| 1 | L1₹3.7 LAccepted-AOC | L1 | Accepted-AOC LOWEST | |
| 2 | L2₹4.0 L+₹28,355.60 (7.61%)Rejected-Finance | L2 | Rejected-Finance L2 |
Tender Value
₹5.0 L
EMD Value
₹15,000
Closing Date
10 Oct 2023, 3:00 pmClosed
Divisional Forest Officer, Diglipur
O/o the Divisional Forest Officer, Diglipur
Construction of RCC retaining wall, 02.00 mtr height for a length of 09.50 mtr backside of qtr at Navin Nagar, Diglipur
2023_DFODP_11712_2
DFO/DP/2024/06
Open Tender
Civil Works - Others
Works
60 days
Navin Nagar
Please refer Tender documents.
7 documents required · 7 mandatory
₹0
₹15,000
Yes
2 Nov 2023
3 Oct 2023
10 Oct 2023
3 Oct 2023
10 Oct 2023
3 Oct 2023
Amount
Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.
All kinds of soil.
Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m.
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :
1:4:8 (1 Cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size)
Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level :
1:2:4 (1 cement : 2 coarse sand (zone-III): 4 graded stone aggregate 20 mm nominal size).
Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement :
1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size).
Centering and shuttering including strutting, propping etc. and removal of form for all heights :
Foundations, footings, bases of columns, etc. for mass concrete
Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.
Thermo-Mechanically Treated bars of grade Fe-500D or more.
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete above plinth level.
Thermo-Mechanically Treated bars of grade Fe-500 D or more.
VISHAL GORAI
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .