| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹6.4 LAdmitted-Finance | L1 | Admitted-Finance | ||
| 2 | L2₹6.6 L+₹25,989.61 (4.09%)Admitted-Finance | L2 | Admitted-Finance | ||
| 3 | L3₹6.8 L+₹41,905.07 (6.60%)Admitted-Finance | L3 | Admitted-Finance | ||
| 4 | L4₹6.9 L+₹58,921.07 (9.27%)Admitted-Finance 785 SNEH MARRIAGE HALL KE SAMNE BASHARATPUR SHAHPUR GORAKHPUR | L4 | Admitted-Finance | ||
| 5 | L5₹7.4 L+₹1.1 L (17.1%)Admitted-Finance | L5 | Admitted-Finance |
Tender Value
₹8.5 L
EMD Value
₹84,657
Closing Date
3 Dec 2025, 12:00 pmClosed
Chief Engineer
NAGAR NIGAM AGRA
Construction work of drain and CC floor from Mata Durga Temple to Hanuman Temple on Church Road and in Vijay Singh Wali Gali under Hariparvat Zone Room No. 74.
2025_DOLBU_1092566_1
17-11-2025/NAGAR NIGAM AGRA/02-12-2025/64
Open Tender
Construction Works
Percentage
30 days
AGRA
Please refer Tender documents.
2 documents required · 2 mandatory
₹590
Nagar Nigam
₹84,657
14 Jan 2026
27 Nov 2025
3 Dec 2025
27 Nov 2025
3 Dec 2025
27 Nov 2025
E/W filling in or in embankment in ordinary soil excavation to be in the form of a regular pits not exceeding 0.50m in depth and earth work in embankment to be in 20cm layers including ramming and dressing the surface to required levels and slopes and also including 1.5m lift and 30 m lead. The earth in form of cutting (b) to be used as spoil banks within 50m distance as directed by the engineer-in-charge including royalty 9.00 cum. Including Cartage of earth up to 8 km lead.
Providing and laying cement concrete in 1:5:10 (1 Cement :5 Fine Sand :10 Stone Ballast 40 mm guages) and curing complete, including cost of form work in foundation and floors.
M-150 Brick work in 1:4 with Cement and coarse sand including supply of all material, labor T & P etc. required for proper completion of work.
Providing and laying cement concrete in 1:2:4 (1 cement : 2 coarse sand : 4 graded stone) aggregate (20 mm nominal size) and cutting complete including cost of form work. In foundation and floors.
12MM Thick cement plaster in single coat of fair side of single of half brick wall for interior plastering up to floor two level including internal rounded angles chamfers and rounded angles not including 80mm in girth and finished even and smooth. No extra for missing any additive. 1 cement : 4 Coarse Sand.
R.C.C. work with cement approved coarse sand and 2 cm (3/4) gauge approved stone ballast in the proportion 1:2:4 for slab work excluding supply of reinforcement and its bending but including its fixing and binding the same with 24 BWGI binding wire and including necessary centering and shuttering etc. and also including supply of all materials labor and tools and plants etc. required for proper completion of the work. Strength of the concrete shall not be less than M-150.
Mild Steel or iron in plain work such as reinforced concrete or reinforced brick work (When not included in and an overall rates) brought to required shape as necessary including bending for proper completion of the work and including supply of steel, its wastage bend hooks and authorized over lapping shall be measured up to floor two level. (10 mm to 12mm tor (TMT Bars).
Raising & re-fixing of manhole including all material labor T&P etc. all complete.
Supply & fixing of R.C.C. manhole frame and cover including all complete.
Supply and fixing of black granite stone board and approved standard matter with brick work, plaster & paint etc. all complete.
Add / Deduction For Estimate Figure Amount Match
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 5.01 MB
BOQ_2008841.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .