| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹4.8 LAccepted-Finance | 1 | Accepted-Finance lOWEST | |
| 2 | 2₹4.9 L+₹5,984 (1.24%)Rejected-Finance | 2 | Rejected-Finance SECOND LOWEST | |
| 3 | 3₹4.9 L+₹8,059 (1.67%)Rejected-Finance | 3 | Rejected-Finance THIRD LOWEST |
Tender Value
₹5.0 L
EMD Value
₹10,000
Closing Date
12 Jun 2023, 3:00 pmClosed
DIVISIONAL FOREST OFFICER DIGLIPUR
DIVISIONAL FOREST OFFICE DIGLIPUR
Construction of RCC Retaining Wall behind Qtr. No. AB/P-3(C) at Aerial Bay camp under Diglipur Range.
2023_DFODP_10536_1
DFO/DP/2024/01
Open Tender
Construction Works
Works
60 days
DIGLIPUR
Please refer Tender documents.
7 documents required · 7 mandatory
₹0
₹10,000
19 Jun 2023
6 Jun 2023
12 Jun 2023
6 Jun 2023
12 Jun 2023
6 Jun 2023
Amount
Earth work in excavation by mechanical means (Hydraulic excavator)/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.
All kinds of soil
Retaining wall Foundation
Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m.
Excavation quantity cum
Dedication Concreat quantity cum
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :
1:4:8 (1 Cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size)
footing section A
footing Section B
Providing and laying in position specified grade of reinforced cement concrete,excluding the cost of centring , shuttering , finishing and reinforcement - All work upto plinth level.
1:1.5:3 ( 1 cement : 1.5 coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size) etc as per Annexure D/Estimate enclsoed
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.
Centring and shuttering including strutting, propping etc. and removal of form for:
Columns, Pillars, Piers, Abutments, Posts and Struts.
12 mm cement plaster on rough side of single or half brick wall of mix :
1 : 4 ( 1 cement : 4 fine sand )
Finishing wall with water proofing cement primer of required shade:
Two or more coats applied @ 3.84 kg/10sqm.
Distempering with 1st quality acrylic diastemper
New work (two or more coats)
VISHAL GORAI
SMTI. SULATA BAROI
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .