| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹5.3 LAccepted-AOC | L1 | Accepted-AOC Accepted | |
| 2 | L2₹5.5 L+₹22,630.33 (4.31%)Rejected-Finance | L2 | Rejected-Finance Rejected |
| Sl No | Description | Qty | Unit | M CHELLAPPANDI L1 | VASANTHA CONSTRUCTIONS L2 |
|---|---|---|---|---|---|
| 1.00Construction of Composit pit at Palayampatti Village and Panchayat | |||||
| 1.01 | Earth work excavation in all clauses of soils with initial lead and lift except hard rock requiring blasting etc., complete for foundation as per SS 20B | 95.56 | m3 | 245.32 ₹23,442.78 Lowest | 255.87 ₹24,450.94 |
| 1.02 | Cement concrete 1:4:8 mix using 40mm ISS HBG metal including all cost and conveyance and all labour charges etc., complete | 3.4 | m3 | 5,081.91 ₹17,278.49 Lowest | 5,306.74 ₹18,042.92 |
| 1.03 | Supplying and Centering erecting including necessary supports on plane surface including all cost and conveyance etc complete.., | 90.69 | m3 | 339.45 ₹30,784.72 Lowest | 354.05 ₹32,108.79 |
| 1.04 | Cement concrete 1:3:6 mix using 20mm ISS metal including cost and conveyance and all labour charges etc., complete | 22.67 | m3 | 5,787.49 ₹1,31,202.4 Lowest | 6,036.42 ₹1,36,845.64 |
| 1.05 | Plastering with cement mortar 1:5 mix to 12mm thick including cost and conveyance of all materials to site and all labour charges etc | 196.74 | m3 | 263.92 ₹51,923.62 Lowest | 275.28 ₹54,158.59 |
| 1.06 | Exterior Emulsion painting two coats with best approved quality and colour paint over one coat of Base coat including cost and convyance of all materials to work site and labour charges etc., complete. | 161.99 | kg | 245.18 ₹39,716.71 Lowest | 255.72 ₹41,424.08 |
| 2.00Construction of Vermi Composit Shed at Palayampatti Village and Panchayat | |||||
| 2.01 | Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth,earth mixed with small sized boulders and hard gravelly soil as per SS 20B | 9.8 | m3 | 122.66 ₹1,202.07 Lowest | 127.93 ₹1,253.71 |
| 2.02 | Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum. | 9.8 | m3 | 5,087.91 ₹49,861.52 Lowest | 5,306.74 ₹52,006.05 |
Tender Value
₹5.8 L
EMD Value
₹5,780
Closing Date
27 Aug 2026, 4:00 pmClosed
The Block Development Officer (V.P),Aruppukottai
The Block Development Officer (V.P),Aruppukottai
1.Construction of Vermi composit shed at Palayampatti Village and Panchayat 2.Construction of Compost pit at Palayampatti Village and Panchayat
2026_RDTN_689916_1
E2/2706/2024 dated.06.07.2026
Open Tender
Civil Works
Item Wise
180 days
Palayampati
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹5,780
Yes
The Block Development Officer (V.P),Aruppukottai
23 Sept 2026
31 Jul 2026
27 Aug 2026
31 Jul 2026
27 Aug 2026
20 Aug 2026
5 Aug 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Construction of Composit pit at Palayampatti Village and Panchayat | |||||
| 1.01 | Earth work excavation in all clauses of soils with initial lead and lift except hard rock requiring blasting etc., complete for foundation as per SS 20B | 95.56 | m3 | - | - |
| 1.02 | Cement concrete 1:4:8 mix using 40mm ISS HBG metal including all cost and conveyance and all labour charges etc., complete | 3.4 | m3 | - | - |
| 1.03 | Supplying and Centering erecting including necessary supports on plane surface including all cost and conveyance etc complete.., | 90.69 | m3 | - | - |
| 1.04 | Cement concrete 1:3:6 mix using 20mm ISS metal including cost and conveyance and all labour charges etc., complete | 22.67 | m3 | - | - |
| 1.05 | Plastering with cement mortar 1:5 mix to 12mm thick including cost and conveyance of all materials to site and all labour charges etc | 196.74 | m3 | - | - |
| 1.06 | Exterior Emulsion painting two coats with best approved quality and colour paint over one coat of Base coat including cost and convyance of all materials to work site and labour charges etc., complete. | 161.99 | kg | - | - |
| 2Construction of Vermi Composit Shed at Palayampatti Village and Panchayat | |||||
| 2.01 | Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth,earth mixed with small sized boulders and hard gravelly soil as per SS 20B | 9.8 | m3 | - | - |
| 2.02 | Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum. | 9.8 | m3 | - | - |
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.52 MB
TenderDocument.pdf
Tender Documents • 1.21 MB
BOQ_829394.xls
BOQ • 0.28 MB
Corrigendum.pdf
PDF • 0.37 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .