Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.2 LAdmitted-Fee/PreQual/Technical/Finance | ₹2.2 L | L1 | Admitted-Fee/PreQual/Technical/Finance |
| 2 | L2₹2.5 L+₹31,968.47 (14.8%)Admitted-Fee/PreQual/Technical/Finance | ₹2.5 L+₹31,968.47 (14.8%) | L2 | Admitted-Fee/PreQual/Technical/Finance |
| Sl No | Description | Qty | Unit | SENTHILKUMAR CONTRACTOR L1 | V SUBRAMANIA PILLAI WORKS CONTRACTOR L2 |
|---|---|---|---|---|---|
| 1.00Providing approach Paver Block at Kadiyapattanam Segregation shed in Muttom Village Panchayat of Kurunthencode Panchayat Union | |||||
| 1.01 | Earthwork excavation for foundation in all sois and subsoils to full depth as directed as perr SS 20B | 5.88 | cum | 218.94 ₹1,287.37 Lowest | 242.68 ₹1,426.96 |
| 1.02 | Cement concrete 1 : 4 : 8 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. | 2.7 | cum | 4,422.99 ₹11,942.07 Lowest | 4,979.83 ₹13,445.54 |
| 1.03 | Supplying and erecting centering shuttering including necessary supports for road sides including conveyance of all materials to site and proper centering etc complete. | 14.8 | sqm | 124.5 ₹1,842.6 Lowest | 138 ₹2,042.4 |
| 1.04 | Cement concrete1:3:6 mix using 20mm metal including watering wherever necessary and laid in layer not more than 15cm thick compacting etc. Complete | 3.4 | cum | 5,093.45 ₹17,317.73 Lowest | 5,670.8 ₹19,280.72 |
| 1.05 | Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 | 17.85 | cum | 1,770.17 ₹31,597.53 Lowest | 2,337.17 ₹41,718.48 |
| 1.06 | Providing and Laying of Interlocking Concrete (Surface Textured) Block Pavements having thickness 60mm and compacted over a thin bedding M.Sand layer of 25 mm thickness and joints shall be filled by fine M.Sand of specified grading as per table 1500.6 of Specification of Rural roads-2014 and Technical specification clause 1504. | 178.48 | sqm | 640.25 ₹1,14,271.82 Lowest | 711.07 ₹1,26,911.77 |
| 1.07 | Cement concrete1:2:4 mix using 20mm metal including watering wherever necessary and laid in layer not more than 15cm thick compacting etc. Complete | 0.84 | cum | 5,541.74 ₹4,655.06 Lowest | 6,167.6 ₹5,180.78 |
| 1.08 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package} | 1 | GST Amount (in Rupees) | 32,925 ₹32,925 Lowest | 37,801 ₹37,801 |
Tender Value
Refer Docs
EMD Value
₹2,870
Closing Date
30 Jul 2026, 3:00 pmClosed
Block Development Officer (V.Pts)
Kurunthencode Panchayat Union
Providing Approach Paver Block at Kadiyapattinam Segregation Shed in Muttom Vpt
2026_RDTN_686367_1
A10/54/2026(5) Date15/07/2026
Open Tender
Civil Works
Item Rate
Kurunthencode Panchayat Union
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹2,870
30 Jul 2026
16 Jul 2026
30 Jul 2026
16 Jul 2026
30 Jul 2026
16 Jul 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Providing approach Paver Block at Kadiyapattanam Segregation shed in Muttom Village Panchayat of Kurunthencode Panchayat Union | |||||
| 1.01 | Earthwork excavation for foundation in all sois and subsoils to full depth as directed as perr SS 20B | 5.88 | cum | 263.78 | ₹1,551.03 |
| 1.02 | Cement concrete 1 : 4 : 8 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. | 2.7 | cum | 5,412.86 | ₹14,614.72 |
| 1.03 | Supplying and erecting centering shuttering including necessary supports for road sides including conveyance of all materials to site and proper centering etc complete. | 14.8 | sqm | 150 | ₹2,220 |
| 1.04 | Cement concrete1:3:6 mix using 20mm metal including watering wherever necessary and laid in layer not more than 15cm thick compacting etc. Complete | 3.4 | cum | 6,163.91 | ₹20,957.29 |
| 1.05 | Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 | 17.85 | cum | 2,540.4 | ₹45,346.14 |
| 1.06 | Providing and Laying of Interlocking Concrete (Surface Textured) Block Pavements having thickness 60mm and compacted over a thin bedding M.Sand layer of 25 mm thickness and joints shall be filled by fine M.Sand of specified grading as per table 1500.6 of Specification of Rural roads-2014 and Technical specification clause 1504. | 178.48 | sqm | 772.9 | ₹1,37,947.19 |
| 1.07 | Cement concrete1:2:4 mix using 20mm metal including watering wherever necessary and laid in layer not more than 15cm thick compacting etc. Complete | 0.84 | cum | 6,703.91 | ₹5,631.28 |
| 1.08 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package} | - | GST Amount (in Rupees) | - | - |
stage.html
html • 0.02 MB
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.09 MB
BOQ_825071.xls
BOQ • 0.32 MB
PVB.pdf
Tender Documents • 0.53 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .