| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.2 CrAccepted-AOC | ₹1.2 Cr | L1 | Accepted-AOC Quoted Lowest rate and Executed Agreement on 02.08.2023 after negotiation |
| 2 | L2₹1.2 Cr+₹1.5 L (1.32%)Rejected-AOC | ₹1.2 Cr+₹1.5 L (1.32%) | L2 | Rejected-AOC L2 |
Tender Value
₹1.3 Cr
EMD Value
₹1.3 L
Closing Date
3 Jul 2023, 3:00 pmClosed
Additional Collector (Dev),DRDA,Thoothukudi
O/O AC (D) / PD DRDA Thoothukudi
Thoothukudi District-MGSMT 25 percentage Component- 2022-23- Upgradation/ Strengthening/ Renewal of 1 No of Rural Roads in Kayathar Block Package No.TN/TUT-11/ MGSMT- 2022-23
2023_RDTN_330600_16
CRDPRChennaiLr.No. DIPR/3113/Tender/23 dt.18.06.23
Open Tender
Civil Works - Roads
Item Rate
180 days
Thoothukudi District
As per Tender Schedule
4 documents required · 4 mandatory
₹0
₹1.3 L
O/O AC (D) / PD DRDA Thoothukudi
7 Sept 2023
28 Jun 2023
3 Jul 2023
28 Jun 2023
3 Jul 2023
28 Jun 2023
28 Jun 2023
Amount
Upgradation of Kappulingampatti - Kumaragiri Road Km 0/0- 2/270 (R252) VPR
Clearing the Scrub jungle including all labour charges for burrying and burning etc., Km 0/0- 2/270
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20A Km 0/0- 2/270
Providing and Laying Red Gravel side berms including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction at optimum moisture content and hire & fuel charges for power roller , water sprinkler and all other incidental charges such as traffic barricading and providing danger lights etc, complete.
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. Km 0/0- 2/270
Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it. Km 0/0- 2/270
Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10Square Meter for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., Km 0/0- 2/270
Providing and laying Bituminious concrete using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Provision for KM Stone (1.65 x 0.45 x 0.15 m)
Provision for HM Stone (0.75 x 0.23 x 0.10 m)
Providing and laying of hot applied Thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35. The finished surface to be level, uniform and free from streaks and holes etc complete as per MORT&H specification No.803 Km0/0-0/470
Construction of 6 m culvert at ch 2/175
Earth work excavation in all clauses of soils with initial lead and lift except hard rock requiring blasting etc., complete for foundation as per SS 20B
Cement concrete 1:4:8 mix using 40mm ISS HBG metal including all cost and conveyance and all labour charges etc., complete
Cement concrete 1:3:6mix using 40 mm ISS HBG metal including all cost and conveyance and all labour charges etc., complete
Centering charges for PCC works including all cost and conveyance all materials to site etc., complete.
Below Sill Level
Above Sill Level
Reinforced cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete.
Supplying, fabricating and placing steel in position including cost and conveyance of materials and all labour charges
Providing and fixing Bitumen belt for Expansion joint between dirt wall and deck
Providing and fixing Tar paper for bearing between Bed Block and Deck slab
Providing weepholes in brick/stone masonry, Plain/Reinforced concrete, abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V) : 20(H) towards drawing face complete as per drawing and technical specification clauses 614,709, 1204.3.7
Gravel filling between body wall including cost and conveyance of gravel, labour for filling, watering and compacting etc complete complying with standard specification and as directed by the departmental officer
Construction of 2 m span RCC culvert at ch 2/265
Earth work excavation in all classes of soils except hard rock requiring blasting and depositing on bank with intial lead and lifts and all other incidental charges such as shoring, strutting, baling out water, forming protective bunds, coffer dam wherever necessary for dressing the bed below sill level etc., complete for foundation. As per SS20B
CC 1:4:8 mix using 40 mm metal including cost and conveyance of materials and all labour charges etc complete
CC 1:3:6 mix using 40 mm metal including cost and conveyance of materials and all labour charges etc complete
CC 1:2:4 mix using 20 mm metal including cost and conveyance of materials and all labour charges etc complete
Supply and fabrication of Steel Grade S-415/Steel Grade S-240 required for all RCC items of works involved in the schedule including cost of steel which will be procured by the contractor by his own arrangement, cost of fabrication, labour charges for cleaning the bars straightening, cutting, bending, tying grills, hoisting and placing the reinforcement in position as specified in the drawings including cost of binding wire, provision of space bars, cover blocks and all other incidental charges etc., complete as per standard specification
Supplying and erecting centering for sides and soffits including cost and conveyance of materials and all labour charges etc complete
Below Sill Level - Without Struttings
Above Sill Level - With Struttings
RCC 1:1.5:3 mix using 20 mm metal including cost and conveyance of materials and all labour charges etc complete
Provision for CIB cum Name Board
Provision for Sign board
Provision for 60 cm circle mandatory board
Towards the charges for routine maintenance of the road work executed under Bharat Nirman including dressing of bermsby refilling the gully with form berms, desilting of side drains and CD works , Whitewashing guardstones, painting of KM & HM stones,Parapets, cutting of breaches of trees, refixing displaced guard stones , caution boards, speed limit boards etc with the periodiocity for the above actitvities as prescribed in IRC SP 20-2002 and as directed by the departmental officers except for the constructional defects which has to be rectiufied by the contractor at his own cost.
First Year
Second Year
Third Year
Fourth Year
Fifth Year
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
RSR INFRA DEVELOPERS PRIVATE LIMITED
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .