| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹4.7 CrAdmitted-Finance | -22.00% | ₹4.7 Cr | L1 | Admitted-Finance |
| 2 | L2₹4.7 CrAdmitted-Finance | -21.66% | ₹4.7 Cr | L2 | Admitted-Finance |
| 3 | L3₹7.6 CrAdmitted-Finance | +26.89% | ₹7.6 Cr | L3 | Admitted-Finance |
Tender Value
₹6.0 Cr
EMD Value
₹12.0 L
Closing Date
5 May 2026, 3:00 pmClosed
Executive Engineer (CD-VII)
Civil Division VII IFCD Rohini Office Complex Sector 15 Rohini Delhi.
Restoration of RCC Drain and Road from Railway Crossing in Khera Kalan to Nahar (DTD Canal) at Khera Kalan in Distt. North.
2026_IFC_290533_1
EE/CD-VII/NIT/2025-26/34 (2nd Call)
Open Tender
Civil Works
240 days
Civil Division VII IFCD Rohini Office Complex Sect
Please refer Tender documents.
8 documents required · 8 mandatory
₹0
₹12.0 L
7 May 2026
29 Apr 2026
5 May 2026
29 Apr 2026
5 May 2026
29 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix) | 304 | Cum | 1,064.75 | ₹3,23,684 |
| 2 | Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge.In cement mortar | 105 | Cum | 899.98 | ₹94,497.9 |
| 3 | Dismantling manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge : bituminous road | 7,050 | Sqm | 189.02 | ₹13,32,591 |
| 4 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil. | 3,102 | Cum | 177.7 | ₹5,51,225.4 |
| 5 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:4:8 (1 Cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size) | 282 | Cum | 4,782.22 | ₹13,48,586.04 |
| 6 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. | 5,625 | Cum | 134.29 | ₹7,55,381.25 |
| 7.1 | Centering and shuttering including strutting, propping etc. and removal of form for all heights :Foundations, footings, bases of columns, etc. for mass concrete | 470 | Sqm | 207.12 | ₹97,346.4 |
| 7.2 | Centering and shuttering including strutting, propping etc. and removal of form for all heights :Lintels, beams, plinth beams, girders, bressumers and cantilevers | 1,876 | Sqm | 366.18 | ₹6,86,953.68 |
| 7.3 | Centering and shuttering including strutting, propping etc. and removalof form for all heights :Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc. | 8,460 | Sqm | 404.31 | ₹34,20,462.6 |
| 8 | Providing and laying in position ready mixed M-25 grade concrete for reinforced cement concrete work, using cement content as per approved design mix, manufactured in fully automatic batching plant and transported to site of work in transit mixer for all leads, having continuous agitated mixer, manufactured as per mix design of specified grade for reinforced cement concrete work, including pumping of R.M.C. from transit mixer to site of laying , excluding the cost of centering, shuttering finishing and reinforcement, including cost of admixtures in recommended proportions as per IS : 9103 to accelerate/ retard setting of concrete,improve workability without impairing strength and durability as per direction of the Engineer-in-charge.(Note :- Cement content considered in this item is @ 330 kg/cum. Excess/less cement used as per design mix is payable/recoverableseparately) All works upto plinth level | 1,706 | Cum | 7,169.46 | ₹1,22,31,098.76 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.78 MB
BOQ_385587.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid