Y D Builders and Hotels Pvt Ltd L4 | SHIVA BUILD TECH PRIVATE LIMITED L3 | C.K. Infrastructures Ltd. L2 | Mannat Construction Company L1 |
|---|---|---|---|---|---|---|---|
| 1.00 | Providing services of qualified surveyor(s) along with all required instruments, tools, accessories and manpower for carrying out survey, establishing and recording levels and topographical details for planning and execution of works including (but not limited to) determination of finished road levels (FRL), drainage invert levels, cross-drainage/road crossing levels, longitudinal and cross-sections, benchmarks/temporary benchmarks, setting out, and any other survey works as directed by the Engineer-in-Charge. The survey team with complete equipment shall remain available at the disposal of GMDA for a period of 03 (three) months for planning/field requirements, and the entire work shall be carried out to the entire satisfaction of the Engineer-in-Charge, complete in all respects.
Payment shall be released only after submission of detailed survey findings/records to the department, duly signed by the Contractor or his authorised representative and jointly verified/signed by the concerned SDE/JE of the department, complete in all respects and as approved by the Engineer-in-Charge. | 1 | Job | 3,50,000 ₹3,50,000 | 1,00,000 ₹1,00,000 Lowest | 7,00,000 ₹7,00,000 | 1,00,000 ₹1,00,000 Lowest |
| 2.00 | The recovery of MS grill fixed on the footpath has been worked out considering a weight of 19 kg per running meter. As per site condition and approval practice, the recovery quantity has been restricted to 50% of the rate. The cost of the existing grill of the above have been worked out on the basis of theoritical quantities laid on existing site. There shall be no measurement after actual scarifying/ dismantling and no claim of agency on this score will be entertained and full recovery on the basis of quoted rate exhibited in the BOQ shall be made. No rates below reserve price will be considered for all purpose in case the agency quotes lesser than reserve price. The rate shall also include the disposal of waste material. All works upto satisfaction of engineer incharge | 23,940 | Kg. | 42 ₹-10,05,480 | 25 ₹-5,98,500 | 22 ₹-5,26,680 | 20 ₹-4,78,800 Lowest |
Tender Value
₹6.7 Cr
EMD Value
₹13.4 L
Closing Date
9 Apr 2026, 12:00 pmClosed
Amit Kumar
Division - Road Maintenance and Urban Amenities
Special Repair of Service Road along master road from Krishna chowk to Rezangla chowk Road, Gurugram, including all other works contingent thereto
2026_HRY_511024_1
2026594E91BE 31C2 46BE A08B E1E6ACAE27CC720001
Open Tender
Civil Works
Works
365 days
Gurugram
DBM BC
2 documents required · 2 mandatory
₹1,180
₹13.4 L
Yes
9 Jun 2026
25 Mar 2026
9 Apr 2026
25 Mar 2026
9 Apr 2026
25 Mar 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Providing services of qualified surveyor(s) along with all required instruments, tools, accessories and manpower for carrying out survey, establishing and recording levels and topographical details for planning and execution of works including (but not limited to) determination of finished road levels (FRL), drainage invert levels, cross-drainage/road crossing levels, longitudinal and cross-sections, benchmarks/temporary benchmarks, setting out, and any other survey works as directed by the Engineer-in-Charge. The survey team with complete equipment shall remain available at the disposal of GMDA for a period of 03 (three) months for planning/field requirements, and the entire work shall be carried out to the entire satisfaction of the Engineer-in-Charge, complete in all respects.
Payment shall be released only after submission of detailed survey findings/records to the department, duly signed by the Contractor or his authorised representative and jointly verified/signed by the concerned SDE/JE of the department, complete in all respects and as approved by the Engineer-in-Charge. | 1 | Job | - | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.83 MB
BOQ_589826.xls
BOQ • 0.37 MB
AD0156662.pdf
Additional Documents • 0.34 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .