Loading…
Tenderkart now works inside Claude and ChatGPT: search and analyse tenders right from your chat
Loading…
Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Status |
|---|---|---|
| 1 | Admitted-Finance | Admitted-Finance |
| 2 | Admitted-Finance | Admitted-Finance |
| 3 | Admitted-Finance | Admitted-Finance |
Tender Value
Refer Docs
EMD Value
₹6,000
Closing Date
22 Feb 2023, 6:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
SE ETC Shahjahanpur
Electy. Trans. Circle shahjahanpur
Replacement of Gasket of 100MVA T/f and other associated works at 220KV S/S Sitapur under ETD Sitapur
2023_UPTCL_773847_1
Short Term E. Tender no. 58ETC(S)/2022-23
Open Tender
Electrical Works
Fixed-rate
60 days
Sitapur
Please refer Tender documents.
2 documents required · 2 mandatory
₹885
0423002100107147 IFSC Code No. PUNB0042300
₹6,000
15 Mar 2023
10 Feb 2023
23 Feb 2023
10 Feb 2023
22 Feb 2023
10 Feb 2023
10 Feb 2023 - 22 Feb 2023
Amount
Following work is to be carried out at 220KV Sub-Station Sitapur for arresting oil leakage of 100 MVA T/F make Alstom make Mfg Year 2000 by Gasket Repacement:-
Partialy dismantling & safe stacking of emulsifire air pipe line & water pipe line and proper stacking of 100 MVA T/F.
Draining of T/F Oil upto the required level in 209 LTR capacity oil durms.
Dismantaling of 100 MVA T/F, HV/LV side bushing all pipe lines conservator tank, radiator, bucholz relay headres, tap changer turrets OLTC pipe line including opening of jumpers from HV/LV Bushing.
Replacement of oil Gasket including top cover of T/F by providing fixing new gasket as per existing size made of rubberized core sheet katika/nucore brands grade 07 including asket of oil pumps.
Cleaning and Flushing of Transformer main tank by hot oil removing of sludge from the bottom of main tank create the vacuum inside the T/F tank and maintain it for 24 Hrs.
Overhauling of diverter switch after drain out of dirty oil.
Erection of 100 MVA T/F of HV/LV side bushing turrets, radiator, conservator tank, bucholz relay and connecting all pipe lines including Jumpering of HV/LV Bushing.
Complete evacuation of 100 MVA T/F main tank and filling of dry Air/Dry nitrogen of dew point 50 cͦ or better in vacuum up to pressure of 0.25 kg/cm2 and the again evacuate the Transformer tank after required time interval (approx. 12/24 hrs) using centrifuging machine.
Creating the vacuum inside the main tank for period for 24 hour step by step in 100 MVA T/F
Filling of T/F oil in oil tank and its centrifuging upto required BDV
Centrifuging of complete T/F oil (39500 Ltr.) of 100 MVA T/F till the required BDV value.
Carriage of 20/40 KL empty oil tank for the centrifuging of T/F oil where it is available within distance of 50 Km Approx. including carefully loading empty oil tank at 132KV S/S Neri & unloading at 220KV S/S Sitapur.
Spray painting of 100 MVA Transformer with one coat of red oxide primer and two coats of standard make Smoke Grey, Good quality enamel paint after cleaning of rust, dust and oil spots etc.
Meena Elect & Engg. Works
Gupta Elect and Engg Works
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .