Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹22.8 LAccepted-AOC | ₹22.8 L | L1 | Accepted-AOC LOWEST RATE QUOTED |
| 2 | L2₹22.8 LRejected-AOC | ₹22.8 L | L2 | Rejected-AOC HIGHER RATE |
| 3 | L3₹29.9 LRejected-AOC | ₹29.9 L | L3 | Rejected-AOC HIGHER RATE |
| 4 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
| 5 | Not Admitted-Fee/PreQual/Technical ODHAN | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹28.4 L
EMD Value
₹56,880
Closing Date
5 Jan 2026, 11:00 amClosed
RAKESH
Municipal Council Mandi Dabwali
Const. of IPB street Pammi Bhai to House of Nihal Singh wali gali, In Front of Sharvan house to ParhaLad home at chouhan Nagar ward 20in MC Dabwali
2025_HRY_491397_1
20259ACA3F41 37C0 4312 B8BF FD72ABD4D8D9280ULB
Open Tender
Civil Works
90 days
Mandi Dabwali
Const. of IPB street Pammi Bhai to House of Nihal Singh wali gali, In Front of Sharvan house to ParhaLad home at chouhan Nagar ward 20in MC Dabwali
2 documents required · 2 mandatory
₹1,000
₹56,880
Yes
22 Jan 2026
18 Dec 2025
5 Jan 2026
18 Dec 2025
5 Jan 2026
18 Dec 2025
18 Dec 2025 - 19 Dec 2025
[10.100.2]Cement Concrete 1:8:16 Flooring 2. Cement Concrete 1:8:16 with stone aggregate 40 mm size in foundation and plinth. [Through Rate]
[11.5.3]12 mm cement plaster of mix : 3. 1:4 (1 cement: 4 fine sand) [Through Rate]
[14.1]Dressing bed and preparation of sub grade for lining by mechanical/ mannual means [Through Rate]
[17.22.2]Water Bound Macadam Gr I 2. Water Bound Macadam Grading I with screening Type A Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with 3 wheeled steel/ vibratory roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density complete as per technical clause 404 of MORT&H specifications [Through Rate]
[17.69.3]Interlocking Concrete Block Pavement 3. Providing and Laying 60 mm thick ISI marked Interlocking Paver Blocks conforming to IS 15658:2006/IRC SP 63: 2004 of all shapes and colours in design mix cement M 35 over the bed of 25 mm thick fine sand complete in all respect. [Through Rate]
[2.B0241] B0241. 100 mm dia PVC pipe [Rate]
[20.62.1]Providing, lowering, laying, cutting (cut surface to be uniformly finished), jointing with rubber rings marked with IS : 5382 and testing of SPIGOT AND SOCKETTED RCC, NP2 MARKED WITH IS : 458-1988 and specials into trenches for all depths including carriage, loading, unloading, stacking, handling, re-handling etc. complete is all respects to the satisfaction to the Engineer - in -charge. 1. 200 mm i/d [Through Rate]
[21.28]Providing and fixing steel bar embedded plastic steps of size 263mm x 165mm of orange colour, confirming to specification in pump chambers, manholes etc., having minimum 3mm thick polypropylene polymer confirming to is:10910 encapsulated on 12mm dia ribbed steel bars per IS :1786. The rate include cost of setting the same to correct lines and levels duly embedded in 1:2:4 cement concrete including carriage, loading, uploading, stacking, handling, re-handling etc., complete in all respect to the satisfaction of Engineer-in-charge [Through Rate]
[21.93.1]Providing and fixing SFRC MANHOLE COVERS AND FRAMES MARKED WITH IS: 12592 including setting the same to correct lines and levels in 1:3 cement sand mortar over manhole including carriage loading unloading stacking handling re-handling etc. complete in all respects to the satisfaction to the Engineer-in-charge. 1. Type:- Extra Heavy Duty Set (EHD-35) 560MM Clear Opening [Through Rate]
[3.1.2]By Mechanical Transport including loading, unloading and stacking 2. Earth [5km]
[4.14.1]Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. 1. All kinds of soil. [Through Rate]
[4.16.1.2]Excavating trenches of required width and depth for pipes, cables, etc including excavation for sockets, and dressing of sides, ramming of bottoms, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20 cm in depth, including consolidating each deposited layer by ramming, watering, etc. and disposing of surplus excavated soil as directed, within a lead of 50 m. 1.2. All kind of soil Pipes, cables etc, exceeding 80 mm dia but not exceeding 300 mm dia. [Through Rate]
[6.1.2]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 2. 1:2:4 (1 cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size) [Through Rate]
[6.14.1]Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1. 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size) [Through Rate]
[6.30.3]Centering and shuttering including strutting, propping etc. and removal of form for 3. Suspended floors, roofs, landings, balconies and access platform [Through Rate]
[6.33.3]Steel reinforcement for R.C.C. work, where not included in the complete rate of RCC, including straightening, cutting, bending, placing in position, binding, wastage, overlaps, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire etc. complete in all respect below plinth level Note: Reinforcement shall be measured in length including hooks, if any, separately for different diameters as actually used in work , excluding overlaps. Wastage, overlaps, couplings, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire or other methods of binding & placing shall not be measured and cost of these items shall be deemed to be included in the rates for reinforcement. 3. Cold twisted bars [Through Rate]
[7.21.1]Brick work with common burnt clay non-modular bricks of class designation 10.5 in foundation and plinth in: 1. Cement mortar 1:4 (1 cement : 4 coarse sand) [Through Rate]
[7.21.2]Brick work with common burnt clay non-modular bricks of class designation 10.5 in foundation and plinth in: 2. Cement mortar 1:6 (1 cement : 6 coarse sand) [Through Rate]
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.74 MB
BOQ_569718.xls
BOQ • 0.26 MB
Download all tender documents and submit your bid