| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹14.9 LAccepted-AOC | ₹14.9 L | L1 | Accepted-AOC Low Quated |
| 2 | L2₹15.4 L+₹58,751.02 (3.95%)Rejected-AOC | ₹15.4 L+₹58,751.02 (3.95%) | L2 | Rejected-AOC Highly Quated |
| 3 | L3₹16.0 L+₹1.1 L (7.71%)Rejected-AOC | ₹16.0 L+₹1.1 L (7.71%) | L3 | Rejected-AOC Highly Quated |
| 4 | L4₹16.8 L+₹1.9 L (13.0%)Rejected-AOC | ₹16.8 L+₹1.9 L (13.0%) | L4 | Rejected-AOC Highly Quated |
| Sl No | Description | Qty | Unit | Senthamizhan L3 | P.Subramaniaswami L1 | D.Rajasekaran L4 | T.Prakash L2 |
|---|---|---|---|---|---|---|---|
| 1.00Providing Cement Concrete road (179m) With Drainage (70m) @ PHC Building in Vadakrishnapuram Panchayat. | |||||||
| 2.00 | Earth work excavation and depositing on bank with in initial lead lift in hard gravelly soil for
foundation etc. complete. | 76.58 | cum | 200 ₹15,316 | 125 ₹9,572.5 | 100 ₹7,658 | 90 ₹6,892.2 Lowest |
| 3.00 | Sand and filling in to the basement including cost and conveyance to the site and all labour charges for filling as per standard specifications | 79.71 | cum | 1,900 ₹1,51,449 | 2,175 ₹1,73,369.25 | 1,950 ₹1,55,434.5 | 1,701 ₹1,35,586.71 Lowest |
| 4.00 | Plain Cement concrete 1:4:8 mix using 40mm ISS metal including all cost and conveyance of
all materials to site and all labour charges etc complete. | 79.71 | cum | 5,200 ₹4,14,492 Lowest | 5,947 ₹4,74,035.37 | 5,750 ₹4,58,332.5 | 5,500 ₹4,38,405 |
| 5.00 | Centering charges for centering post and wooden planks including conveyance of all materials to site and proper centering etc complete. | 346.05 | Sqm | 500 ₹1,73,025 | 540 ₹1,86,867 | 540 ₹1,86,867 | 470 ₹1,62,643.5 Lowest |
| 6.00 | Cement concrete 1:3:6 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete | 36.71 | cum | 6,000 ₹2,20,260 Lowest | 6,701 ₹2,45,993.71 | 6,300 ₹2,31,273 | 6,000 ₹2,20,260 Lowest |
| 7.00 | Wearing coat Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete | 53.48 | cum | 7,000 ₹3,74,360 | 7,247 ₹3,87,569.56 | 6,950 ₹3,71,686 | 6,100 ₹3,26,228 Lowest |
| 8.00 | Provision for Tar pad including all cost and conveyance etc,complete | 36 | No | 98 ₹3,528 Lowest | 100 ₹3,600 | 200 ₹7,200 | 130 ₹4,680 |
| 9.00 | Towards Name board charges | 1 | No | 3,500 ₹3,500 | 4,500 ₹4,500 | 3,490 ₹3,490 | 3,000 ₹3,000 Lowest |
| 10.00 | GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} | 1 | GST Amount | 2,44,067.4 ₹2,44,067.4 Lowest | - | 2,55,949.38 ₹2,55,949.38 | 2,46,563 ₹2,46,563 |
Tender Value
₹17.9 L
EMD Value
₹18,000
Closing Date
1 Jul 2026, 3:00 pmClosed
BDO
Melbhuvanagiri Panchayat Union
Providing Cement Concrete road (179m) with Drainage (70m) at PHC Campus in Vadakrishnapuram Panchayat
2026_RDTN_681086_1
General Fund A3/989/2025
Open Tender
Civil Works
Item Rate
100 days
Melbhuvanagiri Panchayat Union
As per tender
3 documents required · 3 mandatory
₹0
₹18,000
21 Jul 2026
16 Jun 2026
2 Jul 2026
16 Jun 2026
1 Jul 2026
16 Jun 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Providing Cement Concrete road (179m) With Drainage (70m) @ PHC Building in Vadakrishnapuram Panchayat. | - | - | - | - |
| 2 | Earth work excavation and depositing on bank with in initial lead lift in hard gravelly soil for
foundation etc. complete. | 76.58 | cum | 263.78 | ₹20,200.27 |
| 3 | Sand and filling in to the basement including cost and conveyance to the site and all labour charges for filling as per standard specifications | 79.71 | cum | 263.78 | ₹21,025.9 |
| 4 | Plain Cement concrete 1:4:8 mix using 40mm ISS metal including all cost and conveyance of
all materials to site and all labour charges etc complete. | 79.71 | cum | 5,860.66 | ₹4,67,153.21 |
| 5 | Centering charges for centering post and wooden planks including conveyance of all materials to site and proper centering etc complete. | 346.05 | Sqm | 6,200.26 | ₹21,45,599.97 |
| 6 | Cement concrete 1:3:6 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete | 36.71 | cum | 6,293.13 | ₹2,31,020.8 |
| 7 | Wearing coat Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete | 53.48 | cum | 1,095 | ₹58,560.6 |
| 8 | Provision for Tar pad including all cost and conveyance etc,complete | 36 | No | 9,605.53 | ₹3,45,799.08 |
| 9 | Towards Name board charges | 1 | No | 4,500 | ₹4,500 |
| 10 | GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} | 1 | GST Amount | - | - |
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.33 MB
Vadakrishnapuram.pdf
Tender Documents • 0.49 MB
BOQ_818482.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .