| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹8.0 LAccepted-AOC LOCATION TAMIL NADU | KANNIYAKUMARI | TAMIL NADU | 629176 | ₹8.0 L | L1 | Accepted-AOC Accepted |
| 2 | L2₹8.1 LRejected-AOC | ₹8.1 L | L2 | Rejected-AOC Rejected |
| Sl No | Description | Qty | Unit | rajkumar | M/S.RIYA ENTERPRISES |
|---|---|---|---|---|---|
| 1.00 | Earth work open excavation in all soils and sub-soils and to full depth as may be directed except in rock requiring blasting inclusive of shoring shuttering, bailing out water wherever necessary and depositing the excavated earth with a lead of 10 mts. within the compound in places shown by the departmental officers and clearing and levelling the site, etc., complete complying with standard specification. | 53 | M3 | 8,480 ₹10,006.40 | 9,010 ₹10,631.80 |
| 2.00 | Supplying and filling the foundation and basement with stone dust in layers of not more than 15cm thick well rammed watered and compacted etc., complete complying with standard specification. | 8 | M3 | 2,400 ₹2,832 | 2,400 ₹2,832 |
| 3.00 | Plain Cement Concrete 1:4:8 (one part of cement, four part of Crushed Stone Sand (M- Sand) and eight part of coarse aggregates) using 40mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges and all incidential charges such as water providing etc., complete as per standard specification | 11 | M3 | 57,200 ₹67,496 | 58,300 ₹68,794 |
| 4.00Supplying and erecting centering for sides and soffits including necessary supports and strutting upto 3.29 M height for plane surfaces as detailed below in all floors with all cross bracings using Mild Steel sheets of size 90 x 60 cm and 10 BG stiffened with welded Mild Steel angle of size 25mm x 25mm x 3 mm for boarding laid over silver oak joists of size 10cm x 6.50 cm spaced at abote 90 cm centre to centre and supported by casurina props of 10cm to 13 cm dia spaced at not more than 75 cm centre to centre etc. complete complying with the standard specificaiton. (Payment for centering shall be given after the concrete is laid) | |||||
| 4.01 | Culvert Wall | 96 | M2 | 46,080 ₹54,374.40 | 48,000 ₹56,640 |
| 4.02 | Slab Bottom | 82 | M2 | 90,200 ₹1.1 L | 90,200 ₹1.1 L |
| 5.00 | Plain Cement Concrete 1:2:4 (one cement, two sand and four hard broken stone jelly) using 20mm jelly for wearing coat including laying, compacting, finishing and curing, etc., complete as per standard specificatins and as directed by the departmental officers. | 26 | M3 | 1,85,900 ₹2.2 L | 1,87,200 ₹2.2 L |
| 6.00 | Plastering with cement mortar 1:5 (One Part of Cement and Four part of Plastering Sand (P- Sand)) 20mm thick in all floors including cost and conveyance of all materials to site and labour charges etc, complete complying with standard specifications (S.I.309) | 36 | M2 | 11,160 ₹13,168.80 | 11,700 ₹13,806 |
| 7.00 | Supply and fixing of FRC Manhole size of 60cmx60mm Including all other labour charges etc, Complete | 8 | Nos | 20,000 ₹23,600 | 20,000 ₹23,600 |
| 8.00 | Providing and laying in position Standardised Concrete Mix M-20 Grade in accordance with IS 456 - 2000 using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement contenet of 325Kg/ cum and maximum water cement ratio of 0.55 including admixture (Plasticiser / super plasticiser) in recommended proportions as per IS 9103 to accelerate, related setting of concrete, improve workability without imparing strength and durability with about (5.0cum), 7730Kg of 20mm machine crushed stone jelly and with about (3.3 cum), 5156kg of 10 - 12mm machine crushed stone jelly and with about (4.79cum) 7670 kg of Crushed Stone Sand (M- Sand), but excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary without claiming extra cost etc., complete complying with standard specification and as directed by the departmental officers - | 10 | M2 | 73,000 ₹86,140 | 74,000 ₹87,320 |
Tender Value
₹8.5 L
EMD Value
₹8,500
Closing Date
24 Feb 2026, 3:00 pmClosed
The Commissioner,Tambaram City Municipal Corporati
No.01,Kalaivani Strete , Rajakilpakkam,chennai-73
Construction of Strom Water Drain With Cover Slab at sridevi avenue in tellus avenue phase 2 in Ward no. in 41 Zone-3
2026_DMA_664474_29
168/2026/E1
Open Tender
Civil Works
90 days
Tambaram City Municipal Corporation
Construction of Strom Water Drain With Cover Slab at sridevi avenue in tellus avenue phase 2 in Ward no. in 41 Zone-3
2 documents required · 2 mandatory
₹0
₹8,500
1 Jun 2026
23 Feb 2026
24 Feb 2026
23 Feb 2026
24 Feb 2026
23 Feb 2026
Earth work open excavation in all soils and sub-soils and to full depth as may be directed except in rock requiring blasting inclusive of shoring shuttering, bailing out water wherever necessary and depositing the excavated earth with a lead of 10 mts. within the compound in places shown by the departmental officers and clearing and levelling the site, etc., complete complying with standard specification.
Supplying and filling the foundation and basement with stone dust in layers of not more than 15cm thick well rammed watered and compacted etc., complete complying with standard specification.
Plain Cement Concrete 1:4:8 (one part of cement, four part of Crushed Stone Sand (M- Sand) and eight part of coarse aggregates) using 40mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges and all incidential charges such as water providing etc., complete as per standard specification
Supplying and erecting centering for sides and soffits including necessary supports and strutting upto 3.29 M height for plane surfaces as detailed below in all floors with all cross bracings using Mild Steel sheets of size 90 x 60 cm and 10 BG stiffened with welded Mild Steel angle of size 25mm x 25mm x 3 mm for boarding laid over silver oak joists of size 10cm x 6.50 cm spaced at abote 90 cm centre to centre and supported by casurina props of 10cm to 13 cm dia spaced at not more than 75 cm centre to centre etc. complete complying with the standard specificaiton. (Payment for centering shall be given after the concrete is laid)
Culvert Wall
Slab Bottom
Plain Cement Concrete 1:2:4 (one cement, two sand and four hard broken stone jelly) using 20mm jelly for wearing coat including laying, compacting, finishing and curing, etc., complete as per standard specificatins and as directed by the departmental officers.
Plastering with cement mortar 1:5 (One Part of Cement and Four part of Plastering Sand (P- Sand)) 20mm thick in all floors including cost and conveyance of all materials to site and labour charges etc, complete complying with standard specifications (S.I.309)
Supply and fixing of FRC Manhole size of 60cmx60mm Including all other labour charges etc, Complete
Providing and laying in position Standardised Concrete Mix M-20 Grade in accordance with IS 456 - 2000 using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement contenet of 325Kg/ cum and maximum water cement ratio of 0.55 including admixture (Plasticiser / super plasticiser) in recommended proportions as per IS 9103 to accelerate, related setting of concrete, improve workability without imparing strength and durability with about (5.0cum), 7730Kg of 20mm machine crushed stone jelly and with about (3.3 cum), 5156kg of 10 - 12mm machine crushed stone jelly and with about (4.79cum) 7670 kg of Crushed Stone Sand (M- Sand), but excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary without claiming extra cost etc., complete complying with standard specification and as directed by the departmental officers -
Suppling and fabricating and placing in position MS (or) R.T.S. bar for reinforcement to all RCC works as per the design given including cost of steel and binding wire also in all floors.
Removal of Excavated Excess Earth away from the site to 5K.M including loading and transportation charges etc, complete as per standard specification. For 1M3
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_797935.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.49 MB
BOQ_797935.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid