Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Status |
|---|---|---|
| 1 | Admitted-Finance | Admitted-Finance |
| 2 | Admitted-Finance | Admitted-Finance |
Tender Value
₹4.5 L
EMD Value
₹4,500
Closing Date
14 Jun 2022, 1:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
SE EDC-I
SE EDC-I HYDEL COLONY BULANDSHAHR
ELECTRIC WORK
2022_PVVNL_706712_1
T-17/EDC-I/B/2022-23
Open Tender
Electrical Works
Item Rate
30 days
BULANDSHAHR
PLZ REFER TENDER DOCUMENT
2 documents required · 2 mandatory
₹1,180
SE EDC-I
₹4,500
18 Jun 2022
9 Jun 2022
14 Jun 2022
9 Jun 2022
14 Jun 2022
9 Jun 2022
30 days
Amount
fo|qr forj.k [k.M&[kqtkZ@"k"Ve] cqyUn'kgj] ds vUrZxr lej Iyku esa 33@11 ds0oh0 fo|qr midsUnzksa ls iksf”kr vf/kHkkfjr forj.k ifjorZdksa dh vf/kHkkfjrk nwj djus gsrq {kerko`f) gq, ifjorZd LFkkfir djus] ykbZu fuekZ.k dj u;s ifjorZd LFkkfir djus rFkk lqj{kk dh n`f”V ls 250@400 dsoh, ifjorZdksa dh vfFkZx] fifyUFk o QSfUlx djus dk dk;ZA
Carriage of fallowings from ESC. BSR to pit site on kachcha pacaa road including loading and unloading chagres at both ends, rcquricd for proper completion of work, distance about to 60 Kms.
S.T/PCC Pole 11/8.5 mtr Long.
Carriage of All line Material from store center BSR to j.e store Sub station as ACSR Weasel conductor, ABC conductor GI Wire, Earth Wire. M.S. Chanel, Angle, Stay & Earthig Rods, Barbed Wire. Disc Insulator etc.
Erection of Single pole support including complete 1 IT fittings as per RESPO manual and as per direction of Engineer in charge including the cost of labour, T&P and carrier etc. required for proper completion of work.
Erection of Double pole/Scation Pole support including complete 1 IT fittings as per RESPO manual and as per direction of Engineer in charge including the cost of labour, T&P and carrier etc. required for proper completion of work.
Grouting of Single support shall be grouted with cement, sand and birck ballast/stone ballast in ratio 1:4:8 =30x3030 cms. including the cost of cement, sand, birck ballast/stone ballast, etc. as per actual size requirement, as per RESPO manual and as per direction of Engineer in charge including the cost of labour, T&P and carrier etc. required for proper completion of work.
Grouting of Double pole support shall be grouted with cement, sand and birck ballast/stone ballast in ratio 1:4:8 =30x3030 cms. including the cost of cement, sand, birck ballast/stone ballast, etc. as per actual size requirement, as per RESPO manual and as per direction of Engineer in charge including the cost of labour, T&P and carrier etc. required for proper completion of work.
Carriage of All line Material from J.E store Sub station to Pit Site ACSR Weasel conductor, ABC conductor GI Wire, Earth Wire. M.S. Chanel, Angle, Stay & Earthig Rods, Barbed Wire. Disc Insulator etc.
Carriage of LT/11kv ABC CABLE OFF SIZE 1X50, 1X95 SQMM
Carriage of T/F from ESC. BSR to pit site on kachcha pacaa road including loading and unloading chagres at both ends, rcquricd for completion of work.
25 KVA T/F
63 KVA T/F
100 KVA T/F
fixing of 11 Kv Stay rod with Stay wire in proper way with Nozelling
Grouting of 11 Kv Stay rods
Laying, sagging. Stringing and binding and jumpering of ACSR Weisal ,ABC Cable newly erected pole as per RESPO manual and as per direction of supervising engineer. It includes the cost of labour, T&P, carrier etc. requried for proper completion of work.
ACSR weisal conductor
LT/11kv AB Cable Off size
Fixing of Earthing rod
Fixing of pin insulator and pin with nut
Fixing disc insulator and disc feeting
Instolation Old/Repait T/F site as per requerd complection the cost of labour, T&P, carrier etc. requried for proper completion of work.
25 KVA T/F
63 KVA T/F
100 KVA T/F
Instolation distubition box single/3 phase for connection proper complet work.
providing & fixing 250/400 KVA T/F planth & fancing of T/F site as per requerd complection the cost of labour, T&P, carrier etc. requried for proper completion of work.
providing & fixing 250/400 KVA T/Fwater level earthing with strip & G.I. pipe, as per requerd complection the cost of labour, T&P, carrier etc. requried for proper completion of work.
The folloing material is required to be supplied by the contractor.
Holding clamp
Pcc Pole clamp
F clamp
concrete pole and stay
clamp with nut and bolt
Bolt & nut off size.
Stay clamp with nut & bolt
L.T. Insulator
NEHA ENTERPRISES
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .