Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹2.5 LAccepted-Finance BYE PASS N H NEAR STATE BANK OF INDIA SIDHRA JAMMU | 1 | Accepted-Finance Found Eligible | |
| 2 | 2₹2.5 L+₹1,700 (0.69%)Accepted-Finance MAIN ROAD SIDHRA JAMMU | JAMMU | JAMMU AND KASHMIR | 2 | Accepted-Finance Found Eligible | |
| 3 | 3₹2.5 L+₹3,400 (1.38%)Accepted-Finance BHAGWATI NAGAR JAMMU | 3 | Accepted-Finance Found Eligible |
| Sl No | Description | Qty | Unit | GS ENGG WORKS L2 | BEE AAR ENTERPRISES L3 | M/S TRIKUTA ELECTRICAL & MECHANICAL WORKS L1 |
|---|---|---|---|---|---|---|
| 1.00 | 1. Reconditioning of D/O Gate at RD 54000
The work involves dismantling of the existing D/O gate at RD 54000 from its hoisting arrangement and safe extraction using chain pulley block, tripod stand and manual labour from the embedded blocks and then the gate to be shifted to workshop. The damaged and rusted portions of the gate shall be removed and repaired by patch welding using new MS sheet of suitable gauge.
The work includes fabrication, supply and installation of a new winch machine of 3 Ton capacity complete with cover, rain pipe, base plate and stem rod. The repaired gate shall be lowered into position, aligned properly and fitted with the hoisting system using nuts and bolts. The stem rod shall be fixed and aligned to ensure smooth vertical operation. Testing of the gate shall be carried out after installation.
2. Reconditioning of D/O Gate at RD 56600
The existing D/O gate at RD 56600 shall be dismantled from the hoisting structure and extracted safely with the help of chain pulley block, tripod stand and manual labour and then the gate to be shifted to workshop. The rusted and deteriorated sections shall be removed and repaired through patch welding using new MS sheet of proper thickness. P/F of hoisting for resting of winch machine made out of M S channel ISMC75.
The work includes fabrication, supply and installation of a new winch machine of 3 Ton capacity complete with cover, rain pipe, base plate and stem rod. The repaired gate shall be lowered into position, aligned properly and fitted with the hoisting system using nuts and bolts. The stem rod shall be fixed and aligned to ensure smooth vertical operation. Testing of the gate shall be carried out after installation.
3. Reconditioning of Ditch Gate & Escape Gate of D7
The ditch gate and escape gate of D7 shall be dismantled from their existing hoisting systems and extracted using mechanical lifting arrangements and manual labour and then the gates to be shifted to workshop. The corroded portions of the gate leaves shall be cut out and repaired by welding new MS sheets, MS channels of appropriate gauge.
The work includes supply, fabrication and installation of 5-ton capacity (2no.) winch machines complete with cover, rain pipe, base plate and stem rod. After repairs, the gates shall be lowered into position, aligned, and fitted with hoisting components. Stem rods shall be secured and adjusted for smooth and safe operation. Final testing shall be conducted to ensure proper functioning.
The work also includes too and fro transportation charges of repairing of gates at workshop. The work includes surface preparation using emery paper, application of one coat of red oxide primer and two coats of paint, greasing of all moving parts, cost of materials, tools and tackles, labour charges, welding set hire charges and carriage of equipment to site. | 1 | Job | 2,465 ₹2,44,035 | 4,998 ₹2,44,902 | 4,964 ₹2,43,236 Lowest |
Tender Value
₹2.5 L
EMD Value
₹4,968
Closing Date
28 Feb 2026, 2:00 pmClosed
Executive Engineer MID Akhnoor/Nowshera
Office of Executive Engineer MID Akhnoor/Nowshera
Reconditioning of D/O gate at RD 54000, RD 56600, Ditch gate of D7 and escape gate of D7 with allied works installed on New Partap Canal
2026_IFC_304173_1
MID/AN/112
Open Tender
Machineries/ Mechanical Engg Items
Item Wise
10 days
NPC
Please refer Tender documents.
7 documents required · 7 mandatory
₹200
Executive Engineer MID Akhnoor/Nowshera
₹4,968
Yes
Office of Executive Engineer MID Akhnoor/Nowshera
20 Mar 2026
21 Feb 2026
2 Mar 2026
21 Feb 2026
28 Feb 2026
23 Feb 2026
23 Feb 2026
1. Reconditioning of D/O Gate at RD 54000 The work involves dismantling of the existing D/O gate at RD 54000 from its hoisting arrangement and safe extraction using chain pulley block, tripod stand and manual labour from the embedded blocks and then the gate to be shifted to workshop. The damaged and rusted portions of the gate shall be removed and repaired by patch welding using new MS sheet of suitable gauge. The work includes fabrication, supply and installation of a new winch machine of 3 Ton capacity complete with cover, rain pipe, base plate and stem rod. The repaired gate shall be lowered into position, aligned properly and fitted with the hoisting system using nuts and bolts. The stem rod shall be fixed and aligned to ensure smooth vertical operation. Testing of the gate shall be carried out after installation. 2. Reconditioning of D/O Gate at RD 56600 The existing D/O gate at RD 56600 shall be dismantled from the hoisting structure and extracted safely with the help of chain pulley block, tripod stand and manual labour and then the gate to be shifted to workshop. The rusted and deteriorated sections shall be removed and repaired through patch welding using new MS sheet of proper thickness. P/F of hoisting for resting of winch machine made out of M S channel ISMC75. The work includes fabrication, supply and installation of a new winch machine of 3 Ton capacity complete with cover, rain pipe, base plate and stem rod. The repaired gate shall be lowered into position, aligned properly and fitted with the hoisting system using nuts and bolts. The stem rod shall be fixed and aligned to ensure smooth vertical operation. Testing of the gate shall be carried out after installation. 3. Reconditioning of Ditch Gate & Escape Gate of D7 The ditch gate and escape gate of D7 shall be dismantled from their existing hoisting systems and extracted using mechanical lifting arrangements and manual labour and then the gates to be shifted to workshop. The corroded portions of the gate leaves shall be cut out and repaired by welding new MS sheets, MS channels of appropriate gauge. The work includes supply, fabrication and installation of 5-ton capacity (2no.) winch machines complete with cover, rain pipe, base plate and stem rod. After repairs, the gates shall be lowered into position, aligned, and fitted with hoisting components. Stem rods shall be secured and adjusted for smooth and safe operation. Final testing shall be conducted to ensure proper functioning. The work also includes too and fro transportation charges of repairing of gates at workshop. The work includes surface preparation using emery paper, application of one coat of red oxide primer and two coats of paint, greasing of all moving parts, cost of materials, tools and tackles, labour charges, welding set hire charges and carriage of equipment to site.
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.52 MB
BOQ_988078.xls
BOQ • 0.24 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .