| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹30 LAccepted-AOC | L1 | Accepted-AOC found lowest one bidder | |
| 2 | L2₹31.6 L+₹1.6 L (5.41%)Rejected-Finance | L2 | Rejected-Finance Quoted high rates |
Tender Value
Refer Docs
EMD Value
₹60,000
Closing Date
18 Mar 2021, 2:00 pmClosed
Executive Engineer
Rural Engineering Wing Leh
Construction of Foot Bridge at Kisidho Dibling
2021_RDD_2514_5
NIT 202 UTLeh REW of 2020-21
Open Tender
Civil Works - Others
Item Rate
120 days
Leh
Please refer Tender documents.
6 documents required · 6 mandatory
₹1,000
Yes
Executive Engineer
₹60,000
Yes
12 Apr 2021
11 Mar 2021
20 Mar 2021
11 Mar 2021
18 Mar 2021
11 Mar 2021
Amount
Earth work in excavation by manual means over areas (Exceeding 30 em and upto 1.5 mtr in depth, 1.5 mtr in width as well as 10 sqm. on plan) including disposal of excavated earth upto 1 mtr from cutting edge, disposed earth to be levelled and neatly dressed in All kinds of Soil
Earth work in excavation by manual means over areas (Exceeding 30cm and upto 1.5 mtr in depth, 1.5 mtr in width as well as 10 sqm. on plan) including disposal of excavated earth upto 1 mtr from cutting edge, disposed earth to be levelled and neatly dressed Ordinary rock
Earth work in excavation by manual means over areas (Exceeding 30cm and upto 1.5 mtr in depth, 1.5 mtr in width as well as 10 sqm. on plan) including disposal of excavated earth upto 1 mtr from cutting edge, disposed earth to be levelled and neatly dressed Hard rock (Blasting Prohibited)
Providing and laying dry stone soling of any thickness in horizontal level excluding cost of stone
Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering- All work upto plinth level.1:4:8 (1 cement: 4 fine sand : 8 graded stone aggregate 40mm nominal size) Nallah
Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutmen"ts, posts ans sturts, etc. upto floor five level excluding cost of centring, shuttering, fmishing and reinforcement 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded crushed stone aggregate 20mm nominal size)
Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete.Thermo-Mechanically Treated bars.
Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering- All work upto plinth level.1:3:6 (1 cement: 3 coarse sand: 6 gradedstone aggregate 20mm nominal size) Nallah
Centring and shuttermg including strutting, propping etc. and removal of form for·Columns, Pillars, Piers, Abutments, Posts and Struts
Random Rubble masonry with hard stone from nallah in foundation and plinth including levelling up with cement concrete 1 :6:12 ( 1 Cement: 6 coarse sand : 12 graded stone aggregate 20mm nominal size) at plinth level with cement mortar 1:6 (1 Cement: 6 coarse sand)
Providing wood work in frames of false ceiling, partitions etc. sawn and fixed in position Budloo / Fir wood
Providing cable ropes including carriage from leh to dipling rong main cable ropes 32mm dia
Providing cable ropes including carriage from leh to dipling rong suspender rope 16 mm dia
Carriage of stone by MT for 300mtrs by head load
Carriage of sand and coarse aggregate by head load for 300mtrs
Carriage of cement and steel from 252km by MT and 18km by head load
Carriage of timber from 252 km by MT and 18 km by head load
M/S ISHEY TUNDUP
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .